Per OSHA 1926.1404, every crane lift on a construction site must have a designated:
Nccco Lift Director Role And Authority
Question · Easy
Which statement BEST describes the relationship between the Lift Director and the crane operator?
Question · Medium
Chapter 1: Ground Conditions, Site Access & Matting
1.1 Ground & Subsurface Evaluation
Study guide
Before the first pick of the day, the Lift Director should ensure that the lift plan has been:
Nccco Lift Director Pre Lift Planning
Trades Exam Prep Podcast
Listen on Spotify
Podcast
Under OSHA 1926.1408, the minimum clearance distance from energized power lines rated up to 50 kV during crane operations is:
Nccco Lift Director Power Line Safety
OSHA 1926.1408 lists four options for working near power lines. Which option is generally considered the MOST preferred?
Question · Hard
A planned lift will exceed 75% of the crane's rated capacity at the working radius. The Lift Director should treat this as:
Nccco Lift Director Critical Lifts
1.2 Site Access, Travel Routes & Physical Clearances
Which document specifically addresses planning for load handling activities and is therefore most directly applicable to Lift Director duties?
Nccco Lift Director Standards
During a lift in progress, the signal person loses radio contact with the operator. The Lift Director should:
Nccco Lift Director Communication
When establishing an exclusion zone around a planned lift, the Lift Director's primary objective is to:
Nccco Lift Director Site Control
A two-crane tandem lift is planned. Which arrangement BEST reflects Lift Director responsibilities?
Nccco Lift Director Multi Crane
1.3 Matting, Cribbing & Outrigger Pad Sizing
In a typical tandem lift where two cranes share a load, what is the commonly used capacity de-rating applied to each crane's rated chart?
When verifying the qualifications of riggers prior to a lift, the Lift Director should confirm that each rigger is:
Nccco Lift Director Personnel Qualifications
Wind speed at the jobsite has reached 28 mph (gust) and the manufacturer's chart limits picks to 20 mph for the planned load. The Lift Director should:
Nccco Lift Director Weather
Using the 30/30 lightning rule, work should be suspended when lightning is detected and may resume:
Chapter 2: Power Line Safety & Environmental Conditions
2.1 Power Line Safety & OSHA 1926.1408 Table A
Personnel hoisting under OSHA 1926.1431 requires the Lift Director to ensure all of the following EXCEPT:
Nccco Lift Director Personnel Hoisting
Which of the following is the BEST description of stop-work authority for a Lift Director?
Nccco Lift Director Stop Work
Before a critical lift, the Lift Director should ensure the lift plan has been signed by:
Ground bearing pressure under a mobile crane outrigger pad is determined primarily by:
Nccco Lift Director Ground Conditions
2.2 Operations Near Power Lines & Encroachment Prevention
The Lift Director arrives at the lift area and observes the operator skipping the daily pre-shift crane inspection. The CORRECT response is to:
Nccco Lift Director Equipment
Which is the MOST appropriate content element of a written lift plan that the Lift Director prepares or reviews?
During the lift, the load begins to rotate and a tag line operator loses control of the line. The Lift Director should FIRST:
Nccco Lift Director During Lift
Which OSHA reportable event requires notification to OSHA within 8 hours?
Nccco Lift Director Emergency Response
2.3 Environmental & Weather Hazards
OSHA inpatient hospitalization or amputation injuries must be reported to OSHA within:
The MOST important reason for the Lift Director to hold a pre-lift briefing is to:
Which document does the Lift Director typically use to confirm a load's actual weight before authorizing the lift?
When the planned lift will pass a load over a road or pedestrian area, the Lift Director should FIRST consider:
Chapter 3: Roles, Responsibilities, Hierarchy & Qualifications
3.1 Lift Director Role, Mandate & Stop-Work Authority
Which best describes the relationship between the Lift Director and the Site Supervisor?
What is the primary purpose of a trial lift on a personnel hoisting operation?
When a load is rigged but the rigging shows a damaged sling tag and unreadable working load limit, the Lift Director should:
Nccco Lift Director Rigging Inspection
Power lines in the lift area are rated at 230 kV. Per OSHA 1926.1408 Table A, the minimum clearance during operation (Option 1) is:
3.2 Site Personnel Hierarchy & Duty Boundaries
If the actual line voltage is unknown, OSHA 1926.1408 Option 1 requires the Lift Director to:
A 'blind pick' is one in which the operator cannot see the load. The Lift Director must:
Which item is NOT typically part of a critical lift plan under ASME P30 guidance?
The Lift Director sees the rigger using a shackle as a sling-to-sling connector with the pin loaded sideways. The CORRECT action is:
3.3 Qualified Rigger Standards & Scope
The signal person uses hand signals defined in which standard most commonly referenced by NCCCO?
Which scenario should the Lift Director treat as a CRITICAL lift even if the load is well under 75% capacity?
The lift area requires barricades to enforce the exclusion zone. Which is the BEST barricade choice for active rotation hazards?
When supervising a lift, the Lift Director must position themselves so they can: