16.2 Level 4 Functional Performance Testing of Mechanical and Electrical Subsystems

Key Takeaways

  • Level 4 Functional Performance Testing (FPT) verifies the dynamic, automated operation of individual mechanical and electrical subsystems across all normal, maintenance, failure, and emergency operational modes.

  • Electrical subsystem FPT requires UPS step-load testing (0% to 100%), load rejection, full rated kW battery discharge runtime testing with infrared thermography, and STS sub-cycle transfers (less than or equal to 4 ms).

  • Where NFPA 110 Type 10 is specified, generator tests must show power restored within 10 seconds of utility loss, with load steps held within ISO 8528-5 class G3 frequency and voltage limits.

  • Mechanical subsystem FPT validates chiller staging and destaging logic, secondary pump hydronic differential pressure (dP) control, CRAH supply air temperature reset, and economizer mode transitions.

  • The Commissioning Issues Log functions as an auditable tracking ledger where identified deficiencies are logged with severity ratings, root-cause analyses, and mandatory physical re-testing verification before closeout.

Last updated: October 2026

16.2 Level 4 Functional Performance Testing of Mechanical and Electrical Subsystems

While Level 3 Pre-Functional Testing verifies that individual components are properly wired, lubricated, mechanically installed, and safely energized, it provides no verification of how these components behave under dynamic operational stress. A pump may rotate in the proper direction at Level 3, but its variable frequency drive (VFD) might fail to respond to differential pressure signals under varying hydronic flow demands. Similarly, an uninterruptible power supply (UPS) inverter may generate a clean 480V sine wave at no load, but its output voltage may collapse when subjected to a sudden 100% transient step load.

Level 4 Functional Performance Testing (FPT) is the rigorous discipline of evaluating individual mechanical, electrical, and control subsystems dynamically across every operational mode: normal, maintenance bypass, partial failure, and emergency states. Level 4 tests each subsystem in isolation using temporary test instrumentation and artificial load banks before systems are coupled together in Level 5 Integrated Systems Testing.


Prerequisites & The FPT Methodology

Level 4 FPT cannot proceed until rigorous gatekeeper criteria are achieved:

  1. 100% Completion of Level 3 Pre-Functional Checklists: All static inspections, point-to-point wiring verifications, megohmmeter insulation resistance tests, and OEM startup sign-offs must be executed and approved by the Commissioning Authority (CxA).
  2. Approved Step-by-Step Test Scripts: Every test must be governed by an approved, highly detailed script authored by the CxA. Scripts specify required initial system states, exact physical switching actions, expected quantitative outcomes, tolerance bands, and explicit abort criteria.
  3. Calibrated, NIST-Traceable Instrumentation: Data logging cannot rely solely on the building automation system (BAS) or equipment internal meters, which may have uncalibrated sensors or sluggish polling intervals. The CxA deploys independent high-speed power quality analyzers, ultrasonic flow meters, precision thermal imaging cameras, and digital manometers carrying active calibration certificates (typically within 12 months).
  4. Safety & LOTO Protocols: Strict Lockout/Tagout (LOTO) procedures, arc-flash boundary enforcement (NFPA 70E), and emergency contingency plans must be established prior to energizing high-power load banks.

Electrical Subsystem Functional Performance Testing

Electrical FPT validates the power delivery chain from the medium-voltage substation down to the critical computer room power distribution units (PDUs).

+-----------------------------------------------------------------------------------------+
|                        ELECTRICAL SUBSYSTEM FPT TEST PROTOCOL                           |
|                                                                                         |
|   +-----------------------+     +-----------------------+     +---------------------+   |
|   | 1. UPS Step Loading   | --> | 2. Step Load Transient| --> | 3. 100% Battery Run |   |
|   | (0%, 25%, 50%, 75%,   |     | (0->100%, 100->0%,    |     | (Full kW Discharge, |   |
|   |  100% kW / kVA)       |     |  ITIC / CBEMA Bounds) |     |  IR Thermography)   |   |
|   +-----------------------+     +-----------------------+     +----------+----------+   |
|                                                                          |              |
|                                                                          v              |
|   +-----------------------+     +-----------------------+     +---------------------+   |
|   | 6. Breaker Secondary  | <-- | 5. NFPA 110 Type 10   | <-- | 4. Bypass Transfers |   |
|   | Injection Testing     |     | Generator Cold Start  |     | & Static Switch STS |   |
|   | (LSIG Curves / Trip)  |     | (Power in <= 10 sec)  |     | (Sub-cycle < 4 ms)  |   |
|   +-----------------------+     +-----------------------+     +---------------------+   |
+-----------------------------------------------------------------------------------------+

