3.5 Site Research, Site Surveys, and Multi-Site Evaluation
Key Takeaways
ANSI/BICSI 002-2024 requires site suitability to be determined by a site survey and evaluation plus a risk analysis; an existing survey is acceptable only if under six months old.
Site research moves from desktop screening (GIS, flood, seismic, and utility maps) to a field survey and then to due diligence studies such as geotechnical borings and a Phase I ESA.
Separate pass/fail knockout criteria from weighted criteria so a fatal flaw, such as an unmitigable flood risk, cannot be averaged away by strong scores elsewhere.
A weighted site score is the sum of each criterion weight times its score; weights must total 100% and be agreed with the client before scoring.
Sensitivity testing that shifts the weights shows whether the recommended site stays first or whether the ranking depends on one debatable assumption.
3.5 Site Research, Site Surveys, and Multi-Site Evaluation
The DCDC blueprint asks the consultant to conduct site research or a survey to confirm topography, adjacent areas, and the comparison of multiple sites, and then to evaluate how well potential sites meet the criteria. The earlier sections of this chapter explain what makes a site good or bad (hazards, proximity, utilities, zoning). This section explains how the consultant gathers that evidence and turns it into a defensible comparison.
ANSI/BICSI 002-2024 sets the baseline: the suitability of a site shall be determined by a site survey and evaluation and by a risk analysis. An existing survey may be reused only if it is less than six months old, because land use, utility capacity, and neighboring development change quickly.
Stage 1: Desktop Research and Screening
Desktop research eliminates weak sites before anyone travels. Typical sources include:
- GIS and internet mapping: aerial and street imagery, parcel boundaries, ownership, land use, and elevation contours. Survey tools such as handheld GPS and mapping software let the team record exact coordinates for every observation later.
- Natural hazard data: flood maps (in the United States, FEMA's National Flood Hazard Layer), the ASCE Hazard Tool for site-specific wind, seismic, snow, and ice loads under ASCE 7, historical weather, wildfire history, and lightning flash density maps.
- Proximity hazards: distances to airports and flight paths, railroads, highways, pipelines, chemical plants, and other hazards, screened against the BICSI 002 Table 5-1 distances (for example, 8 km from airports, 1.6 km from railroads, 80 km from nuclear plants).
- Utilities and telecommunications: transmission and distribution maps, substation locations, utility service territories, water and sewer mains, gas pipelines, and fiber route maps from access providers.
- Regulatory data: zoning maps, comprehensive plans, environmental databases, and airspace restrictions. In the United States, a structure or construction crane near an airport or taller than 200 ft above ground may require FAA notice under 14 CFR Part 77.
Stage 2: The Field Survey
A field survey confirms what the maps suggest and finds what they miss. The survey team typically:
- Walks the site and records GPS-tagged photographs of boundaries, slopes, drainage, existing structures, and overhead lines.
- Confirms topography: BICSI 002 recommends avoiding slopes steeper than 15% and sites above 3,050 m (10,000 ft) elevation; standing water and erosion show drainage problems.
- Inventories adjacent areas: what is on every side of the parcel and what could be built there under current zoning. A quiet field today can be a truck terminal or quarry later.
- Checks access: BICSI 002 recommends at least two access roads, each with at least 4.3 m (14 ft) of vertical clearance, and routes that stay above flood levels.
- Locates utility points of connection: the nearest substation and feeders, water and sewer connections, and the poles or manholes where access providers would enter.
- Notes nuisance sources: radio transmitters, rail lines, and heavy industry. BICSI 002 recommends measuring vibration and electromagnetic interference near railroads over several days, not in a single visit.
- Meets local stakeholders: planning staff, utility account managers, and economic development officials, who can confirm capacity, schedules, and incentives.
