4.4 Plans Practice & Levels of Plans
Key Takeaways
- The purpose of the Plans practice is to establish structure, control, and baseline mechanisms to define how, when, and by whom products will be delivered.
- PRINCE2 defines 3 primary levels of plans: Project Plan (mandatory), Stage Plan (mandatory), and Team Plan (optional).
- An Exception Plan is prepared when a Project Plan or Stage Plan is forecast to exceed agreed tolerances, and replaces the breached plan upon approval.
- Management Stages are mandatory discrete control periods authorized one at a time by the Project Board; Technical Stages represent specialist work activities.
- PRINCE2 requires a minimum of TWO management stages: an initiation stage and at least one delivery stage.
4.4 Plans Practice & Levels of Plans
Planning is the heart of effective project control. Without a clear plan, progress cannot be measured, risks cannot be anticipated, and resources cannot be allocated efficiently. The Plans Practice in PRINCE2 7 defines how plans are structured, developed, and maintained to align with the foundational principle of Manage by stages.
Purpose of the Plans Practice
PRINCE2 7 Definition: The purpose of the Plans practice is to establish structure, control, and baseline mechanisms to define how, when, and by whom products will be delivered and performance measured.
In PRINCE2, a plan is not merely a gantt chart or activity schedule; it is a comprehensive management document that specifies targets for all seven performance aspects: Time, Cost, Scope, Quality, Risk, Benefits, and Sustainability.
The Three Primary Levels of Plans
To match planning detail with management horizons, PRINCE2 establishes three primary levels of plans corresponding to the management levels within the project team.
┌──────────────────────────────────────────────────────────┐
│ PROJECT PLAN │ (Level 2: Mandatory)
│ Overall view of entire project scope, cost, and time │ Approved by Project Board
└────────────────────────────┬─────────────────────────────┘
│ Divided into Management Stages
┌────────────────────────────▼─────────────────────────────┐
│ STAGE PLAN │ (Level 3: Mandatory)
│ Detailed plan for current management stage execution │ Used by Project Manager
└────────────────────────────┬─────────────────────────────┘
│ Decomposed into Work Packages
┌────────────────────────────▼─────────────────────────────┐
│ TEAM PLAN │ (Level 4: Optional)
│ Operational schedule for executing Work Packages │ Used by Team Manager
└──────────────────────────────────────────────────────────┘
| Plan Level | Created By | Approved By | Mandatory/Optional | Scope & Focus |
|---|---|---|---|---|
| Project Plan | Project Manager | Project Board | Mandatory | Entire project lifecycle; provides baseline for Project Board control |
| Stage Plan | Project Manager | Project Board | Mandatory | Single management stage; detailed baseline for Project Manager control |
| Team Plan | Team Manager | Project Manager | Optional | Single Work Package / specialist team scope; operational schedule |
| Exception Plan | Project Manager | Project Board (or Corporate) | Conditional | Prepares recovery baseline when stage or project tolerances are breached |
The Exception Plan Lifecycle
When a Stage Plan or the overall Project Plan is forecast to exceed agreed tolerances for time, cost, scope, quality, risk, or benefits, an Exception Situation occurs. The Project Manager escalates the issue to the Project Board via an Exception Report.
If the Project Board agrees that the stage or project cannot continue under the current plan, it instructs the Project Manager to produce an Exception Plan during the Managing a Stage Boundary (SB) process.
- Exception Plan Definition: A plan created to show how the project or stage will recover from a tolerance breach. It spans from the current point in time to the end of the stage (or project).
- Approval Authority:
- If a Stage Plan breaches tolerance, the Project Board approves the Exception Plan.
- If the overall Project Plan breaches tolerance, Corporate, Programme Management, or Customer must approve the Exception Plan.
- Baseline Replacement: Once approved, the Exception Plan replaces the existing breached Stage Plan or Project Plan to become the new official performance baseline.
Exam Tip: An Exception Plan is NOT an optional level of plan. It is a conditional plan produced only in response to a tolerance exception.
Management Stages vs. Technical Stages
A central concept in PRINCE2 planning is the distinction between Management Stages and Technical Stages.
Management Stages (Mandatory)
- Definition: Discrete partitions of the project lifecycle that the Project Board authorizes one at a time.
- Focus: Governance, commitment of funds, risk review, and business case re-verification.
- Requirement: Every PRINCE2 project MUST have at least two management stages: an Initiation Stage and at least one Delivery Stage.
Technical Stages (Optional / Advisory)
- Definition: Groupings of specialist work based on technical skillset or development method (e.g., Requirements Gathering, Architectural Design, Testing, Deployment).
- Focus: Technical sequence of execution.
- Relationship: Technical stages can cross management stage boundaries, or multiple technical stages can occur inside a single management stage.
| Aspect | Management Stage | Technical Stage |
|---|---|---|
| Primary Objective | Governance and management control | Technical product completion |
| Decision Gate | Project Board stage boundary review | Technical completion review |
| Mandatory in PRINCE2? | Yes (minimum 2 required) | No (depends on technical approach) |
| Boundary Alignment | Based on risk, cost commitment, and control | Based on technical skill sequence |
Determining Management Stage Boundaries & Planning Horizons
The Project Manager and Executive decide how to divide a project into management stages based on four key factors:
- Planning Horizon: How far into the future it is possible to accurately plan without making wild assumptions. Detailed planning beyond the planning horizon is inefficient.
- Project Risk: Higher risk periods (e.g., unproven technology or complex legal negotiations) warrant shorter management stages to allow frequent Project Board reviews.
- Financial Commitment Horizons: Aligning stage boundaries with major capital authorization decisions or vendor contract payment gates.
- Organizational Control Points: Aligning with corporate budgeting cycles or programme review milestones.
Planning in Agile Environments
In agile delivery contexts, PRINCE2 planning levels seamlessly integrate with iterative techniques:
- The Project Plan defines high-level release roadmaps and overall project tolerances.
- Stage Plans align with major release cycles or fixed timeboxes (e.g., a 2-month management stage).
- Team Plans map directly to Sprint Backlogs, Iteration Plans, or Kanban flow boards managed by self-organizing delivery teams within Work Package constraints.
What is the minimum number of management stages required in any PRINCE2 project?
What happens to the existing Stage Plan when an Exception Plan is approved by the Project Board?
How do Management Stages differ from Technical Stages in PRINCE2 7?