4.1 Feeder Conductor Sizing & Continuous Loads

Key Takeaways

  • Under NEC Article 100, a feeder encompasses all circuit conductors between the service equipment, the source of a separately derived system, or other power supply source and the final branch-circuit overcurrent device.

  • NEC 215.2(A)(1) mandates that feeder conductors must have an allowable ampacity not less than 100 percent of non-continuous loads plus 125 percent of continuous loads prior to the application of adjustment or correction factors.

  • After applying ambient temperature correction factors and conduit fill adjustment factors under Table 310.15(B)(1)(1) and Table 310.15(C)(1), the feeder conductor ampacity must equal or exceed the total non-continuous load plus continuous load.

  • Under NEC 220.61, the feeder neutral load is the maximum unbalanced load; a 70% demand factor is allowed for the neutral load of household ranges, ovens, cooking units, and dryers (220.61(B)(1)) and for the portion of other unbalanced load above 200 A (220.61(B)(2)), but no reduction is allowed for nonlinear loads or 3-wire circuits from a 4-wire wye (220.61(C)).

  • An Informational Note to NEC 215.2(A) recommends sizing feeder conductors to limit voltage drop to a maximum of 3 percent for the feeder alone, and a combined total of not more than 5 percent across both feeder and branch circuits for optimal operational efficiency.

Last updated: October 2026

Feeder Conductor Sizing & Continuous Loads

Feeders represent the primary distribution arteries within any commercial, industrial, or residential electrical infrastructure. They transport bulk power from the service entrance equipment or separately derived source out to secondary distribution points, lighting panels, and subpanels throughout a facility. Because an undersized feeder can throttle an entire building's electrical system, cause destructive conductor overheating, or produce excessive voltage drop that impairs motor and electronic equipment life, sizing feeder conductors accurately is one of the most rigorously tested subjects on the Kentucky Journeyman Electrician licensing examination.


1. Feeder Definition & General Requirements (NEC Article 100 & Article 215)

Article 100 Definition

To apply the National Electrical Code (NEC) correctly, an electrician must clearly distinguish feeders from service conductors and branch circuits. Under NEC Article 100, a Feeder is defined as:

All circuit conductors between the service equipment, the source of a separately derived system, or other power supply source and the final branch-circuit overcurrent device.

Key distinctions:

  • Service Conductors: The conductors from the service point to the service disconnecting means.
  • Feeder Conductors: The conductors originating at the load side of the main service disconnect (or generator/transformer secondary OCPD) and terminating at the line side of subpanel overcurrent devices.
  • Branch Circuit Conductors: The conductors extending downstream from the final overcurrent protective device to the utilization outlet(s).

Article 215 Scope & General Provisions

NEC Article 215 governs the installation requirements, minimum ampacity ratings, and conductor sizes for feeders supplying branch-circuit loads. Key baseline mandates include:

  1. Minimum Rating and Size (NEC 215.2(A)): Feeder conductors must have an ampacity sufficient to supply the connected load calculated in accordance with Parts III, IV, and V of Article 220.
  2. Identification of Ungrounded Conductors (NEC 215.12): Where a premises wiring system contains feeders supplied from more than one nominal voltage system (e.g., 120/208V 3-phase and 277/480V 3-phase), each ungrounded conductor must be identified by phase and system at all termination, connection, and splice points. Identification may be by separate color coding, marking tape, tagging, or other approved means, and an identification plaque or directory must be permanently posted at each feeder panelboard.
  3. Grounded Conductor Identification (NEC 200.6 & 215.12(A)): Grounded (neutral) conductors must comply with Article 200 (continuous white or gray finish, or three continuous white stripes on sizes 6 AWG and smaller; distinctive white or gray marking at terminations for sizes 4 AWG and larger).
  4. Equipment Grounding Conductor (NEC 215.6): Feeders must include or provide an equipment grounding conductor (EGC) sized in accordance with NEC 250.122.

2. Minimum Conductor Sizing & Continuous Loads (NEC 215.2(A)(1))

The Fundamental Sizing Rule

Under NEC 215.2(A)(1)(a), feeder conductors must have an allowable ampacity not less than the sum of the non-continuous load plus 125 percent of the continuous load:

Minimum Feeder Ampacity (Before Derating)=Non-Continuous Load+(1.25×Continuous Load)\text{Minimum Feeder Ampacity (Before Derating)} = \text{Non-Continuous Load} + (1.25 \times \text{Continuous Load})

Definition of Continuous Load (NEC Article 100)

A continuous load is defined as a load where the maximum current is expected to continue for 3 hours or more. Typical continuous loads encountered on licensing exams include:

  • Commercial lighting systems (office buildings, retail stores, educational facilities, parking lot luminaires)
  • Fixed electric space heating systems (NEC 424.4(B) sizes their conductors at 125% of the load)
  • Electric vehicle supply equipment (EVSE) charging circuits (NEC 625.41)
  • Water heaters with a capacity of 120 gallons or less (NEC 422.13 specifies that electric storage-type water heaters are considered continuous loads)

The Two-Condition Verification Process

When sizing feeder conductors that undergo ambient temperature correction or conduit fill adjustment, NEC 215.2(A)(1) mandates a rigorous two-step calculation process:

  1. Condition 1 (Minimum Size Before Derating - NEC 215.2(A)(1)(a)):
    The allowable ampacity of the selected conductor from the appropriate temperature column of NEC Table 310.16 (typically 75°C for standard distribution equipment rated over 100A or with 75°C terminals) must be equal to or greater than the non-continuous load plus 125% of the continuous load.
  2. Condition 2 (Ampacity After Derating - NEC 215.2(A)(1)(b)):
    The conductor ampacity, after applying ambient temperature correction factors (Table 310.15(B)(1)(1)) and conduit fill adjustment factors (Table 310.15(C)(1)), must be equal to or greater than the actual load served (100% of non-continuous load plus 100% of continuous load).

