4.10 Odor Control, Standby Power & Ancillary Plant Equipment

Key Takeaways

  • Hydrogen sulfide is generated by sulfate-reducing bacteria in the absence of dissolved oxygen and nitrate, so liquid-phase odor control works by supplying an alternative electron acceptor or by binding the sulfide chemically.
  • Biofilters treat high-volume low-concentration odorous air using microorganisms on a media bed and depend on maintaining media moisture, pH, and an empty bed residence time of roughly 30 to 60 seconds.
  • Standby generators should be exercised under load at least monthly and load-bank tested annually, because no-load running causes wet stacking in diesel engines.
  • An automatic transfer switch must be exercised and inspected regularly, since a generator that starts but a transfer switch that fails to transfer leaves the plant without power.
  • Plant air systems must be sized and dried appropriately because moisture carryover destroys pneumatic instruments and actuators faster than any other cause.
Last updated: August 2026

Odor Control, Standby Power & Ancillary Plant Equipment

The ABC Wastewater outline lists "odor control devices (e.g., biofilters, scrubbers)," "auxiliary power: generator," and "ancillary equipment: air compressors, conveyors, valves, hoists and cranes, pipes and fittings" as equipment the operator must evaluate, maintain, and operate. The water outline adds "operate and maintain onsite backup power generator" and "install and maintain facility piping."


1. Odor: Where It Comes From

The dominant odor compound in wastewater is hydrogen sulfide, generated when sulfate-reducing bacteria in a slime layer or in stagnant solids use sulfate as an electron acceptor because dissolved oxygen and nitrate are absent.

CompoundOdorThreshold
Hydrogen sulfide (H2S)Rotten egg~0.5 ppb detectable
Methyl mercaptanRotten cabbage~1 ppb
Dimethyl sulfideDecayed vegetable~1 ppb
AmmoniaPungent~5 ppm
Amines (trimethylamine)Fishy~0.4 ppb
Skatole / indoleFecalvery low

Conditions that generate sulfide: long force main detention, flat sewers with solids deposition, warm weather, high-strength or septic industrial discharge, and any anaerobic holding - a full wet well, an idle equalization basin, a gravity thickener with a deep blanket.

Where it is released: anywhere turbulence strips dissolved sulfide into the air - drop structures, the headworks, screening and grit, a force main discharge manhole, weirs, and the influent channel. This is why the odor complaint is almost always at the headworks even though the sulfide was generated miles upstream.


2. Liquid-Phase Odor Control

Treating the liquid prevents the odor from ever entering the air, and it is usually cheaper than treating the air.

MethodMechanismNotes
Nitrate (calcium or sodium nitrate)Supplies an alternative electron acceptor so sulfate reduction never occurs; also oxidizes existing sulfide biologicallyPreventive; must be dosed upstream with enough travel time
Ferric or ferrous chloridePrecipitates sulfide as insoluble iron sulfideImmediate; also aids phosphorus removal; adds solids
Hydrogen peroxideOxidizes sulfide directlyFast, short-lived
Sodium hypochloriteOxidizes sulfideEffective but expensive and creates chlorinated byproducts
pH elevation (magnesium hydroxide, caustic)Above pH 8 sulfide stays as the non-volatile bisulfide ionShifts the equilibrium rather than removing sulfide
Air or oxygen injectionMaintains aerobic conditions in the force mainWatch for air binding and for corrosion in the headspace

The pH point is worth understanding. Sulfide exists as H2S (volatile, odorous) and HS- (non-volatile) with a pKa near 7. At pH 6 nearly all sulfide is volatile H2S; at pH 8 most is bisulfide and stays in solution. Raising pH does not destroy sulfide - it just keeps it in the water.


3. Vapor-Phase Odor Control

TechnologyHow it worksBest forOperator attention
Biofilter (soil, wood chip, compost, engineered media)Microorganisms on wet media oxidize H2S and organicsHigh volume, low concentrationMoisture is everything - dry media kills the biology and channels air; also monitor pH (H2S oxidizes to sulfuric acid), media compaction, and pressure drop. Empty bed residence time of 30 to 60 seconds
Biotrickling filterSynthetic media with continuously recirculated waterHigher H2S loading, smaller footprintNutrient dosing, blowdown to control accumulated sulfate
Chemical scrubber (single or multi-stage)Packed tower with caustic and hypochlorite (and sometimes acid for ammonia)High and variable concentration; fast responseChemical inventory and safety, pH and ORP control, mist eliminator, blowdown
Activated carbon adsorberPhysical adsorption, often on impregnated carbonPolishing, low concentration, unattended sitesBed exhaustion is invisible until breakthrough; track inlet loading and change on a measured basis
Ozone / oxidation injectionOxidizes in the vapor phaseNicheOzone safety
Masking and neutralizing agentsPerfume or counteractantTemporary and political, not treatmentDoes not remove anything

Foul air collection matters as much as the treatment. Covering the odor source and drawing 6 to 12 air changes per hour under slight negative pressure is what keeps odor from escaping; a perfect scrubber on a leaky cover accomplishes nothing.

