11.2 Procurement Methods, Tender Planning and Bid Security
Key Takeaways
Section 35 makes competitive tendering the starting point for goods, works or services, subject to the Act’s exceptions. Consultant selection has its own rules.
Under sections 42–43, compare quotations from at least three unrelated sources and select the lowest evaluated responsive quotation.
Use restricted tendering or single-source procurement only on an applicable statutory ground with prior PPA Board approval.
Section 21(3) governs submission of the following year’s procurement plan. Section 21(4) governs updates after budget approval and at quarterly intervals.
Section 55 regulates tender security where required. Regulation 52 of L.I. 2466 distinguishes permissible forms, the limit for a fixed amount, and methods where security is prohibited.
Start With the Requirement
Under section 35 of Act 663 as amended, competitive tendering is the starting point for goods, works and services, subject to statutory exceptions. Quality- and cost-based selection is the starting point for consultants, subject to section 35(2) and Part Six. Classify the requirement, check the method thresholds under L.I. 2516 and separately check the approving authority in section 11.1.
For national competitive tendering, regulation 41 of L.I. 2466 requires publication in at least one daily newspaper of national circulation and on the PPA website. Section 44 allows locally registered bidders to participate without regard to nationality unless the entity lawfully limits participation to domestic bidders and records its reasons. Section 45 requires international competitive tendering when effective competition in an open tender requires inviting foreign firms. When tendering internationally, section 53(1)(b) allows bidders at least six weeks to prepare tenders. Apply the published evaluation criteria under section 20E and regulations 16–18.
Request for Quotations
For a standard, readily available requirement that meets section 42 and the value limits, solicit quotations from as many suppliers or contractors as practicable. Under section 43, compare at least three sources unrelated by ownership, shareholding or directorship.
- Tell bidders which transport, duties and other charges to include so prices are comparable.
- A supplier submits one quotation and may not change it.
- The award goes to the lowest evaluated responsive quotation that meets the entity's needs.
Read both the operative provision and the schedule if a value is exactly at the goods ceiling. Section 42(1)(b) uses a strict less-than test for the stated goods case, while the Fifth Schedule labels its quotation band as inclusive.
Suppose a school needs standard stationery and receives three otherwise comparable quotes, but two suppliers have the same directors. Those three submissions provide only two independent sources. Seek another qualifying independent source and document the evaluation. Compare the disclosed delivery costs and the specifications as well as the headline prices.
Restricted Tendering and Single-Source Procurement
Sections 38–39 allow restricted tendering, with prior PPA Board approval, for highly specialised requirements with few suppliers, disproportionate evaluation costs or a published competitive invitation receiving no response. The third ground concerns the absence of a response. Use the statutory invitation procedure and select suppliers without discrimination to preserve effective competition. Section 39 also requires an award notice.
Sections 40–41 permit single-source procurement with PPA Board approval in specified cases. Examples include an exclusive supplier when no reasonable substitute exists, qualifying unforeseen urgency, and compatibility with existing equipment after assessing alternatives, scope and price. Section 40 distinguishes an unforeseeable urgency free of dilatory conduct from catastrophic urgency that makes other methods impractical. A late start to a predictable purchase does not establish the former ground. When a laboratory needs proprietary parts, establish the lack of a reasonable substitute and document why any proposed additional supply meets the relevant ground. If applying an exceptional route, check commitment authorisation under section 24A as well as the method approval.
Submit and Update the Procurement Plan
Section 21(2) specifies the plan contents: packages or lots, estimates, method and approval information, and steps and timing. Under section 21(3), send the following year's plan to the Entity Tender Committee no later than one month before financial year-end and post it on the Authority's website. Under section 21(4), update it after budget approval and at quarterly intervals. The committee acts on the plan, while the evaluation panel assesses tenders for an individual procurement. Regulation 14 of L.I. 2466 bars a staff member from serving on both for the same procurement.
Distinguish Tender Security From Performance Security
If a competitive tender requires security, section 55 requires disclosure of its terms in the invitation and consistent application to bidders. It can address withdrawal or modification in the circumstances specified in section 55(3), refusal to sign, failure to provide required performance security or failure to meet another stated pre-signing condition. Performance security instead supports obligations under the awarded contract.
Regulation 52 allows a banker's draft, an instrument from a financial institution or insurer, or a signed tender-securing declaration carrying the stated suspension consequence. A fixed amount cannot exceed two percent of estimated procurement cost. Regulation 52(3) prohibits requesting security under the price quotation method and in consultant selection. If an entity sets a fixed tender security for GH¢2 million of competitive works, GH¢40,000 is the maximum under the regulation. Follow section 55(4) for return of security.
An education procurement entity is preparing its next-year plan before the budget is approved. What does section 21 of Act 663 require?
Wait for budget approval before first sending the next-year plan to the tender committee.
Submit the plan to the Entity Tender Committee no later than one month before financial year-end and update it after budget approval and at quarterly intervals.
Have the evaluation panel approve the annual plan after opening the first tender.
Submit the plan only if it contains an international tender.
A school’s regular laboratory order was delayed because staff failed to begin a known annual purchase. Can the procurement entity rely on unforeseeable urgency to award a single-source contract without prior PPA approval?
Yes, if the head’s approval limit is sufficient.
Yes, with an explanation uploaded after the award.
Yes, if the school opens within five days.
No. Section 40 requires the Board’s approval and excludes urgency caused by the entity’s own delay.
A competitive construction tender has an estimated cost of GH¢3 million. If the entity requires a fixed-sum tender security under regulation 52(2) of L.I. 2466, what is the maximum?
GH¢60,000
GH¢90,000
GH¢150,000
GH¢300,000