5.3 Worked Cable Selection Examples

Key Takeaways

  • Work every cable example in order: CCC after derating → voltage drop → fault/disconnection thinking → mechanical fit, showing units at each step
  • Domestic example: long single-phase final subcircuit often passes Iz on a modest size but fails Clause 3.6 until the conductor is upsized
  • When upsizing for drop, re-state Ib ≤ In ≤ Iz and recompute Vd with the new Vc — do not assume the old drop figure still applies
  • Small commercial example: three-phase submain drop must use three-phase Vc and the 400 V (20 V) 5% limit, while still leaving budget for final circuits if checking end-to-end
  • Capstone answers score marks for transparent working and the correct limit (5% total), not for an unexplained final mm²
Last updated: August 2026

Worked Cable Selection Examples

Quick Answer: Treat every sizing problem as a four-gate workflow. The domestic example shows a long 230 V final subcircuit that needs upsizing for Clause 3.6 even after CCC passes. The commercial example shows a three-phase submain checked with three-phase Vc against a 20 V (5% of 400 V) limit while preserving end-to-end thinking.

How to Read These Examples

Figures for Vc and some Iz values below are illustrative teaching numbers chosen so arithmetic is clear in an open-book setting. On assessment day you must read the actual AS/NZS 3008 tables in the edition your RTO permits. The method, order, and 5% Clause 3.6 rule are what transfer — not the sample millivolt figures.

Assume copper PVC/PVC multicore cables, clipped or enclosed as stated, and MEN 230/400 V supply unless noted.


Example A — Domestic: Long Single-Phase Final Subcircuit

Scenario

A Queensland dwelling needs a dedicated single-phase circuit to a detached workshop:

GivenValue
Supply230 V a.c., MEN
Load / design current Ib20 A continuous (workshop outlets / small tools diversified to 20 A for this circuit)
Protective device In20 A circuit breaker
Route length L (MSB to workshop DB/outlet)45 m
InstallationTwo-core + earth, enclosed in conduit for part of the run; after derating, treat required Iz ≥ 20 A
Consumer mains drop already calculated3.0 V (≈ 1.3%) on the path feeding this MSB
No submainFinal subcircuit leaves the main switchboard

Clause 3.6 allowance to the workshop point of consumption: 5% of 230 V = 11.5 V total from POS. With 3.0 V already used on consumer mains, the final subcircuit may use at most 11.5 − 3.0 = 8.5 V.

Step 1 — Current after derating

Ib = 20 A, In = 20 A → need Iz ≥ 20 A after derating.

Suppose AS/NZS 3008 (illustrative) shows:

ConductorIz after your derating factorsCCC result
2.5 mm²18 AFail — Iz < In
4 mm²24 APass — Ib ≤ In ≤ Iz

Candidate after Step 1: 4 mm².

Step 2 — Voltage drop

Illustrative single-phase Vc:

SizeVc (mV/A·m)
4 mm²11.2
6 mm²7.5
10 mm²4.5

For 4 mm²:

Vd = (45 × 20 × 11.2) / 1000 = 10.08 V

Final subcircuit alone is 10.08 V, but only 8.5 V remains after mains. Total POS → load ≈ 3.0 + 10.08 = 13.08 V (5.7%)fails Clause 3.6.

Upsize to 6 mm²:

Vd = (45 × 20 × 7.5) / 1000 = 6.75 V

Remaining budget 8.5 V → OK for this segment. Total ≈ 3.0 + 6.75 = 9.75 V (4.2%)passes 5%.

Re-check Step 1: 6 mm² Iz will be higher than 4 mm² → still Ib ≤ In ≤ Iz.

Step 3 — Short-circuit / earth-fault disconnection (summary check)

  • Confirm the 20 A breaker and 6 mm² actives (with correctly sized earth) give a plausible Zs for 0.4 s disconnection on a final subcircuit — long 45 m runs are exactly where undersized earths fail EFLI even if actives were upsized for drop.
  • Confirm short-circuit withstand for the prospective fault level at the MSB is within cable/device limits (usually comfortable at domestic fault levels for these sizes, but still state the check).

Step 4 — Mechanical / installation

  • Conduit diameter and bend radius accept 6 mm² 2C+E.
  • Underground section (if any) uses a cable type permitted for burial / in conduit underground.
  • Terminations at 20 A breaker and workshop accessories suit 6 mm².

