3.6 Site Selection Financial Analysis, Incentives, and the Feasibility Report

Key Takeaways

  • ANSI/BICSI 002-2024 groups site costs into one-time costs, temporary telecom and migration costs, constructability, recurring costs, and intangible factors such as skilled staff.

  • A 0.02 USD/kWh power price difference on a 13 MW average facility load is worth about 2.28 million USD a year, or about 19.5 million USD over 15 years at 8%.

  • Sales-and-use tax exemptions matter because servers are bought again every few years; each refresh multiplies the saving, so incentives must be valued as a present-value stream.

  • Incentive agreements usually carry investment, job, and wage commitments with clawbacks, so the feasibility report must test whether the client can meet them.

  • The feasibility report states client requirements, method, site findings, risks, utilities, financial analysis, schedule, comparison with sensitivity, and a conditional recommendation.

Last updated: October 2026

3.6 Site Selection Financial Analysis, Incentives, and the Feasibility Report

Two blueprint tasks close the concept planning phase: determine the financial implications of site selection (for example, cost and tax incentives) and develop a feasibility report based on the client's requirements and the site search findings. Section 4.2 teaches the general tools (CapEx, OpEx, TCO, NPV, IRR). This section applies them to the question every site search must answer: which location costs least over the facility's life while meeting the client's requirements?


The BICSI 002 Site Cost Categories

ANSI/BICSI 002-2024 lists the cost factors that differ by site. Using its structure keeps a comparison complete:

CategoryExamples
One-time costsReal estate purchase, local tax incentives, environmental assessment, utility infrastructure extensions, redundant utility services, demolition and site preparation
Temporary costsInterim telecommunications and migration of equipment and services from existing sites
ConstructabilityLabor availability, construction cost level, access for materials, weather, and permitting timelines
Recurring costsUtility usage, telecommunications services, prevailing wage requirements, lease payments, and taxes
Intangible factorsProximity to the client's other facilities and the availability of skilled staff

Recurring costs usually dominate. A site with cheaper land but more expensive power is rarely the cheaper site over 15 or 20 years.

Public Incentives and Their Strings

Jurisdictions compete for data centers because they bring large capital investment and tax base. Common incentive types include:

  • Sales-and-use tax exemptions on qualifying data center equipment, often the most valuable incentive because servers, storage, and network gear are replaced every few years.
  • Property tax abatements or payment-in-lieu-of-taxes (PILOT) agreements that reduce real and personal property taxes for a set term.
  • Income or franchise tax credits tied to investment or job creation.
  • Utility economic development rates and contributions toward substations, water, or road improvements.
  • Zone-based programs (enterprise zones and similar) and workforce training grants.

Incentives come with conditions: a minimum capital investment within a deadline, a number of new jobs, wage thresholds, and continued operation. Most agreements include clawback provisions that require repayment if commitments are missed. The consultant should model the incentive only for the years and amounts the client can realistically earn, and flag the clawback exposure as a risk.


Comparing Sites in Present Value

Costs and benefits arrive at different times, so compare them in present value (PV):

PV=∑t=0nCFt(1+r)tPV = \sum_{t=0}^{n} \frac{CF_t}{(1+r)^t}

For a level annual amount AA over nn years, PV=A×1−(1+r)−nrPV = A \times \frac{1-(1+r)^{-n}}{r}.

Worked Example: Power Price Versus a Sales Tax Exemption

A client plans a 10 MW (IT) facility with an expected annual PUE of 1.3, so the average facility load is 13 MW. Two finalist sites differ mainly in electricity price and incentives. Use a 15-year horizon and an 8% discount rate.

Step 1: Annual energy

13,000 kW×8,760 h=113,880,000 kWh/year13{,}000\text{ kW} \times 8{,}760\text{ h} = 113{,}880{,}000\text{ kWh/year}

Step 2: Power cost difference. Site A offers 0.065 USD/kWh; Site B charges 0.085 USD/kWh.

