Cheat sheet

API 1169 Pipeline Construction Inspector Cheat Sheet

Quick Facts

Exam
API 1169
Scope
New onshore pipeline construction
Time
3 hours
Format
Multiple choice
Questions
115 total, 100 scored
Pretest
15 unscored questions
Passing score
400 on 200–500 scale
Delivery
In-person computer exam
Personal references
Prohibited
Onscreen references
Selected government excerpts
Effectivity window
Dec 2026 – Aug 2027

OSHA Part Numbers

1910 industry, 1926 construction

1910 general industry1926 Subpart P excavations

Onscreen vs Study References

Onscreen excerpts

  • Government documents
  • Listed on effectivity page two

Study publications

  • API standards and other publications
  • Unavailable inside the test viewer

Check which references are provided

Exam Reference Picker

  1. Need tested editions→Use the effectivity sheet(Match your exam window)
  2. Need tested topic areas→Use the Body of Knowledge(Five main categories)
  3. Question specifies OSHA→Use the OSHA excerpt(Match the cited topic)
  4. Choosing a welding study reference→API 1104 or CSA Z662:23(Exam tests overlapping content)
  5. U.S. gas pipeline construction→Use 49 CFR 192(Construction in Subpart G)
  6. U.S. hazardous liquid construction→Use 49 CFR 195(Construction in Subpart D)
  7. Need U.S. wetland procedures→Find the FERC PDF(May 2013 exam reference)
  8. Need to navigate test PDFs→Practice with API tutorial(Ctrl+F unavailable)

Study Publications

API RP 1169
Construction inspection2nd edition
API RP 1110
Steel pipeline pressure testing7th edition, appendices excluded
API Spec Q1
Quality management systems10th edition, §§ 3–5
API Spec Q1 updates
Addenda 1–2 and Errata 1–3
CGA Best Practices
Underground damage preventionCurrent edition
INGAA CS-S-9
Pressure test safetyDecember 2018
API Std 1104
Welding, inspection and acceptance22nd edition, §§ 3–11
API Std 1104 update
Errata 1September 2023
CSA Z662:23
Canadian pipeline systems standardChs. 1, 2, 4, 6–10

Shoring vs Shielding

Shoring

  • Supports excavation sides
  • Designed to prevent cave-ins

Shielding

  • Withstands cave-in forces
  • Protects workers inside

Support walls vs protect occupants

Exam Screen References

49 CFR 192
U.S. gas pipeline safety
49 CFR 195
U.S. hazardous liquid pipeline safety
29 CFR 1910
OSHA general industry standards
29 CFR 1926
OSHA construction standards
FERC May 2013 Procedures
Wetland and waterbody mitigation
50 CFR 21
U.S. migratory bird permits
Canada OHS Regulations
Federal occupational safetySOR 86-304
Migratory Birds Convention Act
Canadian migratory bird protection1994
PDF viewer
Ctrl+F unavailable

Quality Records

Inspector role
Observe, verify, document, report
Controlled drawing
Verify current approved revision
Daily inspection report
Record observations and test results
Material traceability
Link markings to material records
Nonconformance report
Document unmet requirement and disposition
Calibration record
Verify instrument calibration status
Qualification records
Verify credentials for assigned work

Site Safety

OSHA competent person
Identifies hazards, authorized to act
OSHA trench egress
≥4 ft deep, ≤25 ft laterally29 CFR 1926.651(c)(2)
OSHA cave-in protection
Protective system unless exception applies29 CFR 1926.652
Stable rock exception
Excavation entirely in stable rock
Under 5 ft exception
Competent person finds no cave-in risk
Shoring
Supports excavation walls
Shielding
Protects workers inside the shield
After rainstorm
Competent person reinspectsWhen employee exposure is anticipated
Pressure test exclusion zone
Control access during pressurization

