ICC Journeyman Plumber Cheat Sheet

Quick Facts

Exam IDs
F25 | G25
Credential
Journeyman Plumber (ICC)
Questions
70 multiple-choice
Time
F25 3 hours; G25 4 hours
Code Basis
F25 2015 IPC; G25 2018 IPC
Pass
70%, PASS/FAIL only
Fee
$120
Format
Open book, Pearson VUE
Retake
10-day wait
Pass Rate
Not published by ICC

Test Numbers

Ten feet, five psi, fifteen minutes

Water: 10 ft headAir: 5 psiBoth: 15 minutesMetal supply air: 50 psi

F25 vs G25

F25

  • 2015 IPC
  • 3-hour limit
  • No grease slope clause

G25

  • 2018 IPC
  • 4-hour limit
  • 1/4 in grease slope

Same outline, different edition

Exam Day Logistics

F25
2015 IPC, 3 hours
G25
2018 IPC, 4 hours
Questions
70 four-option multiple-choice
Passing score
70 percent, PASS or FAIL
Retake wait
10 days after a failure
Guessing penalty
None; answer every question
Calculator
Basic non-programmable four-function only
Allowed marks
Ink notes, highlighting, attached tabs
Prohibited
Photocopies of copyrighted material
Fuel gas
Excluded; F28 adds gas

Edition Number Shift

Shower moved up, backwater valve moved down

417.4 to 421.4424.3 to 412.3715.1 to 714.1

Service vs Distribution Pipe

Water Service

  • 160 psi at 73.4 F
  • PVC permitted
  • Buried outside structure

Hot Distribution

  • 100 psi at 180 F
  • CPVC, never PVC
  • Inside the building

Cold buried vs hot inside

Must-Know Definitions

Branch interval
8 ft stack vertical length
Developed length
Along centerline through fittings
Building drain ends
30 in past exterior wall
Stack vent
Extension of the waste stack
Vent stack
Air-only vertical vent pipe
Flood level rim
Edge where receptacle overflows
Critical level
C-L mark on backflow device
No C-L marking
Bottom of device governs
Soil vs waste stack
Fecal matter vs liquid waste

Rough-In and Final Tests

DWV water test
10 ft head, 15 min
Top 10 feet
Exempt from the head
DWV air test
5 psi, 15 minutes
Air test equivalent
10 in mercury column
Plastic DWV piping
Air test prohibited; water only
Water supply test
Working pressure, 15 minutes
Air on metal supply
50 psi minimum allowed
Final smoke test
1 in water column, 15 min
Shower liner test
2 in water, 15 minutes
AAV install timing
Only after DWV test

Materials and Pressure Ratings

PVC
Water service only, never distribution
CPVC
Interior hot and cold distribution
Water service rating
160 psi at 73.4 F
Hot distribution rating
100 psi at 180 F
Lead free pipe
0.25 percent weighted average
Lead free solder
0.2 percent maximum lead
PVC primer
ASTM F656, purple colored
Copper types
K thickest, L medium, M thin

Supports and Protection

PVC/ABS DWV horizontal
4 ft spacing
PVC/ABS DWV vertical
10 ft spacing
Copper 1-1/4 in horizontal
6 ft spacing
Cast iron horizontal
5 ft, or 10 ft lengths
Cast iron vertical
15 ft spacing
Water pipe burial
6 in below frost line
Burial floor
12 in below grade minimum
Foundation penetration
Sleeve two pipe sizes larger

Plan Reading and Math

1/4 in scale
One inch equals four feet
1/8 in scale
One inch equals eight feet
Static head
0.433 psi per vertical foot
1 psi
2.31 feet of head
45-degree offset
Travel equals run times 1.414
Isometric drawing
Shows vertical runs and vents
Read off isometric
DFU, trap arms, vent heights

