1.3 Construction Documents & Submittal Requirements

Key Takeaways

  • Under IPC 106.1, construction documents are submitted in two or more sets or digitally, drawn to scale, and prepared by a registered design professional where state law requires.

  • For buildings over two stories, IPC 106.1 requires documents to show pipe penetrations and how structural safety, fire-resistance ratings and fireblocking are maintained.

  • WSFU load values come from IPC Appendix E Table E103.3(2); Table 604.3 gives required flow rate and pressure at fixture outlets, not WSFU.

  • IPC 307.2 defers wood cutting to IBC 2308, which prohibits notches in the middle third of a joist span and limits bored holes to one-third of joist depth.

  • IPC 105.5.1 allows a permit for part of a system at the holder's own risk; the IPC has no deferred-submittal procedure like IBC 107.3.4.1.

Last updated: October 2026

Construction Documents & Submittal Requirements

The construction document review is the primary checkpoint where noncompliant designs, undersized distribution lines, improper venting configurations, and dangerous structural interferences are caught before construction begins. In the 2024 IPC, Section 106 governs construction documents, and Section 105.5 governs permit issuance, the "APPROVED" stamp and changes to approved documents. A thorough plans examiner must verify not only the hydraulic sizing of pipes and fixtures, but also the physical and structural coordination of plumbing assemblies within the building envelope.


What IPC 106.1 Requires of Construction Documents

Under IPC 106.1, construction documents, engineering calculations, diagrams and other data are submitted in two or more sets, or in a digital format where the code official allows, with each permit application. The code official requires the documents to be prepared by a registered design professional (RDP) where state law requires it. Documents must be drawn to scale and be clear enough to show the location, nature and extent of the work and to demonstrate in detail that it conforms to the code. For buildings more than two stories in height, the documents must show where pipes, fittings and components penetrate the structure and the materials and methods used to maintain structural safety, fire-resistance ratings and fireblocking. The code official may waive submission where review is not necessary to determine compliance.

IPC 106.1 sets the performance standard; each jurisdiction publishes its own checklist. In practice, a complete commercial plumbing submittal usually contains the following components:

1. Site Utility Plan

  • Exact location of the public water main, sanitary sewer main, and storm sewer main
  • Point of connection for the water service pipe and building sewer
  • Invert elevations of the public sewer main, property line cleanout, and building drain exit
  • Separation between the water service and the building sewer under IPC 603.2: a shared trench is allowed only where the sewer is a Table 702.2 material; otherwise 5 feet of undisturbed or compacted earth, a sleeve extending 5 feet each side of a crossing, or the bottom of the water pipe at least 12 inches above the top of the sewer within 5 feet
  • Water meter location, vault details, and service entrance backflow containment assembly

2. Architectural Floor Plans with Plumbing Layouts

  • Scaled locations of all plumbing fixtures, equipment, and appliances (floor plans are commonly drawn at 1/8 inch = 1 foot, with enlarged restroom plans at a larger scale)
  • Floor drain and cleanout locations with directional flow arrows
  • Clear floor space and dimensional clearances for accessible fixtures compliant with ICC A117.1
  • Cold water, hot water, and hot water recirculation piping layouts
  • Sanitary drainage piping runs, pipe sizes, and minimum specified slopes

3. Isometric Riser Diagrams (DWV & Water Distribution)

While two-dimensional schematic diagrams show logical connections, three-dimensional isometric riser diagrams are indispensable for commercial plan review. Isometrics provide accurate visual confirmation of:

  • Vertical stack routing and offsets (45-degree vs 90-degree offsets)
  • Branch interval connections and vertical drop between fixtures
  • Developed lengths of fixture drains and vent piping
  • Vent rises and connections (dry vents rise at least 6 inches above the flood level rim of the highest trap vented, IPC 905.4; connections to a vent stack and horizontal branch, relief or loop vents at least 6 inches above the flood level rim of the highest fixture served, IPC 905.5)
  • Stack vent and vent stack terminations through the roof
           Sample Commercial DWV Riser Detail (Isometric View)

