8.3 Form Ties, Walers, Bracing & Pre-Pour Cleanliness

Key Takeaways

  • In a tied wall form, the facing and framing transfer fresh concrete pressure into the ties. Verify the actual load path and bracing in the approved formwork plan.

  • For ferrous ties in ACI 301-20 SF-2 or SF-3 surfaces, the default breakback is at least 3/4 inch. Check any specified coating or integral water barrier.

  • Use the ACI 347R-14 pressure case that matches slump, vibration depth, member geometry, placement method and rate.

  • ACI 301-20 requires temporary openings where needed for cleaning and inspection. Check the contact surface and secure closure before placing concrete.

Last updated: November 2026

Form Ties, Walers, Bracing & Pre-Pour Cleanliness

Wall and column forms need a load path for fresh concrete pressure and construction loads. Read the approved formwork plan before checking the installed system. Compare member marks, spacing, connections and support with the design assumptions. ACI 318-19 Section 26.11.1.2 covers placement loads, tightness and the bracing or ties that maintain position and shape.

1. Trace the pressure load path

ComponentWhat it does
FacingShapes the surface and carries fresh concrete pressure into the supporting framing.
Studs and walersSupport the facing and distribute loads to ties or other supports as designed.
StrongbacksStiffen and align the framing where the formwork design uses them.
TiesConnect opposing form faces and resist separation in a tied system.
External braces and anchorsHold alignment and resist the loads shown in the formwork design. A one-sided form may rely on exterior supports for concrete pressure.

Snap ties leave an embedded portion after the removable ends are broken off. She-bolt systems use removable outer bolts with an inner tie, and taper ties are withdrawn from the formed wall. Use the approved system’s instructions for removal and treatment of the resulting opening. Where specified, ACI 301-20 Section 2.2.1.2 calls for ties with integral water barrier plates or another acceptable positive barrier. Check the tie detail and placement for that wall.

Under the unmodified ACI 301-20 Section 2.2.1.2 default, ferrous ties in SF-2 and SF-3 finishes have a breakback of at least 3/4 inch. Use coated or corrosion-resistant ties when specified or if the specified breakback is less than 3/4 inch. Sections 2.3.2.7 and 5.3.7.2 address tie-hole treatment. Check the finish and patching requirements. For the specified portland-cement repair mortar, clean and dampen the holes. Use accepted alternatives in accordance with the applicable instructions.

2. Choose the lateral pressure case

In ACI 347R-14 Section 4.2.2.1a, the inch-pound full liquid head at a point is whwh, where ww is the concrete unit weight in lb/ft³ and hh is the depth in feet of fluid or plastic concrete above the point. For w=150w=150 lb/ft³, a 10-ft head produces 1,500 psf and a 20-ft head produces 3,000 psf. Use the unit weight assumed in the design for the actual mixture.

For conventional concrete, use Table 4.2.2.1a(a) to choose the equation. Measure slump for this purpose after admixtures are added. For the table only, a column has no plan dimension exceeding 6.5 ft, and a wall has at least one exceeding 6.5 ft.

Placement conditionInch-pound equation
Slump greater than 7 in. or internal vibration deeper than 4 ft(a), full liquid head
Slump at most 7 in. and vibration at most 4 ft, with a column or a wall at most 14 ft tall placed below 7 ft/h(b)
Same slump and vibration limits, with a wall taller than 14 ft placed below 7 ft/h, or any wall placed at 7 through 15 ft/h(c)
Wall placed faster than 15 ft/h(a), full liquid head

For equations (b) and (c), use concrete temperature TT in °F, placement rate RR in ft/h, and chemistry and unit-weight coefficients CcC_c and CwC_w from their tables.

pb=CcCw(150+9000RT)p_b=C_cC_w\left(150+\frac{9000R}{T}\right) pc=CcCw(150+43400T+2800RT)p_c=C_cC_w\left(150+\frac{43400}{T}+\frac{2800R}{T}\right)

For these equations, apply the minimum 600Cw600C_w psf, subject to the upper limit whwh. This upper limit applies to these equations. A separate base-pumped case can exceed the full liquid head. Section 4.2.2.2 recommends full head for self-consolidating concrete unless its effect on form pressure is understood through measurements or previous studies and experience. Section 4.2.2.4 recommends full head plus at least a 25% surge allowance for concrete pumped in at the base. The 4-ft internal vibration criterion used for pressure selection is distinct from the ACI 309R-05 guidance on penetrating into a previous plastic layer.

Worked example: Compare placement rates

A 12-ft conventional wall form uses 150 lb/ft³ concrete at 60°F. Slump is 6 inches, internal vibration depth is 3 ft, and assume Cc=Cw=1.0C_c=C_w=1.0. At a rate of 6 ft/h, use (b). The calculation is 150+9000(6)/60=1050150+9000(6)/60=1050 psf, between 600 and 150(12)=1800150(12)=1800 psf. At 10 ft/h, use (c), which gives 150+43400/60+2800(10)/60=1340150+43400/60+2800(10)/60=1340 psf. At 16 ft/h, use full head, 1,800 psf. If the design specifies a 6-ft/h limit, observe and report an actual rate above that limit even when the concrete remains visually stable. Refer changes to the responsible parties under the approved procedure.

3. Check cleanout access and closure

ACI 301-20 Section 2.2.2.6 requires temporary openings where needed for cleaning and inspection. Locate them from the form plan or accepted procedure so concealed areas can be checked. Before placement, verify removal of debris and standing water, a sound and prepared joint where applicable, and secure closure of the access openings. Compare closure, tie and bracing details with the approved plan and report deviations. A clean form and correct dimensions are separate observations.

Test Your Knowledge

Under the unmodified ACI 301-20 Section 2.2.1.2 default, what breakback is required for ferrous form ties in an SF-2 finish?

A

Flush with the surface

B

1/4 inch

C

At least 3/4 inch

D

At least 1-1/2 inches

Test Your Knowledge

A 12-ft conventional wall uses 150 lb/ft³ concrete, 6-inch slump and 3-ft internal vibration depth. It is placed at 16 ft/h. Under ACI 347R-14 Table 4.2.2.1a(a), what is the full-head pressure at its base?

A

600 psf

B

1,050 psf

C

1,340 psf

D

1,800 psf

Test Your Knowledge

Why does ACI 301-20 Section 2.2.2.6 require temporary formwork openings where needed?

A

To permit access for cleaning and inspection before placement

B

To drain bleed water during placement

C

To replace the specified form ties

D

To remove the need to close the form before placement

Sections you finish are checked off in the contents.