All Practice Exams

151+ Free CCM Practice Questions

Pass your Certified Construction Manager exam on the first try — instant access, no signup required.

✓ No registration✓ No credit card✓ No hidden fees✓ Start practicing immediately
Not publicly disclosed Pass Rate
151+ Questions
100% Free
1 / 151
Question 1
Score: 0/0

During the pre-construction phase, what is the primary purpose of a constructability review?

A
B
C
D
to track
2026 Statistics

Key Facts: CCM Exam

175

Exam Questions

CMAA

4 hours

Exam Time

CMAA

$275

Exam Fee

CMAA

The CCM exam is a 4-hour, 175-question exam that covers the full breadth of construction management practice. The exam is not easy, but with the right preparation, you can pass on your first attempt. The CCM is a valuable credential that can help you advance your career and increase your earning potential.

Sample CCM Practice Questions

Try these sample questions to test your CCM exam readiness. Each question includes a detailed explanation. Start the interactive quiz above for the full 151+ question experience with AI tutoring.

1During the pre-construction phase, what is the primary purpose of a constructability review?
A.To finalize the project budget.
B.To identify and resolve potential construction issues before they arise.
C.To select the primary construction contractor.
D.To secure all necessary building permits.
Explanation: A constructability review is a critical process during the design and planning stages. It involves a detailed analysis of the construction documents to identify potential obstacles, conflicts, or inefficiencies that could impede construction, increase costs, or lower quality. By addressing these issues proactively, the project team can save significant time and money. While the review may influence the budget and contractor selection, its primary goal is issue resolution.
2Which project delivery method places the owner in a single contract with a design-build entity for both design and construction services?
A.Design-Bid-Build (DBB)
B.Construction Manager at Risk (CMAR)
C.Design-Build (DB)
D.Integrated Project Delivery (IPD)
Explanation: The Design-Build (DB) delivery method is characterized by a single point of responsibility for the owner. The owner contracts with one entity, the design-builder, who is responsible for both the design and construction of the project. This contrasts with Design-Bid-Build, where the owner has separate contracts with the designer and the contractor.
3What is the critical path in a project schedule?
A.The sequence of tasks that has the longest duration.
B.The most expensive sequence of tasks.
C.The tasks with the highest risk.
D.The shortest possible time to complete the project.
Explanation: The critical path is the longest sequence of dependent tasks in a project schedule. The duration of the critical path determines the shortest possible duration for the entire project. Any delay to a task on the critical path will delay the project completion date. Tasks not on the critical path have 'float' or 'slack' and can be delayed to some extent without affecting the project deadline.
4A contractor submits a claim for additional compensation due to unforeseen site conditions. What is the first step the construction manager should take?
A.Reject the claim immediately.
B.Approve the claim to avoid delays.
C.Review the contract documents for a differing site conditions clause.
D.Negotiate a lower amount with the contractor.
Explanation: When a contractor submits a claim for differing site conditions, the construction manager must first consult the contract. Most construction contracts contain a 'Differing Site Conditions' or 'Unforeseen Conditions' clause that outlines the procedures for handling such claims. The CM must follow these procedures, which typically involve investigating the claim, notifying the owner, and evaluating the claim's validity based on the contract terms.
5Which of the following is an example of a lagging indicator for safety performance?
A.Number of safety training hours.
B.Results of safety audits.
C.Number of near-miss incidents reported.
D.OSHA recordable incident rate.
Explanation: Lagging indicators measure past performance and outcomes. The OSHA recordable incident rate is a classic example of a lagging indicator because it measures the number of incidents that have already occurred. Leading indicators, in contrast, are proactive measures that can predict future safety performance, such as safety training hours, audit results, and near-miss reporting.
6What is the primary purpose of a Request for Information (RFI)?
A.To request a change in the project scope.
B.To clarify ambiguities or missing information in the contract documents.
C.To submit a claim for additional payment.
D.To formally accept a completed phase of the project.
Explanation: An RFI is a formal written process used by contractors to ask for clarification of the plans, specifications, or other contract documents. RFIs are essential for resolving uncertainties before they lead to costly mistakes or disputes. While an RFI response might lead to a change order, the primary purpose of the RFI itself is to seek clarification, not to request a change.
7In value engineering, what is the primary focus?
A.Reducing costs by using lower-quality materials.
B.Improving the project's aesthetic appeal.
C.Achieving the required function at the lowest life-cycle cost.
D.Accelerating the project schedule.
Explanation: Value engineering is a systematic method to improve the 'value' of a project by analyzing its functions. The core principle is to achieve the essential functions at the lowest life-cycle cost without sacrificing quality, reliability, performance, or safety. It's about finding the best balance between cost, function, and quality, not just cutting costs.
8Which type of insurance protects the owner against losses arising from the contractor's failure to complete the project?
A.Commercial General Liability (CGL)
B.Builder's Risk
C.Workers' Compensation
D.Performance Bond
Explanation: A performance bond is a type of surety bond, not an insurance policy in the traditional sense, but it serves a similar purpose. It is issued by a surety company to guarantee the contractor's performance. If the contractor defaults, the surety can either complete the project or provide funds for the owner to do so. Builder's Risk covers damage to the project itself, CGL covers third-party claims, and Workers' Compensation covers employee injuries.
9What does a 'pay-when-paid' clause in a subcontract typically mean?
A.The subcontractor will be paid within 30 days of invoicing.
B.The general contractor is not obligated to pay the subcontractor until the owner pays the general contractor.
C.The subcontractor is paid directly by the project owner.
D.The subcontractor assumes all risk of owner non-payment.
Explanation: 'Pay-when-paid' clauses are common in subcontracts and make the general contractor's receipt of payment from the owner a condition for paying the subcontractor. A stricter version, the 'pay-if-paid' clause, can shift the entire risk of owner non-payment to the subcontractor. The enforceability of these clauses varies by jurisdiction.
10What is the primary goal of a quality assurance (QA) program in construction?
A.To inspect and test completed work to ensure it meets specifications.
B.To establish processes and procedures to prevent defects from occurring.
C.To punish contractors for poor-quality work.
D.To document all construction defects for legal purposes.
Explanation: Quality Assurance (QA) is a proactive process focused on preventing defects. It involves establishing a system of procedures, standards, and policies to ensure that quality is built into the project from the start. Quality Control (QC), on the other hand, is a reactive process focused on identifying defects through inspection and testing of the completed work. A comprehensive quality management program includes both QA and QC.