1. Uninterruptible Power Supply (UPS) Testing

UPS testing utilizes temporary portable resistive and reactive load banks connected to the UPS output distribution switchboards:

  • Steady-State Load Testing: Operating the UPS at 0%, 25%, 50%, 75%, and 100% of rated nameplate capacity at both unity (1.0 PF1.0\text{ PF}) and rated lagging power factors (0.80.8 or 0.9 PF0.9\text{ PF}). Verifying phase voltage balance (within ±1%\pm 1\%), frequency stability (±0.1 Hz\pm 0.1\text{ Hz}), and overall efficiency.
  • Harmonics Verification: Measuring input current Total Harmonic Distortion (THDiTHD_i) and output voltage Total Harmonic Distortion (THDvTHD_v) across all load steps against the specification (IEEE 519 limits apply at the utility point of common coupling, not at each UPS). Active front-end IGBT rectifiers are typically specified for THDiTHD_i below about 3% to 5% at full load, and output THDvTHD_v below about 3% for linear loads and about 5% for non-linear loads.
  • Step-Load Transient Response: Subjecting the UPS inverter to instantaneous load steps: 0% to 100%, 100% to 0%, and 25% to 75% load steps. Voltage transient excursions and recovery times are recorded on high-speed digital oscilloscopes:
    • The transient voltage deviation must stay within the specified IEC 62040-3 output performance class and well inside the ITIC (Information Technology Industry Council) / CBEMA acceptability curve (commonly specified as about ±10%\pm 10\% or better).
    • The inverter output voltage must recover to within ±1%\pm 1\% of nominal voltage within 20 to 50 milliseconds.
  • Static Bypass and Maintenance Wrap-Around Transfers:
    • Automated Static Bypass Transfer: Simulating internal inverter faults and severe output overloads (e.g., 125%125\% for 10 minutes, 150%150\% for 60 seconds) to verify seamless automated transfer to static bypass and subsequent automatic re-transfer to inverter once conditions normalize.
    • Maintenance Bypass: Exercising make-before-break overlapping mechanical bypass switches to isolate the UPS module for maintenance without dropping downstream critical output power.

2. Battery Runtime Discharge & Thermal Validation

A battery bank is only as strong as its weakest cell. A 100% rated design kW load bank discharge test is performed on the energy storage system (VRLA, Lithium-ion, or flywheel):

  • 100% kW Load Discharge: The UPS rectifier input breaker is opened while the UPS is fully loaded to 100% of its rated design IT capacity, forcing the system onto battery power. The discharge runs continuously until the battery string reaches its end-of-discharge cutoff voltage (typically 1.671.67 to 1.75 volts per cell [VPC]1.75\text{ volts per cell [VPC]} for lead-acid).
  • DC Current Calculation: The discharge current (IDCI_{\text{DC}}) drawn by the inverter is governed by:

IDC=PkW×1000Vbus×ηinverterI_{\text{DC}} = \frac{P_{\text{kW}} \times 1000}{V_{\text{bus}} \times \eta_{\text{inverter}}}

Where:

  • PkWP_{\text{kW}} = Total real power delivered to load (kWkW)
  • VbusV_{\text{bus}} = Instantaneous DC bus battery voltage (VV)
  • ηinverter\eta_{\text{inverter}} = Inverter conversion efficiency (typically 0.940.94 to 0.970.97)

As the battery discharges and VbusV_{\text{bus}} drops from float voltage (e.g., 540V DC) toward end-of-discharge voltage (e.g., 400V DC), the DC current rises in inverse proportion to the voltage (about 35% higher at 400 V than at 540 V). This rising current places maximum thermal stress on terminations.

  • Continuous Infrared (IR) Thermography: During the entire discharge cycle, thermographers scan every battery terminal post, inter-cell busbar link, DC fuse, and DC circuit breaker. A temperature differential above the specification's limit (for example, more than 5∘C5^\circ\text{C} between similar terminals, or more than 15∘C15^\circ\text{C} above ambient) flags an un-torqued bolt, oxidized lug, or internal cell defect that would cause catastrophic thermal runaway under emergency operation.