Stage 3: Due Diligence Studies
For the short-listed sites, specialists prepare formal studies, usually while the client holds the land under an option or a contract with a due diligence period:
| Study | What it establishes |
|---|---|
| ALTA/NSPS land title survey | Boundaries, easements, encroachments, and access rights tied to the title commitment |
| Topographic survey | Contours, existing grades, and drainage paths for civil design and earthwork estimates |
| Geotechnical investigation | Soil bearing capacity, groundwater depth, seismic site class, and liquefaction potential from borings |
| Phase I Environmental Site Assessment (ASTM E1527-21) | Recognized environmental conditions from past uses; may lead to Phase II sampling |
| Utility capacity studies and will-serve letters | Whether power, water, and sewer can serve the planned load, by what date, and at what cost |
| Access provider inquiries | Which carriers can deliver diverse routes to the site, and the build cost |
| Wetlands, cultural resource, and traffic studies | Permitting constraints that can shrink the buildable area or delay approvals |
Multi-Site Evaluation: Knockouts, Weights, and Scores
Comparing sites is where many consultants lose credibility. A sound method has four parts.
1. Define criteria from the client's requirements. Use the needs assessment (capacity, availability class, growth, schedule, budget) and BICSI's site factors. Each criterion needs a written scoring rubric, such as "5 = two independent substations with capacity available within 18 months."
2. Apply knockout criteria first. Some conditions are pass/fail: inadequate power by the required date, an unmitigable flood risk, or zoning that cannot be changed. A site that fails a knockout is removed, no matter how well it scores elsewhere.
3. Weight and score the remaining criteria. Weights reflect client priorities and must total 100%. The weighted score is:
where is the weight of criterion and is the site's score on that criterion.
4. Test sensitivity. Shift the weights within a reasonable range and confirm whether the ranking changes.
Worked Example
Three sites survive the knockout screen. Scores use a 1-to-5 scale:
| Criterion | Weight | Site A | Site B | Site C |
|---|---|---|---|---|
| Power availability and cost | 30% | 5 | 3 | 4 |
| Telecommunications diversity | 20% | 3 | 5 | 4 |
| Natural hazard exposure | 20% | 4 | 3 | 5 |
| Land, zoning, and expansion room | 15% | 3 | 4 | 2 |
| Labor, access, and logistics | 15% | 4 | 5 | 3 |
| Weighted score | 100% | 3.95 | 3.85 | 3.75 |
Site A scores .
Now test sensitivity. If the client decides telecommunications diversity matters more and shifts the weights to 20% power and 30% telecommunications, Site A falls to 3.75 and Site B rises to 4.05. The ranking flips. The report must show this, and the consultant should confirm the weights with the client before recommending a site. A recommendation that depends on one disputed weight is a decision for the client, not a fact for the consultant to assert.
Common Exam Traps & DCDC Pitfalls
- Relying on an old survey: BICSI 002 accepts an existing site survey only if it is less than six months old.
- Averaging away a fatal flaw: A site in a flood hazard area should fail a knockout screen, not lose a few weighted points.
- Scoring before agreeing weights: Weights set after scores are known invite bias. Agree the criteria, rubrics, and weights with the client first.
- Skipping the field visit: Maps rarely show a new neighbor under construction, a shared fiber bridge crossing, or poor drainage.
- Confusing survey types: A topographic survey shows grades; an ALTA/NSPS survey shows boundaries and easements; a geotechnical investigation shows soil and groundwater conditions.
A client offers a site survey of a candidate parcel completed nine months ago and asks the DCDC to rely on it. What does ANSI/BICSI 002-2024 indicate?
The survey may be reused, because BICSI 002 considers site surveys valid for up to two years
The survey is acceptable as long as the local zoning has not changed
No survey is needed if a risk analysis is completed instead
A new survey, because BICSI accepts an existing survey only if it is under six months old
Using weights of 30% power, 20% telecommunications, 20% natural hazards, 15% land, and 15% labor, what is the weighted score of a site scored 4, 4, 5, 2, and 3 on those criteria (1-to-5 scale)?
3.60
4.10
3.75
3.95
A candidate site scores highest overall, but part of the building footprint lies within a 500-year flood hazard area that cannot be mitigated. How should a well-structured evaluation treat this?
Treat it as a knockout condition that removes the site regardless of its weighted score
Increase the weight of the power criterion to offset the flood exposure
Ignore it because the 500-year flood area is less severe than the 100-year area
Deduct one point from the natural hazard score and keep the site's overall rank
Which due diligence study identifies soil bearing capacity, groundwater depth, and liquefaction potential at a candidate data center site?
An ALTA/NSPS land title survey of the parcel boundaries
A geotechnical investigation with soil borings
A Phase I Environmental Site Assessment
A utility will-serve letter