About the CCM Exam

The Certified Construction Manager (CCM) credential is the gold standard for professionals in the construction management field. It is awarded by the Construction Management Association of America (CMAA).

Questions

175 scored questions

Time Limit

4 hours

Passing Score

Not publicly disclosed

Exam Fee

$275 (CMAA)

CCM Exam Content Outline

19%

Contract Administration

Contract law, risk allocation, and dispute resolution

16%

Time Management

Scheduling, sequencing, and schedule control

15%

Cost Management

Estimating, budgeting, and cost control

15%

Project Management

Planning, execution, and project controls

11%

Quality Management

Quality assurance, quality control, and commissioning

9%

Professional Practice

Ethics, leadership, and professional development

How to Pass the CCM Exam

What You Need to Know

  • Passing score: Not publicly disclosed
  • Exam length: 175 questions
  • Time limit: 4 hours
  • Exam fee: $275

Keys to Passing

  • Complete 500+ practice questions
  • Score 80%+ consistently before scheduling
  • Focus on highest-weighted sections
  • Use our AI tutor for tough concepts

CCM Study Tips from Top Performers

1Focus on the 'Big 4' domains: Contract Administration, Time Management, Cost Management, and Project Management. Together, they account for 65% of the exam.
2Understand the different project delivery methods and contract types.
3Review the CMAA Standards of Practice.
4Complete as many practice questions as possible to familiarize yourself with the format and style of the exam questions.

Frequently Asked Questions

How many questions are on the CCM exam?

The CCM exam contains 175 multiple-choice questions. 150 are scored, and 25 are unscored pre-test questions. You have 4 hours to complete the exam.

What is the passing score for the CCM exam?

The passing score for the CCM exam is not publicly disclosed by the CMAA. It is a scaled score based on the difficulty of the questions.

How much does the CCM exam cost?

The CCM exam fee is $275. There is a $100 re-take fee if you do not pass on your first attempt.