3. Static Transfer Switches (STS)

Dual-input Static Transfer Switches (STS) utilize Silicon Controlled Rectifiers (SCRs) to provide instantaneous power path redundancy to downstream single-corded or PDU loads:

  • Sub-Cycle Transfer Verification: Testing preferred-to-alternate source transfers under both synchronized and unsynchronized input conditions.
  • Acceptance Criteria: Specifications typically require transfer within about 4 ms4\text{ ms} (a quarter of a 60 Hz cycle) between synchronized sources. That keeps the interruption well inside the ITIC curve's 20 ms zero-voltage tolerance and the 16 to 20 ms16\text{ to }20\text{ ms} hold-up time of server switch-mode power supplies. For unsynchronized sources, many STS units delay or block transfer according to phase angle to limit downstream transformer inrush, and the test verifies that configured behavior.

4. Standby Generator Systems & NFPA 110 Type 10

Standby diesel generators undergo dynamic testing using resistive/reactive load banks:

  • NFPA 110 Type 10 Start Requirement: NFPA 110 types (U, 10, 60, 120, and M) give the maximum time the load terminals may be without acceptable power. For Type 10, from standstill (with jacket-water heaters keeping the engine warm, as NFPA 110 requires for Level 1 systems) and with utility power disconnected, the generator starting system must crank the engine, achieve rated speed (1800 RPM for 60 Hz) and rated voltage (e.g., 480V or 13.8 kV), stabilize frequency, and energize the emergency distribution bus in less than or equal to 10 seconds:

Tstart+Tstabilize+Tclose≤10.0 secondsT_{\text{start}} + T_{\text{stabilize}} + T_{\text{close}} \le 10.0\text{ seconds}

  • Transient Step-Load Acceptance: Testing step-load acceptance per ISO 8528-5 performance class G3 (or G4 by agreement), using the load steps the manufacturer states the set can accept, such as 33%, 50%, or 100% blocks. For G3, the frequency dip must not exceed about 7% with recovery within about 3 seconds, and the voltage dip must stay within about 15% with recovery within about 4 seconds.
  • Endurance Burn-In Run: NFPA 110 on-site acceptance testing includes a 2-hour full-load run; many data center specifications require 4 hours or more at rated kW. The CxA logs lube oil pressure, cooling jacket temperature, exhaust gas backpressure, and alternator bearing temperature at 15-minute intervals.

5. Circuit Breaker Secondary Injection Testing

Before closing breakers under functional load, electronic trip units (ETUs) on low-voltage air circuit breakers (ACBs) and molded case circuit breakers (MCCBs) must undergo secondary current injection testing. A calibrated test set injects simulated fault signals directly into the trip unit logic to verify:

  • Long-Time (L) Pickup & Delay: Thermal overload protection curve.
  • Short-Time (S) Pickup & Delay: Short-circuit protection with I2tI^2t response.
  • Instantaneous (I) Pickup: High-level fault trip with zero intentional delay.
  • Ground-Fault (G) Pickup & Delay: Earth leakage protection.

Measured trip times must conform precisely to the engineer of record's selective coordination time-current characteristic (TCC) curves, ensuring that a downstream branch fault never cascades upstream to trip a main service switchboard.


Mechanical Subsystem Functional Performance Testing

Mechanical FPT evaluates the automated thermodynamic behavior of cooling infrastructure under varying heat loads, verifying that thermal management loops prevent IT hardware overheating.

+-----------------------------------------------------------------------------------------+
|                        MECHANICAL SUBSYSTEM FPT TEST PROTOCOL                           |
|                                                                                         |
|   +-----------------------+     +-----------------------+     +---------------------+   |
|   | 1. Chiller Staging    | --> | 2. Variable Primary / | --> | 3. Cooling Tower    |   |
|   | Staged capacity,      |     | Secondary Pumping dP  |     | Fan VFD Staging &   |   |
|   | CHWST setpoint reset  |     | Loop & Min Flow Bypass|     | Basin Freeze Loops  |   |
|   +-----------------------+     +-----------------------+     +----------+----------+   |
|                                                                          |              |
|                                                                          v              |
|   +-----------------------+     +-----------------------+     +---------------------+   |
|   | 6. Containment & Room | <-- | 5. Economizer Mode    | <-- | 4. CRAH / CRAC Air  |   |
|   | Differential Pressure |     | Transitions (Air/Water|     | Modulation (EC Fans,|   |
|   | (+0.02 to +0.05 in.wg)|     | Free/Mixed/Mechanical)|     | Temp/Dewpoint Loops)|   |
+-----------------------------------------------------------------------------------------+