                      Vent Through Roof (VTR)
                               │ [Height set by jurisdiction, IPC 903.1.1]
                               ▲
                               │
       Stack Vent ─────────────┤
                               │
                       ┌───────┴───────┐
                       │               │
             Lavatory  O [1 DFU]       │ [2" Common Vent]
             WC (Flush)O [4 DFU]       │
                       └───────┬───────┘
                               │ [3" Soil Stack]
                               │
       Floor 2                 ├─────────────────────────┐
                               │                         │
                               │                  Sink   O [2 DFU]
                               │                  FD     O [2 DFU]
                               │                         │
                               ├─────────────────────────┘
                               │
       Floor 1                 │
                               │ [4" Soil Stack at Base]
                               ▼
                      (CO) ────┴──────── Building Drain (Min 1/8" per ft slope)

4. Fixture Schedules & Unit Load Calculations

  • Comprehensive fixture schedule listing each fixture type, model, flow rate, and consumption (not exceeding the maximums in IPC Table 604.4)
  • Required flow rate and flow pressure at each fixture outlet (IPC Table 604.3) and minimum fixture supply sizes (IPC Table 604.5)
  • Tabulation of Water Supply Fixture Units (WSFU), separated into cold, hot, and total loads, using the load values in IPC Appendix E Table E103.3(2) or another approved engineering method (IPC 604.1)
  • Conversion of WSFU to peak gallons per minute (GPM) using the Hunter-based demand table, Appendix E Table E103.3(3), for predominantly flush-tank versus predominantly flushometer-valve systems
  • Tabulation of Drainage Fixture Units (DFU) per IPC Table 709.1 and 709.2
  • Building drain and sewer sizing calculations demonstrating compliance with IPC Table 710.1(1)

5. Storm Drainage Calculations

  • Horizontal projected roof area in square feet
  • Local 100-year, 1-hour rainfall rate (inches per hour) from IPC Figures 1106.1(1) through 1106.1(5) or approved local weather data (IPC 1106.1)
  • Vertical wall allowances (IPC 1106.4: add one-half of the area of any vertical wall that diverts rainwater onto the roof)
  • Flow calculations (gpm) for primary roof drains, vertical leaders, and storm drains checked against IPC Tables 1106.2, 1106.3 and 1106.6
  • Secondary (emergency overflow) drains or scuppers sized under IPC 1108.3, with an end point of discharge separate from the primary system (IPC 1108.2)

Structural and Architectural Coordination (Cross-Code Verification)

Plumbing piping must pass through floors, bearing walls, and ceilings. Failure to coordinate plumbing routes with structural framing can severely compromise building integrity. Plans examiners must verify compliance with IPC Section 307 and structural building codes (IBC Chapter 23 for wood, Chapter 22 for steel).

Wood Framing Notching and Boring Rules (IPC 307.2, which defers to IBC Section 2308)

Framing MemberMaximum Bored Hole SizeMaximum Edge NotchCritical Location Restrictions
Floor Joists1/3 of joist depth1/6 of joist depth (outer thirds only)NO NOTCHING in the middle third of the joist span. End notches limited to 1/4 joist depth. Holes must be at least 2 inches from top/bottom edges and other holes.
Exterior & Bearing Studs40% of stud width (60% only where the stud is doubled and not more than two successive doubled studs are bored)25% of stud widthHole edge at least 5/8 inch from the stud edge; a hole may not be in the same section of stud as a cut or notch.
Nonbearing Studs60% of stud width40% of stud widthHole edge at least 5/8 inch from the stud edge.

Example Calculation: In a nominal 2x10 wood floor joist (actual depth = 9.25 inches):

  • Maximum bored hole diameter = 9.25/3=3.089.25 / 3 = 3.08 inches. A 3-inch DWV pipe (outside diameter ~3.5 inches) CANNOT pass through a single 2x10 joist without violating the 1/3 depth limit!
  • Minimum distance from top and bottom edge of the joist to hole edge = 2.0 inches.
  • Maximum notch depth in outer third of span = 9.25/6=1.549.25 / 6 = 1.54 inches.

Cold-Formed Steel Framing (IPC 307.3 & 305.1)

IPC 307.3 requires cutting and notching of cold-formed steel framing to follow AISI S240 for structural members and AISI S220 for nonstructural members, so pipes normally pass through factory punch-outs or engineered web openings. Separately, IPC 305.1 prohibits metallic piping (other than cast iron, ductile iron and galvanized steel) from direct contact with steel framing members. Where sheathing is used to prevent contact, it must be plastic at least 0.008 inch (8 mil) thick, which is why grommets or isolators appear on the drawings.