0.02×113,880,000=2,277,600 USD/year (Site B costs more)0.02 \times 113{,}880{,}000 = 2{,}277{,}600\text{ USD/year (Site B costs more)}

PV=2,277,600×1−1.08−150.08=2,277,600×8.5595≈19.5 million USDPV = 2{,}277{,}600 \times \frac{1-1.08^{-15}}{0.08} = 2{,}277{,}600 \times 8.5595 \approx 19.5\text{ million USD}

Step 3: Sales tax exemption at Site B. The client expects to buy about 200 million USD of IT equipment at opening and to refresh it at years 4 and 8. Site B's state exempts it from a 6% sales tax, saving 12 million USD per purchase:

PV=12+121.084+121.088=12+8.82+6.48≈27.3 million USDPV = 12 + \frac{12}{1.08^{4}} + \frac{12}{1.08^{8}} = 12 + 8.82 + 6.48 \approx 27.3\text{ million USD}

Step 4: Compare. Site B's exemption (about 27.3 million USD) outweighs its power penalty (about 19.5 million USD) by roughly 7.8 million USD in present value, before land, construction, and other differences. The answer changes if the refresh cycle lengthens, the client misses the incentive's job commitments, or power prices diverge further, so the report should show these sensitivities rather than a single number.

Notice what a nominal comparison would have done: three exemptions of 12 million USD look like 36 million USD, and 15 years of power penalty look like 34 million USD. Present value changes both figures and the size of the gap.


The Feasibility Report

The feasibility report is the decision document for the client's leadership. It should let a reader who skipped the meetings understand what was required, what was found, and why one site (or none) is recommended. A typical structure:

  1. Executive summary and recommendation, including conditions that must hold for the recommendation to stand.
  2. Client requirements: capacity and growth, availability class, schedule, budget, and operational needs from the needs assessment.
  3. Methodology: criteria, knockout rules, weights, scoring rubrics, data sources, and site visit dates.
  4. Site descriptions and survey findings with maps and photographs.
  5. Risk analysis: natural, human-caused, and technological hazards measured against the BICSI 002 site criteria, with mitigation and residual risk.
  6. Utilities and telecommunications: capacity, redundancy, delivery dates, and connection costs, supported by will-serve letters where available.
  7. Financial analysis: one-time and recurring costs, incentives with their conditions, and present-value or TCO comparison.
  8. Schedule and entitlement path: zoning, permits, utility lead times, and long-lead procurement.
  9. Comparison matrix and sensitivity analysis.
  10. Assumptions, limitations, and next steps, such as securing an option on the land and commissioning detailed due diligence studies.

Common Exam Traps & DCDC Pitfalls

  • Comparing nominal totals: Always discount future costs and savings to present value before comparing sites.
  • Treating incentives as guaranteed: Missed job or investment commitments can trigger clawbacks.
  • Ignoring recurring costs: Power, water, telecom, labor, and taxes usually outweigh land price over the facility life.
  • A recommendation without conditions: State the assumptions (refresh cycle, power price, incentive approval) that the recommendation depends on.
  • Mixing the feasibility report with the design: The report supports a go/no-go and site decision; detailed design follows in the next project phase.
Loading diagram...
From Site Costs to the Feasibility Report
Test Your Knowledge

Under the ANSI/BICSI 002-2024 site cost categories, which of these is a recurring cost rather than a one-time cost?

A

Utility usage and telecommunications services

B

Environmental assessment of the parcel

C

Demolition and site preparation

D

Extension of utility infrastructure to the site

Test Your Knowledge

A sales tax exemption saves 12 million USD on the opening equipment purchase and again on refreshes at years 4 and 8. At an 8% discount rate, what is the present value of the exemption?

A

About 36.0 million USD

B

About 24.0 million USD

C

About 27.3 million USD

D

About 31.1 million USD

Test Your Knowledge

A state offers a large property tax abatement if the client invests a minimum amount and creates a set number of jobs within five years. What should the feasibility report do with this incentive?

A

Exclude it entirely, because incentives are not part of site selection

B

Treat it as a one-time cost reduction in the year of construction only

C

Count its full face value, because approved incentive agreements cannot be withdrawn or reduced later

D

Value it only for commitments the client can realistically meet, and flag the clawback risk