1. Central Chilled Water Plant Testing

  • Chiller Staging & Capacity Modulation: Testing automated chiller sequencing algorithms within the chiller plant automation system. Verifying lead/lag rotation, staged addition of lag chillers upon rising cooling load or flow demand, and smooth destaging as load recedes.
  • Chiller Thermal Heat Rejection Formula: Chiller thermal performance (QtonsQ_{\text{tons}}) is validated across hydronic flow measurements:

Qtons=500×GPM×ΔT12,000=GPM×ΔT24Q_{\text{tons}} = \frac{500 \times \text{GPM} \times \Delta T}{12,000} = \frac{\text{GPM} \times \Delta T}{24}

Where:

  • GPM\text{GPM} = Chilled water volumetric flow rate (Gallons Per Minute)

  • ΔT\Delta T = Chilled water temperature differential between return and supply (TCHWR−TCHWST_{\text{CHWR}} - T_{\text{CHWS}} in ∘F^\circ\text{F})

  • 500500 = Fluid density and specific heat constant (8.33 lb/gal×60 min/hr×1.0 BTU/(lb⋅∘F)8.33\text{ lb/gal} \times 60\text{ min/hr} \times 1.0\text{ BTU}/(\text{lb}\cdot^\circ\text{F}))

  • 12,00012,000 = BTU/hr per refrigeration ton

  • Hydronic Pumping Differential Pressure (dPdP) Control: In variable-flow secondary chilled water loops, pump VFD speeds are modulated to maintain a constant differential pressure across the hydraulically most remote CRAH unit. FPT tests this response by artificially throttling two-way control valves: secondary pump VFDs must smoothly modulate down without hunting. When flow drops toward minimum allowable chiller evaporator limits, the modulating minimum flow bypass valve must open smoothly to prevent evaporator freezing and compressor trip.

2. Cooling Tower & Heat Rejection Systems

  • Cooling Tower Fan Staging & VFD Control: Modulating fan speed tracking the Condenser Water Supply Temperature (CWST) setpoint (typically 85∘F/29.4∘C85^\circ\text{F} / 29.4^\circ\text{C}). Testing fan vibration cutout switches and basin water level float controls.
  • Freeze Protection: Validating automatic basin immersion heaters and bypass drain-down valves under simulated freezing ambient conditions.

3. Whitespace Air Handling (CRAH / CRAC Units)

  • Airflow Modulation: Electronically Commutated (EC) fans or supply fan VFDs modulate airflow volume (CFM) to maintain constant underfloor static pressure or containment static pressure differential (+0.02 to +0.05 in. w.g./5 to 12 Pa+0.02\text{ to }+0.05\text{ in. w.g.} / 5\text{ to }12\text{ Pa}). FPT verifies that fan speeds ramp smoothly without surging or creating draft dead zones.
  • Supply Air Temperature Control: Testing modulating two-way chilled water valves to maintain supply air temperature within the ASHRAE TC 9.9 Recommended Thermal Envelope (18∘C18^\circ\text{C} to 27∘C/64.4∘F27^\circ\text{C} / 64.4^\circ\text{F} to 80.6∘F80.6^\circ\text{F}).
  • Humidity & Dew Point Control: Verifying that ultrasonic humidifiers and cooling coil dehumidification cycles track dew point targets (the ASHRAE 2021 recommended range of −9∘C-9^\circ\text{C} to 15∘C15^\circ\text{C} dew point and 70%70\% RH maximum where gaseous pollutants are low, or 50%50\% RH where they are high) without triggering fighting control loops where adjacent units simultaneously humidify and dehumidify.

