Cheat sheet

CCM (Certified Construction Manager) Cheat Sheet

Program & Project Management

20%of exam

Delivery MethodsProject PhasesProgram MgmtStakeholder Mgmt

Cost Management

10%of exam

Estimating & BudgetingEarned Value MgmtGMPContingency

Time Management

10%of exam

Contract Administration

10%of exam

Quality Management

10%of exam

QA and QCMock-UpsCommissioningNon-Conformance

Safety Management

10%of exam

Safety ProgramOSHAJHAPPE

Risk Management

10%of exam

Professional Practice

10%of exam

Ethics and RolesCMAA StandardsRIC ExperienceFiduciary Duty

Sustainability

5%of exam

Sustainability PracticesLEEDLife-Cycle AssessmentWaste Mgmt

Technology

5%of exam

CM Technology ToolsBIMClash DetectionDigital Twin

Quick Facts

Exam
CCM
Credential
Certified Construction Manager
Questions
175 total (150 scored)
Time
240 min (4 hrs)
Pass Score
72%
Format
CBT via PSI
Level
Advanced (RIC experience req.)
Blueprint
CMCI Handbook v4.1 (2021)

Delivery Method Risk Spectrum

DBB -> CMAR -> Design-Build -> IPD

DBB: most separationCMAR: CM joins earlyDB: single responsibilityIPD: shared risk and reward

CMAR vs Design-Build

CMAR

  • CM at risk
  • Separate designer contract
  • GMP set after design

Design-Build

  • Single combined contract
  • Design and build merged
  • One point of responsibility

Two contracts versus one

Delivery Method Picker

  1. Owner wants fixed priceDBB(Design finished first)
  2. Need speed and GMP controlCMAR(CM joins during design)
  3. Single point of responsibilityDB(One contract, one entity)
  4. Max collaboration and shared riskIPD(Multi-party shared agreement)
  5. Owner self-manages trade contractsMulti-Prime(Separate direct contracts)

Delivery Methods

DBB
Sequential design-bid-build
DB
Single design-build contract
CMAR
CM-at-risk with GMP
CM Agency
CM acts as agent
IPD
Shared risk and reward
Multi-Prime
Owner holds separate contracts
DBOM
Design-build-operate-maintain

Project Phases

Pre-Design
Feasibility and programming
Schematic Design
Early concept design
Design Development
Refine design details
Construction Documents
Bid-ready drawings and specs
Procurement
Bid and award
Construction Phase
Build and control
Closeout
Punch list and turnover
Post-Occupancy
Warranty and evaluation

Program and Stakeholder Mgmt

Program Mgmt
Multi-project oversight
PMP
Project management plan
WBS
Work breakdown structure
Stakeholder Mgmt
Engage all parties
Owner's Rep
Acts for owner

EVM Core Formulas

CV=EV-AC | SV=EV-PV | CPI=EV/AC | SPI=EV/PV

CV: cost varianceSV: schedule varianceCPI: cost efficiencySPI: schedule efficiency

CPI vs SPI

CPI

  • Measures cost efficiency
  • EV divided by AC

SPI

  • Measures schedule efficiency
  • EV divided by PV

Cost versus schedule

Cost Variance Response

  1. CPI below 1.0Investigate cost overrun(Spending more than earned)
  2. SPI below 1.0Investigate schedule slip(Behind planned progress)
  3. CPI and SPI both lowEscalate to owner(Recovery plan needed)
  4. EAC exceeds approved budgetRequest change order(Reforecast completion cost)

Estimating and Budgeting

ROM Estimate
Rough order of magnitude
Conceptual Estimate
Early, low detail
Detailed Estimate
Quantity takeoff based
GMP
Guaranteed maximum price
Contingency
Reserve for unknowns
Life-Cycle Cost
Total ownership cost

Earned Value Management

PV
Planned value (BCWS)
EV
Earned value (BCWP)
AC
Actual cost (ACWP)
CPI
Cost performance index
SPI
Schedule performance index
CV
EV minus AC
SV
EV minus PV
EAC
Forecast final cost

Schedule Levels

Master -> Baseline -> Look-ahead -> Daily

Master: whole projectBaseline: approved planLook-ahead: two to six weeksDaily: field execution

Critical Path vs Float

Critical Path

  • Zero float
  • Longest duration path
  • Delay delays whole project

Float

  • Slack time available
  • Can delay safely
  • Non-critical activities only

No slack versus slack

Schedule Delay Response

  1. Owner-caused delay occursTime extension granted(Excusable and compensable)
  2. Contractor-caused delay occursNo time extension(Non-excusable delay)
  3. Weather beyond normal rangeExcusable, non-compensable delay(Time only, no cost)
  4. Need faster completion dateCrash or fast-track(Adds cost or risk)

CPM Scheduling

CPM
Critical path method
Critical Path
Longest, zero-float path
Float
Slack before delay
Free Float
Delay without successor impact
Total Float
Delay without finish impact
Predecessor
Must-precede activity
Milestone
Zero-duration marker
Fast-Tracking
Overlap sequential phases
Crashing
Add resources, shorten