Fire-Resistance Rated Assemblies (IPC 307.4 → IBC Section 714; IPC 315.1)

Piping penetrating fire-rated walls, floors, or smoke barriers creates pathways for flame and toxic gases. IPC 307.4 requires such penetrations to be protected under the IBC, and IPC 315.1 requires annular spaces at building-envelope penetrations to be sealed in an approved manner. Plans examiners verify that the construction documents detail listed through-penetration firestop systems tested under ASTM E814 or UL 1479:

  • F-Rating: The time period (in hours) that the firestop system prevents flame passage through the penetration (must equal or exceed the rating of the assembly).
  • T-Rating: The time period before the temperature on the unexposed surface rises 325°F above its initial temperature (required for most floor penetrations; IBC 714 lists exceptions such as penetrations contained within a wall cavity).
  • Combustible Piping (PVC/ABS): Requires approved intumescent firestop collars or wrap strips that expand under heat to crush the melting pipe and seal the annular space.

Administrative Plan Review Workflow & Correction Protocols

The plan examination process follows a structured administrative pipeline:

  1. Completeness Screening (Intake): Verifying required design professional seals, application forms, code edition references, and inclusion of all discipline sheets.
  2. Substantive Technical Plan Check: Verification of hydraulic loads, slopes, clearances, accessibility, structural coordination, and backflow protection.
  3. Plan Check Correction Letters: If deficiencies are identified, the examiner issues a formal correction letter. Every comment must cite the specific code section violated (e.g., "IPC 704.1: Slope of 3-inch horizontal branch drain serving restrooms 201 and 202 is indicated as 1/16 in/ft; minimum required slope is 1/8 in/ft"), state the technical deficiency clearly, and indicate required corrective action.
  4. Partial Permits (IPC 105.5.1): The IPC does not use the IBC's "deferred submittal" procedure (IBC 107.3.4.1). Instead, IPC 105.5.1 lets the code official issue a permit for part of a plumbing system before the documents for the whole system are submitted or approved, provided adequate information and detailed statements have been filed. The permit holder proceeds at their own risk, without assurance that the permit for the entire system will be granted.
  5. Approved Plan Stamping: When the permit is issued, the construction documents are endorsed in writing and stamped "APPROVED" (IPC 105.5.1). Approved documents may not be changed, modified or altered without the code official's authorization, and work must follow them. Under IPC 106.2, the code official retains one approved set for at least 180 days after completion of the work (or longer where state or local law requires), and one set is returned to the applicant and kept on the site while the work is in progress. Approval never authorizes a code violation, and the code official may later require correction of errors (IPC 105.5.2).
Test Your Knowledge

During the review of a multi-story wood-framed commercial building, the plumbing drawings show a 3-inch horizontal waste branch notched into the bottom edge of a 2x10 wood floor joist (actual depth 9.25 inches) within the middle third of the joist span. How must the plans examiner rule on this detail?

A

Approved, provided the notch depth does not exceed one-sixth of the joist depth

B

Disapproved, because notching of joists within the middle third of the span is strictly prohibited by code

C

Disapproved, because horizontal waste branches larger than 2 inches cannot pass through wood joists under any condition

D

Approved, provided an engineered steel strap is nailed across the bottom of the notched joist

Test Your Knowledge

A plumbing submittal for a large medical office building is complete except for the medical gas and process-piping layouts, which the owner wants to submit later. Under IPC Section 105.5.1, what may the code official do?

A

Approve the missing layouts automatically if the design professional seals the cover sheet

B

Issue a permit for the completed portion, with the holder proceeding at their own risk

C

Issue a full permit and review the missing layouts only at the final inspection

D

Refuse any permit until the board of appeals grants a variance for the incomplete submittal

Test Your Knowledge

Which of the following sets of drawings and calculations is mandatory on a complete commercial plumbing plan submittal to enable the plans examiner to verify code-compliant drainage and venting hydraulics?

A

Riser diagrams or isometrics showing pipe sizes, developed lengths, fixture units and vent terminations

B

Architectural site renderings showing exterior utility trench aesthetic alignments without invert elevations

C

Electrical panel load schedules and lighting reflected ceiling plans

D

Cut sheets of finish plumbing trim and fixture manufacturer marketing brochures only

Sections you finish are checked off in the contents.