4. Economizer Mode Transitions

Economizer systems reduce operating expenses by leveraging cool ambient outdoor conditions:

  • Waterside Economizers (Plate-and-Frame Heat Exchangers): Testing automated diverter valves that route condenser water through a plate-and-frame heat exchanger to chill the loop when outdoor wet-bulb temperatures drop below design thresholds (WBT≤45∘F−50∘F/7.2∘C−10∘CWBT \le 45^\circ\text{F}-50^\circ\text{F} / 7.2^\circ\text{C}-10^\circ\text{C}), completely bypassing the chillers.
  • Airside Economizers: Testing outdoor air, return air, and relief air motorized dampers across three distinct modes: 100% Free Cooling Mode, Mixed/Integrated Mode, and Full Mechanical Recirculation Mode. Testing high-limit outdoor enthalpy lockouts and freeze-stat safety dampers to ensure freezing outdoor air never shocks cooling coils.

Acceptance Criteria, Test Instrumentation & Issues Log Management

The Commissioning Issues Log

The Commissioning Issues Log is the master ledger tracking every observed deficiency, non-conformance, and anomaly uncovered during FPT. Managed exclusively by the CxA, every item is categorized by severity:

  • Level 1 Deficiency (Critical Showstopper): Compromises life safety, threatens catastrophic equipment damage, violates code, or prevents completion of testing. Testing is suspended immediately until resolved.
  • Level 2 Deficiency (Major Non-Compliance): System operates but fails to meet performance tolerance bands, design redundancy (N+1N+1), or efficiency targets. Must be rectified prior to Level 5 IST.
  • Level 3 Deficiency (Minor / Cosmetic): Missing nameplates, minor paint scratches, or incomplete labeling that does not impair dynamic performance.
+-------------------------------------------------------------------------------------------------------------------+
|                               SAMPLE COMMISSIONING ISSUES LOG ENTRY & RESOLUTION                                  |
+------+--------+------------------------+------------------------------------+---------------+-------------+-------+
| Item | Level  | Subsystem & Location   | Description of Deficiency          | Assigned Party| Remediation | Status|
+------+--------+------------------------+------------------------------------+---------------+-------------+-------+
| E-42 | Level 1| Switchgear Lineup SWG-A| Generator 2 breaker failed to sync;| OEM Controls  | Re-tuned PID| CLOSED|
|      |        | Generator Paralleling  | frequency slew rate exceeded limits| & Switchgear  | governor &  | (AFTER|
|      |        | Bus Compartment 3      | during 100% step-load acceptance   | Contractor    | re-tested)  |RETEST)|
+------+--------+------------------------+------------------------------------+---------------+-------------+-------+

Mandatory Retesting Protocols

An issue in the Commissioning Issues Log can never be closed administratively. The responsible trade contractor must submit written notification of correction, after which the CxA must physically re-execute the exact step-by-step test script. Only when the subsystem satisfies the quantitative acceptance criteria in the presence of the CxA is the issue formally marked as "Closed."


Practical Design Scenario: The Unstable Generator-UPS Interface

The Operational Context

A 5 MW (IT) data hall is undergoing Level 4 FPT. The electrical plant consists of six 1,000 kVA static UPS modules (5+1) and four 2.5 MW standby diesel generators operating in an N+1N+1 (3+1) paralleling configuration.

The Dynamic Failure

During the UPS 100% step-load test while powered by the generator bus, the load bank was stepped instantly from 0% to 100% (1,000 kW). The sudden load application caused the generator engine to bog down momentarily: engine speed dropped by 6.5%, causing electrical frequency to sag to 56.1 Hz for 1.8 seconds.

Although the generator recovered within ISO 8528 Class G3 limits, the rapid frequency rate of change (frequency slew rate =2.1 Hz/second= 2.1\text{ Hz/second}) caused the UPS internal static bypass switch to declare the input source "unstable and out-of-sync." The UPS controller immediately inhibited bypass capability and alarmed. When the load bank was stepped back to 0% (load rejection), the generator overshot in frequency and voltage, and the overvoltage tripped the UPS rectifier's input protection, forcing the UPS onto battery with bypass unavailable.

The Engineering Remediation

The CxA issued a critical Level 1 deficiency in the Issues Log. A joint technical session with the generator governor programmer and the UPS field engineer uncovered two contributing root causes:

  1. Generator Digital Governor Tuning: The electronic engine governor proportional and integral (PI) gains were set too sluggishly, allowing excessive speed droop during block loading.
  2. UPS Rectifier Walk-In Programming: The UPS input IGBT rectifier was programmed with an aggressive 1-second "walk-in" ramp rate, shocking the generator like a hammer blow.