2015 to 2018 Renumbering

Shower compartment
417.4 becomes 421.4
Shower opening
417.4.2 becomes 421.4.2
Shower valve
424.3 becomes 412.3
Backwater valve
715.1 becomes 714.1
Chapter 4 order
Resequenced alphabetically by fixture
What changed
Numbers moved, rules unchanged

Fixture Clearance Numbers

Fifteen to the wall, thirty apart, twenty-one ahead

15 in to wall30 in center to center21 in in front

Shower Valve vs Public Lavatory

Shower Valve

  • 120 F maximum
  • ASSE 1016 valve
  • Limit stop at valve

Public Lavatory

  • 110 F maximum
  • ASSE 1070 device
  • Tempered water required

Two limits, two devices

Fixture Clearances

Centerline to wall
15 in minimum
Centerline to centerline
30 in minimum
Clear space in front
21 in minimum
Shower area
900 sq in minimum
Shower least dimension
30 in minimum
Shower exception
25 in with 1,300 sq in
Shower measure height
Up to 70 in
Shower door opening
22 in clear width
Fixture outlet to weir
24 in vertical maximum

IPC vs WaterSense Flow

IPC Table 604.4

  • Showerhead 2.5 gpm
  • Lavatory 2.2 gpm
  • Urinal 1.0 gpf

WaterSense or State

  • Showerhead 2.0 gpm
  • Lavatory 1.5 gpm
  • Urinal 0.5 gpf

Code base vs amendment

IPC Flow and Flush Limits

Showerhead
2.5 gpm at 80 psi
Private lavatory faucet
2.2 gpm at 60 psi
Public lavatory faucet
0.5 gpm at 60 psi
Metering faucet
0.25 gallon per cycle
Water closet
1.6 gallons per flush
Urinal
1.0 gallon per flush
2015 vs 2018
Identical flow and flush values
2.0, 1.5, 0.5 figures
WaterSense or state amendment

Water Heater Safety

T&P discharge size
Full size of valve outlet
Discharge termination
6 in maximum above floor
Discharge end
No threads, no valves
Discharge routing
Gravity, untrapped, one device
Never connect to
The drainage system
Pan depth
1-1/2 in minimum
Pan drain
3/4 in indirect waste
Shower valve limit
120 F, ASSE 1016
Public lavatory limit
110 F, ASSE 1070

AVB vs RPZ

AVB

  • 6 in above rim
  • No downstream valve
  • Not continuous pressure

RPZ

  • High hazard rated
  • Continuous pressure allowed
  • Backpressure and backsiphonage

Hazard and pressure decide

Backflow Device Picker

  1. High hazard, continuous pressureRPZ assembly(ASSE 1013)
  2. Low hazard, pollution onlyDouble check assembly
  3. Hose bibb or sillcockHose connection vacuum breaker(Permanently attached)
  4. No downstream valve, intermittentAtmospheric vacuum breaker(6 in above rim)
  5. Open receptor availablePhysical air gap(Cannot fail mechanically)
  6. Static pressure over 80 psiPressure-reducing valve(Creates a closed system)

Water Service and Pressure

Minimum service size
3/4 in diameter
Sewer separation
5 ft compacted earth
Sleeve alternative
5 ft each side of sewer
Vertical alternative
12 in above sewer top
PRV trigger
Static pressure over 80 psi
PRV standard
ASSE 1003 with strainer
10 ft separation
Utility rule, not IPC

RPZ vs Double Check

RPZ

  • High hazard, contamination
  • ASSE 1013 assembly

DCVA

  • Low hazard, pollution
  • Never on health hazard

Hazard class picks device

Minimum Fixture Supply Sizes

Lavatory
3/8 in
Water closet flush tank
3/8 in
Kitchen sink
1/2 in
Bathtub
1/2 in
Shower, single head
1/2 in
Hose bibb
1/2 in
Urinal flushometer
3/4 in
Water closet flushometer
1 in, the outlier

