2.3 Statutory Lien Waivers & Affidavits of Nonpayment
Key Takeaways
- Georgia requires the statutory interim or final waiver form; current forms release lien and bond rights, not the underlying contract claim.
- A waiver becomes effective on actual payment, written acknowledgment, or 90 days after execution unless a timely Affidavit of Nonpayment is filed.
- After filing the affidavit, serve the owner within seven days and also serve the contractor when the claimant lacks owner privity and a Notice of Commencement was filed.
- An Affidavit of Nonpayment does not restart the separate 90-day claim-of-lien period measured from last furnishing.
2.3 Statutory Lien Waivers & Affidavits of Nonpayment
Statutory Authority: Official Code of Georgia Annotated (O.C.G.A.) § 44-14-366 (Waiver of Lien or Claim Upon Bond; Forms; Affidavit of Nonpayment).
Lien waivers are standard commercial instruments exchanged during progress billings and project closeout. In Georgia, the rules governing lien waivers are uniquely rigid. Georgia is one of a select group of states that requires forms that substantially follow the statutory language and enforces an automatic statutory conversion rule that can permanently strip contractors of lien rights if payment is not received and affirmative action is not taken.
1. Mandatory Statutory Forms (O.C.G.A. § 44-14-366)
Under Georgia public policy, parties cannot draft custom lien waiver forms that circumvent statutory protections. Under O.C.G.A. § 44-14-366(a), any waiver of lien rights or bond claims that does not substantially follow the statutory format is void and unenforceable. Georgia recognizes exactly two statutory waiver forms:
- Interim Waiver and Release Upon Payment (O.C.G.A. § 44-14-366(c)):
- Used for interim progress payments throughout construction.
- Releases lien and bond rights through a specific "through date" (effective date), upon receipt of the stated progress payment amount.
- Preserves retainage and later furnishing; the executed form and its payment and through-date language control the precise released amount.
- Waiver and Release Upon Final Payment (O.C.G.A. § 44-14-366(d)):
- Used at final contract closeout and final retainage release.
- Releases all mechanics' lien and payment bond rights for the entire contract sum upon receipt of final payment.
Mandatory Statutory Notice
Both statutory forms must substantially follow the current statutory language and use at least 12-point font. The notice need not be in boldface capital letters. Omitting the required notice makes the form unenforceable and invalid under § 44-14-366.
2. The 2021 Statutory Reform (Senate Bill 315)
To understand Georgia's current lien waiver rules, contractors must understand the major statutory overhaul enacted by the Georgia General Assembly effective January 1, 2021.
The ALA Construction Services Ruling (2019)
In 2019, the Georgia Court of Appeals issued a controversial decision in ALA Construction Services, LLC v. Controlled Access, Inc. The court held that under the plain language of the previous statute, if a subcontractor signed a statutory lien waiver and failed to file an Affidavit of Nonpayment within the statutory window, the waiver operated as a complete release of ALL claims, including the subcontractor's underlying breach-of-contract lawsuit for money damages against the general contractor.
The Legislative Fix
In response to outrage from the construction industry, the General Assembly passed Senate Bill 315, amending O.C.G.A. § 44-14-366 with three vital changes:
- Scope Limited to Lien & Bond Rights: The revised statute explicitly clarifies that executing a statutory waiver only waives mechanics' lien rights and payment bond claims. It does not waive or extinguish underlying breach-of-contract claims or other common-law remedies for unpaid work.
- Extension of Statutory Window from 60 to 90 Days: The deadline to file an Affidavit of Nonpayment to prevent automatic waiver conversion was extended from 60 days to 90 calendar days.
- Updated Statutory Form Text: The mandatory bold text in both waiver forms was updated to reflect the 90-day timeline and the limitation to lien/bond rights.