Schedule Formats

Gantt Chart
Bar chart timeline
PDM
Precedence diagram method
Look-Ahead Schedule
Short-term 2-6 weeks
Baseline Schedule
Approved original plan
Schedule Update
Progress versus baseline
Delay Analysis
TIA or as-built

RFI vs Submittal

RFI

  • Clarifies design intent
  • A question, not approval

Submittal

  • Shop drawings or product data
  • Confirms spec compliance

Ask versus confirm

Contract Types

Lump Sum
Fixed total price
Unit Price
Price per unit
Cost-Plus-Fee
Cost plus fixed fee
GMP Contract
Cost-plus with a cap
T&M
Time and materials

Contract Administration

RFI
Request for information
Submittal
Shop drawing review
Change Order
Approved scope or cost change
PCO
Potential change order
ASI
Architect's supplemental instruction
Notice to Proceed
Start authorization
Punch List
Final defect list
Retainage
Withheld payment percent

QA vs QC

QA

  • Process-focused
  • Prevents defects
  • Ongoing procedures

QC

  • Product-focused
  • Detects defects
  • Inspection and testing

Prevent versus detect

QA and QC

QA
Process-focused prevention
QC
Product-focused inspection
Mock-Up
Sample for approval
Commissioning
Verify systems perform
Non-Conformance
Work fails specification
ITP
Inspection and test plan

Safety Program

OSHA
Federal safety regulator
JHA
Job hazard analysis
Competent Person
OSHA-authorized hazard identifier
Toolbox Talk
Daily safety briefing
PPE
Personal protective equipment
OSHA 300 Log
Injury and illness log
Fall Protection
Required above six feet

Risk Response Options

Avoid, Transfer, Mitigate, or Accept

Avoid: eliminate exposureTransfer: insurance or contractMitigate: reduce impactAccept: retain and monitor

Bid Bond vs Performance Bond

Bid Bond

  • Guarantees bid is honored
  • Protects before contract award

Performance Bond

  • Guarantees full completion
  • Protects after contract award

Before award versus after

Risk Response Selection

  1. Risk is high and avoidableAvoidance(Eliminate the exposure)
  2. Risk transferable to third partyTransfer(Insurance or subcontract)
  3. Risk manageable in-houseMitigation(Reduce likelihood and impact)
  4. Risk is low impactAcceptance(Retain and monitor)

Risk Management Process

Risk ID
Find potential risks
Risk Register
Log of tracked risks
Mitigation
Reduce likelihood and impact
Transfer
Insurance or contract
Avoidance
Eliminate the exposure
Acceptance
Retain known risk
Contingency Reserve
Cost and time buffer

Insurance and Bonds

Builder's Risk
Property damage coverage
GL Insurance
General liability coverage
Bid Bond
Guarantees bid commitment
Performance Bond
Guarantees contract completion
Payment Bond
Guarantees sub and supplier pay
Indemnification
Shifts liability by contract

Ethics and Roles

CCM Ethics
Conditions and Conduct agreement
RIC
Responsible-in-charge experience
Fiduciary Duty
Act in owner's interest
Standard of Care
Reasonable professional skill level
CMAA SOP
Standards of Practice

Sustainability Practices

LEED
USGBC green building rating
Life-Cycle Assessment
Environmental impact review
Commissioning Agent
Verifies green performance
Waste Mgmt Plan
Reduce and recycle debris
Energy Modeling
Predicts building performance

CM Technology Tools

BIM
3D model coordination
Clash Detection
Model conflict check
CDE
Common data environment
PM Software
Procore, e-Builder, etc.
Drone Survey
Aerial progress monitoring
Digital Twin
Virtual asset replica

Common Traps

QA ≠ QC

QA prevents defects proactively QC detects defects reactively

Float ≠ Critical Path

Float allows scheduling slack Critical path has zero slack

CMAR ≠ Design-Build

CMAR keeps designer separate Design-Build merges into one contract

RFI ≠ Submittal

RFI asks a question Submittal confirms spec compliance

Mitigation ≠ Avoidance

Mitigation reduces risk impact Avoidance eliminates risk entirely

CPI ≠ SPI

CPI measures cost performance SPI measures schedule performance

Bid Bond ≠ Performance Bond

Bid bond covers pre-award Performance bond covers post-award

Last Minute

  1. 1.Ten domains, PPM heaviest at 20%
  2. 2.175 questions total, 150 scored
  3. 3.240 minutes, 72% passing score
  4. 4.CBT delivered via PSI, not Prometric
  5. 5.CPI or SPI below 1.0 warns
  6. 6.Critical path activities have zero float
  7. 7.QA prevents; QC detects defects
  8. 8.CMAR joins early; Design-Build merges roles
  9. 9.RFI asks; submittal confirms compliance
  10. 10.Avoid, transfer, mitigate, or accept risk
  11. 11.Retainage withholds a payment percentage
  12. 12.CCM recertifies every three years