Corrosion follows odor. The same H2S that smells becomes sulfuric acid on wet concrete and metal surfaces. Odor-control decisions are also asset-protection decisions, which is how they get funded.


4. Standby Power

Components

  • Generator set - diesel or natural gas engine driving an alternator.
  • Automatic transfer switch (ATS) - senses utility loss, signals the generator to start, and transfers the load after the generator reaches voltage and frequency. On utility restoration it retransfers after a stabilization delay and then runs the generator unloaded to cool down.
  • Fuel system - day tank and bulk tank, with spill containment and, for diesel, a fuel polishing or periodic testing program.
  • Batteries and charger - the number one cause of a generator failing to start is the starting battery.
  • Block heater - keeps the engine warm so it can accept load immediately.

Exercise and testing

TestFrequencyPurpose
Visual and fluid checkWeeklyCoolant, oil, fuel level, battery, leaks, block heater
Exercise under loadMonthly, at least 30 minutesReaches operating temperature and exercises the ATS
Load bank testAnnually, typically 2 to 4 hours at 80 to 100 percent of nameplateProves full capacity and burns off deposits
Fuel quality testAnnuallyDiesel degrades, absorbs water, and grows microbial contamination

Wet stacking is the failure mode most operators create themselves. Running a diesel unloaded or lightly loaded lets unburned fuel and soot accumulate in the exhaust and on the injectors and rings, robbing power and eventually causing damage. Exercise under real load, not at no load, and load-bank the unit annually if the plant's connected load is small relative to the generator.

The ATS is as important as the generator. A generator that starts flawlessly while the transfer switch fails to transfer is the same outage as no generator at all. Exercise the ATS in transfer, not just in engine-start mode, and inspect its contacts and controls on the manufacturer's schedule.

Sizing considerations: motor starting inrush (which can be six times full-load current) governs generator sizing more often than running load does; and where a variable frequency drive is on the standby bus, the harmonics it produces must be accounted for in the alternator rating.


5. Plant Air, Conveyors and Lifting Equipment

Compressed air

Plant air drives pneumatic actuators, instruments, air-operated diaphragm pumps, and grit airlifts.

  • Moisture is the enemy. Compressed air is saturated at the compressor discharge; on cooling it condenses in the lines. Instrument air requires a dryer - refrigerated for general service (dew point about 38 degrees F), or desiccant where lines run outdoors and could freeze.
  • Drain the receiver tank automatically; a receiver half full of water has half its capacity and delivers water to every actuator.
  • Filter and regulate at each point of use; oil-free compressors are required for instrument air.
  • Receiver tanks are pressure vessels and require relief valve testing and inspection.

Conveyors

Screenings, grit, and dewatered cake conveyors are among the most dangerous equipment in a plant.

  • Guarding of nip points, and lockout before clearing a jam, are non-negotiable. Belt and screw conveyors have killed operators who reached into a running machine.
  • Emergency pull-cords the full length of the conveyor, tested regularly.
  • Screw (shaftless) conveyors for cake plug when solids are too dry or too wet; belt conveyors mistrack and need idler alignment.
  • Zero-speed switches detect a stopped belt with the drive running - the precursor to a torn belt or a fire.

Hoists and cranes

Used for pulling pumps, mixers, and screens.

  • Rated capacity marked and never exceeded; know the weight of what is being lifted.
  • Periodic inspection of hooks (throat opening, twist), chains and wire rope (broken wires, kinking, corrosion), brakes, and limit switches, with documented frequent and periodic inspections.
  • Never lift over personnel, use tag lines, and use a spotter for blind lifts.
  • Portable davit arms and their bases have specific rated loads and installation requirements, and their sockets corrode in wet environments.

Ventilation and heating

  • Classified spaces - lift station wet wells, digester gas rooms, chlorine rooms - have prescribed ventilation rates and electrical classifications.
  • Chlorine rooms require ventilation taken from near the floor because chlorine gas is heavier than air, with the switch located outside the room and a viewing window in the door.
  • Digester gas rooms require ventilation taken from near the ceiling because methane is lighter than air.
  • Freeze protection - heat tracing on sample lines, chemical lines, and instrument tubing - is the difference between a working plant and a blind one in February.
Test Your Knowledge

A force main discharging to a manhole produces severe hydrogen sulfide odor at the headworks. Which liquid-phase control acts by preventing sulfide from being generated in the first place rather than by treating sulfide already formed?

A
B
C
D
Test Your Knowledge

A standby diesel generator is exercised for 20 minutes every month with no load connected. What problem does this practice create?

A
B
C
D
Test Your Knowledge

Where must the ventilation intake be located in a chlorine gas storage room, and why?

A
B
C
D