Corrective Action: The generator governor PID loop was re-tuned for rapid transient fuel rack response. The UPS rectifier walk-in ramp rate was extended from 1 second to 15 seconds, allowing the UPS to gradually draw load from 0% to 100% over a 15-second ramp. Upon re-testing, frequency droop was held to less than 1.2 Hz1.2\text{ Hz}, frequency slew rate remained below 0.4 Hz/sec0.4\text{ Hz/sec}, and the UPS maintained completely stable operation through both step-load and load-rejection cycles.


Common Exam Traps & DCDC Pitfalls

  • Extrapolating Battery Capacity from Partial-Load Tests: A common exam trap asserts that running a battery discharge test at 50% load for twice the duration validates a 100% full-load runtime. This is scientifically false. Due to Peukert's law and internal cell resistance, available capacity falls and heating rises nonlinearly at high discharge currents. Battery discharge validation must be performed at 100% rated design kW load.
  • Misinterpreting NFPA 110 Type 10 Timing: NFPA 110 Type 10 does not mean the engine has 10 seconds to crank and additional time to transfer. It allows a maximum of 10 seconds total, from the instant of utility failure, before acceptable power is restored at the load terminals.
  • Omitting Out-of-Phase STS Transfers: Testing a Static Transfer Switch only between two synchronized, phase-matched sources is an incomplete test. Level 4 FPT must also test STS behavior under unsynchronized, out-of-phase conditions (up to 180∘180^\circ phase displacement) to prove the configured transfer logic prevents downstream transformer saturation and breaker trips.
  • Administrative Closure of the Issues Log: Assuming an issues log item can be signed off based on a contractor's email or revised shop drawing is a major professional trap. In mission-critical commissioning, every Level 1 and Level 2 deficiency requires physical, witnessed re-testing.
Loading diagram...
Level 4 Functional Performance Testing (FPT) Sequence for Electrical and Mechanical Subsystems
Test Your Knowledge

Under NFPA 110 standards governing Level 4 Functional Performance Testing of emergency and standby power systems (EPS), what is the maximum allowable time for a Type 10 system's generator sets to start, accelerate to rated speed, achieve stable voltage and frequency, and restore power to the emergency load?

A

Within 3 seconds from utility loss

B

Within 120 seconds from utility loss (NFPA 110 Type 120)

C

Within 60 seconds from utility loss (NFPA 110 Type 60)

D

Within 10 seconds from utility loss (NFPA 110 Type 10)

Test Your Knowledge

During Level 4 Functional Performance Testing of a 1,000 kVA double-conversion static UPS system, how should the battery runtime capacity and thermal integrity be definitively validated?

A

A continuous discharge at 100% rated kW on load banks down to end voltage, with infrared thermography throughout

B

By measuring open-circuit terminal voltage while the battery bank remains connected to its float charger

C

By performing a mathematical extrapolation based on a 15-minute test run at 10% load using internal diagnostic software

D

By disconnecting the DC bus breakers and discharging a single pilot cell using a handheld carbon-pile resistor

Test Your Knowledge

A data center design uses dual-input Static Transfer Switches (STS) to feed high-density PDUs. During Level 4 FPT, the specification requires synchronized transfers to complete within about 4 ms (a quarter of a 60 Hz cycle). What is the main reason for this requirement?

A

NEC Article 700 requires every emergency source transfer to finish within a quarter cycle

B

The STS must match the transfer time of the upstream generator automatic transfer switches to stay coordinated

C

It keeps the interruption well inside the ITIC 20 ms tolerance and server power supply hold-up time

D

Silicon controlled rectifiers physically cannot switch more slowly than a quarter cycle

Test Your Knowledge

An unexpected control oscillation is discovered during Level 4 FPT of a central chilled water plant: the secondary pump variable frequency drives (VFDs) hunt continuously between 30 Hz and 60 Hz as CRAH control valves modulate. The Commissioning Authority (CxA) enters this finding into the Commissioning Issues Log. What is the mandatory protocol required before this issue can be closed?

A

The mechanical engineer of record signs an administrative waiver re-classifying the VFD hunting as normal system noise

B

Retune the PID loop, update the control documentation, and have the CxA witness a retest under load

C

The general contractor provides written assurance that the oscillation will stabilize once live server IT heat load is deployed

D

The CxA lowers the secondary chilled water flow setpoint in the BMS software to force the pumps to run constantly at 100% speed