+-----------------------------------------------------------------------------------------+
| GEORGIA LIEN WAIVER LAW: BEFORE VS. AFTER 2021 |
+------------------------------------+----------------------------------------------------+
| Feature | Pre-2021 Law (ALA Construction) | Current Law (2021+ Reform) |
+------------------------------------+---------------------------------+------------------+
| Automatic Conversion Window | 60 Calendar Days | 90 Calendar Days |
| Scope of Automatic Waiver | Lien, Bond, & Contract Claims | Lien & Bond Rights ONLY |
| Breach of Contract Lawsuit Survival| Extinguished if no affidavit | REMAINS INTACT (Can still sue) |
| Statutory Forms Mandate | Strict 12pt Bold Form | Updated 12pt Bold Form |
+------------------------------------+---------------------------------+------------------+
3. The 90-Day Automatic Conversion Rule
The most critical concept in Georgia lien waiver management is the 90-Day Automatic Conversion Rule under O.C.G.A. § 44-14-366(f).
When the waiver becomes effective:
A duly executed waiver becomes conclusively effective to the stated extent on the earliest of three events: (1) actual receipt of the funds stated in the waiver; (2) the claimant's execution of a separate written acknowledgment of payment in full; or (3) 90 days after execution unless the claimant files the statutory Affidavit of Nonpayment before that period expires. Filing the affidavit suspends the waiver until payment in full. The claimant must still preserve the separate deadline for a claim of lien.
4. The Affidavit of Nonpayment (O.C.G.A. § 44-14-366(f))
The Affidavit of Nonpayment is the sole statutory mechanism created by Georgia law to stop an unpaid waiver from converting into a permanent release.
Strict Recording & Notice Rules:
- Recording Deadline: The Affidavit of Nonpayment must be filed for record with the Clerk of the Superior Court in the county where the improved property is located within 90 calendar days from the date the waiver was executed.
- Service after filing: Within seven days, send a copy to the owner. Send a copy to the contractor when the claimant lacks privity with the owner and a Notice of Commencement was filed. Use registered or certified mail or statutory overnight delivery and retain proof.
Effect of Filing an Affidavit of Nonpayment:
- It prevents the waiver from becoming effective as to the unpaid amount.
- It preserves the lien and bond rights that would otherwise be released.
- It does not create a new 90-day lien-filing period. The ordinary claim-of-lien deadline still runs from the last furnishing, so calendar both deadlines independently.
+-----------------------------------------------------------------------------------------+
| AFFIDAVIT OF NONPAYMENT COMPLIANCE CHECKLIST |
+-----------------------------------------------------------------------------------------+
| [ ] Executed statutory Interim or Final Waiver on [Date] |
| [ ] Payment has NOT cleared or was only partially received |
| [ ] Calendar 90 days from execution date (DO NOT rely on invoice or through dates) |
| [ ] Draft statutory Affidavit of Nonpayment identifying property, waiver date, & amount |
| [ ] Record with Clerk of Superior Court within 90 calendar days of waiver date |
| [ ] Serve owner within seven days; also serve contractor when the statutory privity/NOC condition applies |
| [ ] Independently preserve the ordinary 90-day claim-of-lien deadline measured from last furnishing |
+-----------------------------------------------------------------------------------------+
5. What Happens When Payment Is Received After Filing?
If the debtor pays the outstanding amount after an Affidavit of Nonpayment has been recorded:
- The claimant must record an Affidavit of Payment or satisfaction document with the Clerk of Superior Court to cancel the Affidavit of Nonpayment.
- If a formal Claim of Lien was recorded, the claimant must file a Lien Cancellation within 30 calendar days of receiving cleared funds to remove the cloud on the owner's title.
Under Georgia's post-2021 amended statutory lien waiver law (O.C.G.A. § 44-14-366), what rights are released when a contractor signs a statutory lien waiver?
Under the Georgia 90-Day Automatic Conversion Rule, within how many days from executing a statutory lien waiver must an unpaid claimant record an Affidavit of Nonpayment to prevent the waiver from becoming an unconditional release?
After filing an affidavit of nonpayment, what service rule applies?