Backflow Device Rules

Air gap size
Twice the effective opening
Air gap minimum
1 in above flood rim
AVB height
6 in above flood rim
AVB downstream valve
Never permitted
AVB pressure limit
12 hours in any 24
RPZ
High hazard, continuous pressure
DCVA
Low hazard, pollution only
Hose bibb
Permanently attached vacuum breaker

Slope Ladder

Quarter, eighth, sixteenth as pipe grows

2-1/2 in: 1/4 in3-6 in: 1/8 in8 in: 1/16 inGrease upstream: 1/4 in, G25

Air Gap vs Air Break

Air Gap

  • Open space above rim
  • Twice the effective opening
  • Food equipment requires it

Air Break

  • Pipe ends below rim
  • Separation to trap seal
  • Dishwasher may use it

Above rim vs below rim

Which Slope Applies

  1. Pipe 2-1/2 in or less1/4 in per foot
  2. Pipe 3 in to 6 in1/8 in per foot(Steeper always allowed)
  3. Pipe 8 in or larger1/16 in per foot
  4. Upstream of grease interceptor1/4 in per foot(G25 only, 2018 IPC)
  5. F25, upstream of interceptorTable 704.1 slopes apply
  6. Trap arm 2 in or smaller1/4 in per foot(Table 909.1 basis)
  7. Trap arm 3 or 4 in1/8 in per foot(Table 909.1 basis)

DFU Values and Slopes

Bathroom group
5 dfu, 1.6 gpf closet
Water closet, private
3 dfu
Water closet, public
4 dfu
Lavatory
1 dfu
Bathtub, shower, kitchen sink
2 dfu each
Pipe 2-1/2 in or less
1/4 in per foot
Pipe 3 in to 6 in
1/8 in per foot
Pipe 8 in or larger
1/16 in per foot
Upstream of grease trap
1/4 in per foot, G25

Air Gap or Air Break

  1. Food-handling equipment wasteAir gap(Air break not allowed)
  2. Potable clear-water wasteAir gap
  3. Commercial dishwashing machineAir gap or air break
  4. Potable water storage tankAir gap above overflow
  5. Pipe ends below flood rimAir break(Separation to trap seal)
  6. Sizing the air gapTwice the effective opening(No 1-in floor here)

Cleanouts, Sumps, Backwater

Cleanout interval
100 ft, all pipe sizes
Direction change
Cleanout over 45 degrees
Stack base
Cleanout at the foot
Drain meets sewer
Cleanout near that junction
Clearance, 6 in pipe
18 in in front
Clearance, 8 in pipe
36 in in front
Sewage sump pit
18 in wide, 24 deep
Sump cover
Gas-tight, removable, vented
Discharge valve order
Check valve, then full-open
Ejector solids
2 in spheres with closets
Backwater valve trigger
Floor below upstream manhole cover
Above that elevation
Must bypass the valve

Which Cleanout Is Required

  1. Horizontal run over 100 ftCleanout at 100 ft intervals
  2. Direction change over 45 degreesCleanout at the fitting
  3. Base of a waste stackCleanout at stack base
  4. Building drain meets sewerCleanout near that junction
  5. Pipe 6 in or smaller18 in clearance in front
  6. Pipe 8 in or larger36 in clearance in front
  7. Backwater valve installedAccessible cleanout for service

Trap Arm Ladder

Bigger trap arm buys a longer run

1-1/4 in = 5 ft1-1/2 in = 6 ft2 in = 8 ft3 in = 12 ft4 in = 16 ft

Vent Stack vs Stack Vent

Vent Stack

  • Carries air only
  • Required at 5 intervals
  • Connects at stack base

Stack Vent

  • Extends the waste stack
  • Above highest drain connection
  • Terminates through roof

Separate pipe vs extension

Vent Method Picker

  1. One fixture trapIndividual vent(Half the drain served)
  2. Two traps, one fittingCommon vent
  3. Bathroom group, one branchWet vent
  4. Battery of 2-8 fixturesCircuit vent
  5. Island sink, no wallIsland fixture vent
  6. No roof penetration possibleAir admittance valve(One open vent required)
  7. Stack has 5 branch intervalsVent stack required