Route and Work Limits

Stake the route, mark utilities

Alignment shows proposed routeLine list records parcel commitments

Survey Stakes vs Utility Marks

Survey stakes

  • Mark proposed route
  • Show construction limits

Utility marks

  • Mark estimated existing location
  • Verify exact location near excavation

Proposed alignment vs existing facilities

Before Ground Disturbance

  1. Clearing limits unclear→Check approved alignment sheets(Include temporary workspace)
  2. Parcel restrictions unclear→Check the line list(Verify landowner commitments)
  3. Existing utility nearby→Safely verify exact location(Before digging near it)
  4. Crossing conditions unclear→Check crossing permit or agreement(Confirm method and limits)
  5. Runoff control needed→Check SWPPP and selected BMPs(Verify controls in place)

Alignment and Access

Right of way (ROW)
Corridor for pipeline work
Alignment sheet
Route, stationing and special conditions
Survey stakes
Mark designed location and limits
PI
Point of intersection
Line list
Parcel-specific requirements and commitments
Utility locate marks
Indicate estimated facility location
Crossing permit
Work conditions at regulated crossings
Topsoil segregation
Save topsoil separately for restoration

Environmental Controls

SWPPP
Stormwater pollution prevention plan
BMP
Best management practice
Silt fence
Intercept sediment in runoff
Topsoil stockpile
Keep separate where required
Wetland work limits
Check approved workspace and conditions
Spill response
Follow containment and reporting plan

Weld Paperwork

Procedure, proof, person

WPS directs productionPQR records procedure testsWelder qualification covers personnel

WPS vs PQR

WPS

  • Tells welders how to weld
  • Specifies production variables

PQR

  • Records qualification test variables
  • Records qualification test results

Instructions vs qualification evidence

Installation Inspection Checks

  1. Pipe joint at wrong station→Check tally against alignment(Verify grade and wall thickness)
  2. Pipe identity cannot be traced→Flag and segregate the joint(Follow project disposition process)
  3. Production welding about to start→Check WPS and welder qualifications(Verify applicable ranges)
  4. Weld indication reported→Apply governing acceptance criteria(Document disposition by weld ID)
  5. Holiday found before lowering→Verify repair and retest(Follow coating procedure)
  6. Tie-in spool cut→Verify transferred material identifiers(Update tie-in tally)

Stringing and Bending

Stringing
Lay joints along route
Pipe tally
Track joint identifiers and placement
Heat number
Links pipe to steel heat
Pipe number
Identifies the individual joint
Material check
Match grade, wall, coating
Ovality
Departure from circular cross-section
Bend acceptance
Check wrinkles, ovality, coating damage
Bend record
Record angle and installed location

Weld NDE vs Holiday Testing

Weld NDE

  • Examines weld soundness
  • RT or UT are examples

Holiday testing

  • Checks coating continuity
  • Uses electrical detector

Weld quality vs coating continuity

Weld Inspection

WPS
Welding procedure specification
PQR
Procedure qualification record
Welder qualification
Documents personnel qualification range
Fit-up
Check root gap and alignment
Preheat
Check before welding begins
Interpass temperature
Check between weld passes
NDE or NDT
Nondestructive examination or testing
RT
Radiographic testing
UT
Ultrasonic testing
Repair record
Trace repair and follow-up examination

Crossings and Trenching

Crossing agreement
Owner conditions and method constraints
Ditch profile
Check depth, width and support
Underground clearance
Separation from adjacent structures
Depth of cover
Distance from pipe top to surface
Cased crossing
Carrier pipe within protective casing
HDD
Horizontal directional drilling
HDD inspection
Track drill path and fluids

Coating and Lowering

Field joint coating
Protects exposed girth weld area
Surface preparation
Check cleanliness and profile
Dry film thickness
Measure thickness of dry coating
Holiday
Discontinuity in protective coating
Jeeping
Electrical check for coating holidays
Padding
Protect pipe from coarse material
Lowering-in
Check lift plan and pipe support
Tie-in
Connects adjoining pipe sections
Tie-in tally
Record pipe ID and cut length