Domestic result

Select 6 mm² (not 4 mm²): CCC passed at 4 mm², but voltage drop against the remaining 8.5 V budget forced the upsize. Document mains drop + subcircuit drop = total ≤ 11.5 V.


Example B — Small Commercial: Three-Phase Submain

Scenario

A small warehouse distribution board is fed from the main switchboard:

GivenValue
SubmainThree-phase + neutral + earth
Nominal voltage400 V phase–phase (230 V phase–neutral)
Design current Ib63 A (after diversity for that DB)
Protective device In63 A MCCB
Route length L55 m
InstallationMulticore copper, cable tray; after grouping/ambient derating, need Iz ≥ 63 A
Consumer mains drop POS → MSB4.0 V on the 400 V basis already assessed for three-phase
Longest final subcircuit from warehouse DB (separate later check)Design target leave ~6 V on 400 V basis for finals

End-to-end three-phase limit: 5% of 400 V = 20 V. After 4.0 V mains, 16 V remains for submain + finals. If finals may use 6 V, submain budget ≈ 10 V (design allocation inside the mandatory 20 V total).

Step 1 — Current after derating

Need Iz ≥ 63 A.

Illustrative CCC after derating:

ConductorIzResult
10 mm²55 AFail
16 mm²72 APass
25 mm²95 APass

Candidate: 16 mm².

Step 2 — Voltage drop (three-phase Vc)

Illustrative three-phase Vc:

SizeVc (mV/A·m)
16 mm²2.4
25 mm²1.55

For 16 mm²:

Vd = (55 × 63 × 2.4) / 1000 = 8.32 V

Against a 10 V submain design budget → passes the allocation. End-to-end so far: 4.0 + 8.32 = 12.32 V, leaving 7.68 V for finals (near the 6 V planning figure — finals must be checked explicitly on the longest run).

If a question instead asked only “does the submain alone stay within 5%?”, 8.32 V ≪ 20 V — but that weaker question is not the full Clause 3.6 story when mains and finals also exist. Capstone-quality answers keep the POS → load narrative.

Suppose grouping was worse and only 16 mm² barely passed Iz, but the longest final later consumed 9 V. Then total 4.0 + 8.32 + 9.0 = 21.32 V > 20 V → fail. Remedy: upsize submain to 25 mm²:

Vd = (55 × 63 × 1.55) / 1000 = 5.37 V

Total with 9 V final ≈ 18.37 V → passes 5%.

Step 3 — Fault performance

  • Check MCCB breaking capacity ≥ prospective fault current at the MSB.
  • Confirm cable short-circuit capacity for the clearing time.
  • Confirm earth size and length keep Zs within disconnection limits for the warehouse DB protection scheme.

Step 4 — Mechanical

  • Tray fill and support spacing for 16 mm² or 25 mm² multicore.
  • Gland and MCCB lug capacity.
  • Neutral and earth continuity through the submain consistent with MEN rules (MEN link remains at the main switchboard — do not create parallel MEN links at the warehouse DB).

Commercial result

Start at 16 mm² for CCC; confirm three-phase Vd; if end-to-end finals push the installation over 20 V, upsize to 25 mm² and re-check. Always use three-phase Vc and the 400 V / 20 V limit for the three-phase path.


Capstone Template (Copy This Structure Into Your Working)

  1. Ib, In, installation method, derating → Iz (state Ib ≤ In ≤ Iz).
  2. List series segments from POS; convert 5% → volts.
  3. Vd = (L × I × Vc)/1000 per segment; sum; compare.
  4. Fault / EFLI / withstand note.
  5. Mechanical / termination note.
  6. Final selected size with one sentence why (usually “CCC OK at X mm²; Vd required Y mm²”).

That template is the calculation mindset: open book, ordered gates, no mystery millimetres.

Test Your Knowledge

In Example A, why was 4 mm² rejected even though Iz after derating was adequate for a 20 A breaker?

A
B
C
D
Test Your Knowledge

For the three-phase warehouse submain, which voltage should be used when converting the Clause 3.6 5% limit into volts for a phase-to-phase drop check?

A
B
C
D
Test Your Knowledge

After upsizing a cable solely to pass voltage drop, what must you do next in the selection order?

A
B
C
D