PracticeVideosBlogFlashcards

3.5 Time, Work, Efficiency & Pipes & Cisterns

Key Takeaways

  • The LCM method assigns total work as the least common multiple of individual completion times, replacing fraction addition with integer work units.

  • Work done equals Efficiency multiplied by Time (W = E × T); efficiency and time are inversely proportional when work is held constant.

  • The chain rule formula (M1 × D1 × H1) / W1 = (M2 × D2 × H2) / W2 handles variable workforce, hours per day, and output scale.

  • Pipes and cisterns operate on identical principles to time and work, with inlet pipes performing positive work and outlet leaks performing negative work.

  • Alternate day working models require identifying complete multi-day work cycles before evaluating remaining fractional work.

Last updated: July 2026

Time, Work, Efficiency & Pipes & Cisterns

Time and Work problems test logical allocation of efficiency, combined work outputs, variable workforce chain rules, and reservoir filling/draining mechanics. Assigning arbitrary work units using the Least Common Multiple (LCM) method streamlines calculations and eliminates tedious fraction arithmetic.


1. Core Principles & LCM Method

Fundamental Equation

Work Done=Efficiency×Time  ⟹  W=E×T\text{Work Done} = \text{Efficiency} \times \text{Time} \implies W = E \times T
  • Inverse Relationship: Efficiency (EE) is inversely proportional to time (TT) required to complete a fixed task. If A takes DAD_A days, A's 1-day work efficiency is 1DA\frac{1}{D_A}.
  • LCM Unit Assignment Method:
    1. Take the LCM of all given completion times as Total Work Units (WW).
    2. Calculate individual 1-day or 1-hour work rates (units/day =Total UnitsIndividual Days= \frac{\text{Total Units}}{\text{Individual Days}}).
    3. Sum or subtract unit rates to solve combined work timelines.

2. Chain Rule & Workforce Equations

When workforce size, daily working hours, efficiency rates, and output quantities vary, use the generalized Chain Rule formula:

M1×D1×H1×E1W1=M2×D2×H2×E2W2\frac{M_1 \times D_1 \times H_1 \times E_1}{W_1} = \frac{M_2 \times D_2 \times H_2 \times E_2}{W_2}

Where MM = number of workers, DD = days, HH = hours per day, EE = efficiency factor, WW = units of work produced.


3. Pipes and Cisterns Mechanics

Pipes and Cisterns follow identical mathematical laws as Time and Work:

  • Inlet Pipe (Positive Work): Fills the tank. 1-hour rate =+1Fill Time= +\frac{1}{\text{Fill Time}}.
  • Outlet Pipe / Leak (Negative Work): Empties the tank. 1-hour rate =−1Empty Time= -\frac{1}{\text{Empty Time}}.
  • Net Filling Rate: Net 1-Hour Work=∑(Inlet Rates)−∑(Outlet Rates)\text{Net 1-Hour Work} = \sum (\text{Inlet Rates}) - \sum (\text{Outlet Rates})

4. Step-by-Step Worked Math Examples

Worked Example 1: Efficiency Ratios & Combined Work

Problem: A is 60% more efficient than B. If B alone can complete a work in 24 days, in how many days can A and B working together finish the same work?

Step-by-Step Solution:

  1. Let B's daily efficiency EB=100E_B = 100 units/day.
  2. A is 60% more efficient, so A's daily efficiency EA=100+60=160E_A = 100 + 60 = 160 units/day.
  3. Ratio of efficiency EA:EB=160:100=8:5E_A : E_B = 160 : 100 = 8 : 5.
  4. B takes 24 days, so Total Work W=EB×24=5×24=120W = E_B \times 24 = 5 \times 24 = 120 units.
  5. Combined daily efficiency of (A+B)=8+5=13(A + B) = 8 + 5 = 13 units/day.
  6. Time taken together =Total WorkCombined Efficiency=12013=9313 days= \frac{\text{Total Work}}{\text{Combined Efficiency}} = \frac{120}{13} = 9 \frac{3}{13} \text{ days}.

Worked Example 2: Alternate Day Work Strategy

Problem: A can finish a work in 10 days and B in 15 days. If they work on alternate days starting with A, in how many days will the work be completed?

Step-by-Step Solution:

  1. Take LCM of completion times (10 and 15) =30= 30 units (Total Work).
  2. A's daily rate =3010=3= \frac{30}{10} = 3 units/day.
  3. B's daily rate =3015=2= \frac{30}{15} = 2 units/day.
  4. Work cycle: Day 1 (A) =3= 3 units; Day 2 (B) =2= 2 units.
  5. 1 2-day cycle output =3+2=5= 3 + 2 = 5 units.
  6. Number of 2-day cycles required to reach 30 units =305=6= \frac{30}{5} = 6 cycles.
  7. Total time =6 cycles×2 days/cycle=12 days= 6 \text{ cycles} \times 2 \text{ days/cycle} = 12 \text{ days}.

Worked Example 3: Cistern Inlet and Leak Calculations

Problem: Pipe A can fill a tank in 12 hours, and Pipe B can fill it in 15 hours. A leak at the bottom can empty the full tank in 20 hours. If all three are opened simultaneously, how long will it take to fill the tank?

Step-by-Step Solution:

  1. Take LCM of (12,15,20)=60(12, 15, 20) = 60 units (Tank Capacity).
  2. Pipe A rate =+6012=+5= +\frac{60}{12} = +5 units/hour.
  3. Pipe B rate =+6015=+4= +\frac{60}{15} = +4 units/hour.
  4. Leak rate =−6020=−3= -\frac{60}{20} = -3 units/hour.
  5. Net filling rate per hour =+5+4−3=+6= +5 + 4 - 3 = +6 units/hour.
  6. Total time to fill tank =606=10 hours= \frac{60}{6} = 10 \text{ hours}.

5. Common Traps & Advanced Edge Cases

  • Incomplete Alternate Day Cycles: When work does not divide evenly into full 2-day cycles, evaluate remaining work units carefully. If 1 unit remains and it's A's turn (efficiency 3 units/day), add 13\frac{1}{3} of a day to the full cycle count.
  • Negative Tank Filling: If outlet leak rate exceeds inlet rate, net work is negative, causing an already filled tank to empty rather than fill.
Test Your Knowledge

A tank can be filled by an inlet pipe in 8 hours, but takes 10 hours to fill due to a leak at the bottom. How long will the leak take to empty a full tank?

A

40 hours

B

35 hours

C

45 hours

D

50 hours

Test Your Knowledge

A is twice as efficient as B. Working together, they can complete a task in 14 days. In how many days can A alone complete the task?

A

28 days

B

21 days

C

42 days

D

35 days

Test Your Knowledge

A and B can do a piece of work in 12 days and 18 days respectively. They work on alternate days starting with A. In how many days will the work be completed?

A

14 days

B

15 days

C

14.33 days

D

16 days

Test Your Knowledge

If 12 men working 8 hours a day can build a wall in 10 days, how many men working 6 hours a day can build the same wall in 16 days?

A

8 men

B

12 men

C

15 men

D

10 men

Sections you finish are checked off in the contents.