2.5 Principle 5: Manage by Exception
Key Takeaways
- PRINCE2 projects establish distinct tolerance limits for seven performance targets: Time, Cost, Quality, Scope, Risk, Benefits, and Sustainability.
- Authority is delegated across four management levels; each level only escalates when a forecast indicates a tolerance breach (an exception).
- An Exception Report informs the next higher management level of a forecast breach and presents options for decision.
- An Exception Plan replaces the remainder of the current plan when the Project Board authorizes recovery after an exception.
- Team Managers escalate Work Package tolerance threats to the Project Manager via issue notification and Checkpoint reporting—not Highlight Reports.
2.5 Principle 5: Manage by Exception
In traditional management environments, senior executives are frequently bombarded with routine operational updates, minor variance requests, and endless status meetings. This micro-management wastes executive time and slows down operational execution. Conversely, if executives delegate completely without controls, projects can drift off course without warning until catastrophic overruns occur.
PRINCE2 Principle 5: Manage by Exception establishes an efficient control model by setting pre-agreed boundaries—called tolerances—for project performance targets. Higher management levels delegate day-to-day authority to lower levels, intervening only when tolerances are forecasted to be exceeded.
PRINCE2 Principle Rule: A PRINCE2 project has defined tolerances for each project objective to establish limits of delegated authority.
The Seven Performance Targets (Aspects) for Tolerances
PRINCE2 7 establishes tolerances across seven project performance targets (frequently tested on Foundation exams):
+-----------------------------------------------------------------------------------+
| THE SEVEN PERFORMANCE TARGETS (ASPECTS) |
+-----------------------------------------------------------------------------------+
| 1. TIME | Permissible deviation on schedule dates (e.g. +/- 2 weeks) |
| 2. COST | Permissible deviation on financial budget (e.g. +/- $50k) |
| 3. QUALITY | Permissible variation in quality criteria metrics |
| 4. SCOPE | Permissible variation in deliverable features (e.g. MoSCoW) |
| 5. RISK | Permissible aggregated risk exposure / appetite thresholds |
| 6. BENEFITS | Permissible variation in expected outcome realization |
| 7. SUSTAINABILITY| Permissible environmental and social impact thresholds |
+-----------------------------------------------------------------------------------+
1. Time Tolerance
- Defines acceptable schedule variance. Example: "Target completion date is October 15, with a time tolerance of +1 week / -2 weeks."
2. Cost Tolerance
- Defines acceptable budget variance. Example: "Stage budget is $200,000, with a cost tolerance of +$15,000 / -$10,000."
3. Quality Tolerance
- Defines acceptable variance in physical or technical performance targets defined in Product Descriptions. Example: "System response time target is 1.8 seconds, with an acceptable quality tolerance of up to 2.2 seconds."
4. Scope Tolerance
- Defines acceptable variation in deliverables or requirements. Usually tied to prioritized features (e.g., using MoSCoW: Must Have items are mandatory; Should Have items represent scope tolerance that can be dropped if time/cost pressure arises).
5. Risk Tolerance
- Defines acceptable aggregated risk exposure for the plan. Example: "No single residual threat may exceed $40,000 exposure without Project Board review; stage risk budget $25,000."
6. Benefits Tolerance
- Defines acceptable variance in expected post-project benefits. Example: "Target operational savings of $500k/year, with a benefit tolerance of -$50k/year (minimum acceptable $450k/year)."
7. Sustainability Tolerance (Elevated in PRINCE2 7!)
- Defines acceptable thresholds for environmental and social impacts. Example: "Project carbon footprint target is 50 tonnes CO2e, with a sustainability tolerance of +5 tonnes CO2e maximum."
Delegating Tolerances Across Management Levels
Tolerances flow down through the four management levels, establishing precise boundaries of authority at each tier:
Corporate / Programme Management
│ (Sets Project Tolerances)
▼
Project Board (Directing)
│ (Sets Stage Tolerances)
▼
Project Manager (Managing)
│ (Sets Work Package Tolerances)
▼
Team Manager (Delivering)
| Management Level | Tolerances Set | Controlled By | Action if Tolerance Breached |
|---|---|---|---|
| Corporate / Programme | Project Tolerances | Corporate / Programme Management | Project Board escalates to Corporate via Exception Report. |
| Project Board | Stage Tolerances | Project Board | Project Manager escalates to Board via Exception Report. |
| Project Manager | Work Package Tolerances | Project Manager | Team Manager escalates to Project Manager via Issue / Checkpoint notification. |
The Exception Escalation Workflow
Exam Trap / Critical Rule: Escalation must occur when a tolerance is FORECASTED to be exceeded, NOT after the breach has already occurred!
If a Project Manager monitors stage progress and calculates that upcoming material delays will cause the stage to finish 10 days late (when time tolerance is +5 days), the Project Manager must not wait until day 5 of the overrun to act.
Step-by-Step Escalation Procedure:
- Detection & Forecast: Project Manager identifies that a stage or project target is forecasted to exceed agreed tolerance.
- Raise Exception Report: Project Manager creates an Exception Report detailing:
- The nature of the forecasted breach.
- Root cause analysis.
- Available options for resolution (with pros, cons, and costs for each option).
- Recommended option.
- Escalate to Project Board: Submit the Exception Report to the Project Board.
- Board Direction (Directing a Project): The Project Board reviews the report and directs an action:
- Option A: Increase tolerances to cover the variance.
- Option B: Instruct the Project Manager to submit an Exception Plan to replace the current plan.
- Option C: Terminate the project prematurely if business justification is broken.
- Execute Exception Plan: If requested, the Project Manager drafts an Exception Plan (re-planning the remainder of the stage or project). Upon Board approval, the Exception Plan baselines and replaces the old plan.
Benefits of Managing by Exception
Applying Principle 5 delivers profound organizational benefits:
- Executive Efficiency: The Project Board does not need to attend weekly operational status meetings; they receive concise Highlight Reports and intervene only when exceptions occur.
- Empowerment: Project Managers and Team Managers have clear operational autonomy to make decisions within their delegated tolerances.
- Early Warning System: Proactive forecasting ensures senior leadership is never surprised by sudden, unmanaged project failures.
Summary Matrix: Tolerances Across the 6 Aspects
| Performance Target | Typical Metric | Example Target | Permissible Tolerance | | :--- | :--- | :--- | | Time | Schedule dates / Durations | Complete Stage 2 by Dec 1 | +/- 1 Week | | Cost | Financial budget / Expenditure | Stage 2 Budget $150,000 | +$10,000 / -$5,000 | | Quality | Technical specifications | Battery life 12 hours | +/- 30 Minutes | | Scope | Feature count / Requirements | Deliver 20 user stories | Drop up to 3 "Should Have" stories | | Benefits | Operational ROI / Metrics | Reduce call volume by 25% | Minimum acceptable 20% reduction | | Sustainability | Carbon / Waste metrics | Recycling rate 90% | Minimum acceptable 85% |
In PRINCE2 7, what are the seven performance targets for which explicit tolerances are established?
A Project Manager calculates during mid-stage monitoring that stage expenditure will finish $3,000 over budget. The agreed stage cost tolerance is +$10,000. What action should the Project Manager take?
When must a Project Manager escalate an exception to the Project Board under Principle 5?