Pressure Test Records

Section, instrument, chart

Identify test limitsVerify calibrationCapture time and pressure

Coating vs Cathodic Protection

External coating

  • Physical corrosion barrier
  • Check damage and holidays

Cathodic protection

  • Uses protective current
  • Verify anodes and test leads

Barrier and electrochemical protection

Back-End Verification

  1. CP leads installed→Verify and record connections(Match approved CP drawings)
  2. Actual route differs from drawing→Capture survey and redline(Record actual conditions)
  3. Hydrotest about to start→Check instruments and exclusion zone(Follow approved test plan)
  4. Pressure drops during hold→Flag and record the change(Evaluate under test procedure)
  5. Bore restriction suspected→Check gauging results(Review plate condition)

Burial and Restoration

Selected backfill
Protect pipe and coating
Compaction
Verify project density requirements
Backfill crown
Allowance for settlement where specified
Buoyancy control
Check weight placement and spacing
Topsoil replacement
Restore segregated surface soil
Bank stabilization
Protect restored waterbody banks
Revegetation
Restore cover per project requirements
Landowner restoration
Check fences and parcel commitments

Hydrotest vs Gauging

Hydrotest

  • Pressurized water
  • Checks strength and leakage

Gauging

  • Pig with gauge plate
  • Checks for internal restrictions

Pressure integrity vs bore clearance

Cathodic Protection and As-Builts

Cathodic protection (CP)
Electrochemical corrosion control
Anode bed
Supplies protective current
Test lead
Provides electrical measurement access
CP installation record
Track anodes, leads and connections
Redline
Mark field changes on drawings
As-built survey
Records actual installed location
As-built weld map
Links weld IDs and locations

Hydrotest and Pigging

Hydrostatic test
Pressure test using water
Test limits
Verify test section boundaries
Pressure chart
Records pressure over time
Test instruments
Verify calibration before testing
Intake and discharge
Check applicable permits and conditions
Cleaning pig
Removes internal debris
Gauge plate
Screens for bore restrictions
Dewatering pig
Displaces residual bulk water
Drying
Meet specified moisture criterion

Closeout Evidence

Close, reconcile, hand off

Close punch itemsReconcile inspection recordsProvide operations package

Punch List vs As-Built

Punch list

  • Outstanding deficiencies
  • Tracks closure or disposition

As-built

  • Actual installed configuration
  • Captures field deviations

Work remaining vs installed condition

Turnover Checks

  1. Parcel restoration item open→Check line list closeout(Verify completion evidence)
  2. Deficiency found on walkthrough→Log it on punch list(Track disposition)
  3. Weld record missing at turnover→Reconcile weld map and reports(Resolve record gap)
  4. Accepted segment ready for handoff→Transfer records to operations(Follow project acceptance process)

Closeout Records

Line list closeout
Verify parcel commitments were resolved
Final walkthrough
Identify remaining deficiencies
Punch list
Track unresolved work and disposition
Final inspection reports
Document completed verification
Turnover package
As-builts, tests, inspection records
Operations handoff
Transfer accepted segment and records

Common Traps

Scaled scoring

400 scaled ≠ Fixed raw percent correct

Welding alternatives

Either welding study reference ≠ Both welding study references required

Trench entry

4 ft egress trigger ≠ Cave-in protection rule

Traceability

Heat number ≠ Individual pipe number

Stormwater

SWPPP planning document ≠ BMP field control

Burial geometry

Depth of cover ≠ Total trench depth

Closeout

Passed pressure test ≠ Complete turnover package

Last Minute

  1. 1.Match effectivity to exam window
  2. 2.400 is a scaled score
  3. 3.Use OSHA for OSHA questions
  4. 4.Verify utility location before digging
  5. 5.Trace each joint to material records
  6. 6.Check procedure and welder qualifications
  7. 7.Verify coating repairs before burial
  8. 8.Map welds and cathodic protection
  9. 9.Record hydrotest pressure over time
  10. 10.Resolve and document punch items