Vent Sizing and Terminals

Individual vent size
Half the drain served
Absolute minimum vent
1-1/4 in
Vent over 40 ft
Increase one nominal size
Vent stack trigger
5 or more branch intervals
Trap to vent, 1-1/4 in
5 ft maximum
Trap to vent, 1-1/2 in
6 ft maximum
Trap to vent, 2 in
8 ft maximum
Trap to vent, 3 in
12 ft maximum
Trap to vent, 4 in
16 ft maximum
Terminal near opening
10 ft, or 3 ft above
Promenade roof
7 ft above the roof
Plain roof height
Bracketed; jurisdiction fills in
Frost closure areas
Increase to 3 in diameter

Trap Seal Window

Two to four inches, never deeper

2 in minimum4 in maximumDeeper holds solidsShallower gets siphoned

Trap Rules

Trap seal depth
2 in to 4 in
Deeper than 4 in
Holds solids, not self-scouring
Prohibited traps
S, bell, crown-vented, drum
Also prohibited
Moving-part and partition traps
Building trap
Prohibited, no exception
Drum trap exception
Solids interceptor or chemical waste
Trap arm fall
Not over one pipe diameter
Fixture outlet to weir
24 in vertical, 30 horizontal

Interceptors and Separators

Grease interceptor
Receives FOG-bearing kitchen waste
Water closet waste
Never into grease interceptor
Upstream slope, G25
1/4 in per foot minimum
Upstream slope, F25
Table 704.1 slopes govern
Oil separator
Garages and fuel facilities
Oil separator venting
Separate vapor vent required
Sand interceptor
Grit from wash-down areas
Chemical waste
Independent system, neutralize first

Storm Drainage Rules

Storm to sanitary
Prohibited under the IPC
Combined public sewer
Connect storm independently, trapped
Design basis
100-year, one-hour rainfall
Secondary drainage
Required where parapets trap water
Secondary inlet height
2 in above roof low point
Subsoil drains
Storm system, never sanitary

Common Traps

Flow rates did not change

IPC showerhead is 2.5 gpm 2.0 gpm is WaterSense

Urinal flush volume

IPC urinal is 1.0 gpf 0.5 gpf is an amendment

Lavatory faucet flow

Private lavatory is 2.2 gpm 1.5 gpm is an amendment

Renumbering is not rule change

417.4 became 421.4 Requirements stayed identical

Building traps are banned

Building trap prohibited outright Not the same as interceptor

Deeper trap seals are worse

Over 4 in holds solids 2 to 4 in only

Water service is not distribution

PVC for service only CPVC for interior hot

Sewer separation is 5 feet

IPC requires 5 ft 10 ft is a utility rule

Burial needs both numbers

6 in below frost line 12 in below grade

Cleanout clearance is IPC-specific

IPC uses 18 and 36 in The 12 in split is UPC

Vent stack vs stack vent

Vent stack carries air Stack vent extends waste stack

Bathroom group is discounted

Group equals 5 dfu Less than summing parts

Individual vent sizes off drain

Half the drain served Not the trap arm

Last Minute

  1. 1.70 questions, open book
  2. 2.F25 3 hours; G25 4 hours
  3. 3.Pass is 70 percent
  4. 4.Retake wait is 10 days
  5. 5.Administration is 40 percent
  6. 6.Slopes drop: quarter, eighth, sixteenth
  7. 7.Trap seal 2 to 4 in
  8. 8.Cleanouts every 100 ft
  9. 9.Air gap is twice opening
  10. 10.Showerhead 2.5 gpm, not 2.0
  11. 11.Water test: 10 ft, 15 min
  12. 12.No air test on plastic
  13. 13.Vent stack at 5 intervals
  14. 14.Storm never enters sanitary sewer
  15. 15.Building traps are prohibited
  16. 16.PVC service only; CPVC hot
  17. 17.Tab Tables 604.4, 704.1, 709.1