Step-by-Step Feeder Conductor Sizing Problem

Scenario: A commercial subpanel feeder supplies a non-continuous load of 45 amperes and a continuous lighting load of 80 amperes. The feeder will be installed in electrical metallic tubing (EMT) containing three current-carrying copper conductors in a conditioned interior space with an ambient temperature of 30°C (86°F). Terminals at both the main distribution panel and the subpanel are rated for 75°C. What is the minimum standard THHN/THWN-2 copper conductor size and the minimum standard overcurrent protective device (OCPD) rating?

Step 1: Calculate Minimum Required Ampacity (125% Continuous Rule)
Minimum Required Ampacity=45 A+(1.25×80 A)=45 A+100 A=145 Amperes\text{Minimum Required Ampacity} = 45\text{ A} + (1.25 \times 80\text{ A}) = 45\text{ A} + 100\text{ A} = \mathbf{145\text{ Amperes}}

Step 2: Conductor Selection from NEC Table 310.16
Consulting the 75°C column of NEC Table 310.16 for copper conductors:

  • 1 AWG copper is rated for 130 amperes (insufficient; 130 A<145 A130\text{ A} < 145\text{ A}).
  • 1/0 AWG copper is rated for 150 amperes (150 A≥145 A150\text{ A} \ge 145\text{ A}).

Step 3: Verify Derated Ampacity (Condition 2)

  • Actual load to be served: 45 A+80 A=125 Amperes45\text{ A} + 80\text{ A} = 125\text{ Amperes}.
  • Conduit fill adjustment (3 conductors): 1.00 (100%).
  • Temperature correction (30°C): 1.00 (100%).
  • Conductor derated ampacity: 150 A×1.00=150 A150\text{ A} \times 1.00 = 150\text{ A}, which easily exceeds 125 A.

Step 4: Select Overcurrent Protective Device (NEC 215.3 & 240.6(A))
Per NEC 215.3, the feeder overcurrent device must have a rating not less than the non-continuous load plus 125% of the continuous load (145 A145\text{ A}). Per NEC 240.6(A), standard OCPD ratings are 125A, 150A, 175A, 200A, etc. A 150-ampere circuit breaker protects the 1/0 AWG copper conductor (150 A150\text{ A} allowable ampacity) and satisfies all requirements.


3. Feeder Neutral Sizing & Load Calculations (NEC 220.61)

Feeder neutral conductors are not sized identically to phase conductors. Sizing a neutral conductor to match the phase conductors when the neutral carries only a fraction of the load is costly and wasteful. Conversely, undersizing the neutral on systems with unbalanced or harmonic loads introduces severe thermal hazards.

The Maximum Unbalanced Load Principle (NEC 220.61(A))

Under NEC 220.61(A), the feeder neutral load is defined as the maximum unbalanced load determined between the neutral conductor and any one ungrounded conductor. For 120/240V single-phase 3-wire systems or 208Y/120V 3-phase 4-wire systems, any 240V or 208V line-to-line loads (such as 3-phase motors, 240V water heaters, or 208V commercial fryers) do not connect to the neutral and produce zero neutral current. Only line-to-neutral (120V or 277V) loads contribute to the unbalanced neutral demand.

Permissible Neutral Reductions (NEC 220.61(B))

NEC 220.61(B) permits two major demand factor reductions for feeder neutral calculations:

  1. Ranges and Cooking Appliances (220.61(B)(1)):
    For household electric ranges, wall-mounted ovens, counter-mounted cooking units, and electric clothes dryers, the neutral load calculated under Table 220.55 (cooking) and Table 220.54 (dryers) is permitted to take a 70 percent (0.70) demand factor.
  2. Commercial / General Neutral Loads Over 200 Amperes (220.61(B)(2)):
    For feeders supplying 120/240V single-phase systems, or 3-phase 4-wire systems where nonlinear loads are not present, that portion of the maximum unbalanced neutral load that exceeds 200 amperes is permitted to be calculated at a 70 percent demand factor:

Total Neutral Demand Load=200 A+[(Unbalanced Load−200 A)×0.70]\text{Total Neutral Demand Load} = 200\text{ A} + [(\text{Unbalanced Load} - 200\text{ A}) \times 0.70]

Prohibited Neutral Reductions & Nonlinear Loads (NEC 220.61(C))

Journeyman exams frequently test the statutory exceptions where neutral reductions are strictly prohibited under NEC 220.61(C):

  • Nonlinear Loads on 3-Phase, 4-Wire Wye Systems (220.61(C)(2)):
    There shall be no reduction in the grounded conductor capacity for that portion of the load consisting of nonlinear loads (personal computers, servers, electronic ballasts, LED drivers, variable-frequency drives). These devices draw current in short, high-magnitude pulses, creating triplen harmonics (3rd, 9th, 15th harmonic frequencies). Triplen harmonics do not cancel in the neutral; they add arithmetically, causing neutral current to equal or exceed phase current.
  • 3-Wire Circuits from 4-Wire Wye Systems (220.61(C)(1)):
    There shall be no reduction for a 3-wire circuit consisting of two ungrounded conductors and the neutral derived from a 208Y/120V or 480Y/277V 4-wire, 3-phase wye system. Because the two phases are separated by 120 degrees rather than 180 degrees, the neutral carries approximately the same current as the ungrounded conductors even when the loads are balanced (IN≈IphaseI_N \approx I_{\text{phase}}).

Minimum Feeder Neutral Conductor Size (NEC 215.2(A)(2))

Regardless of how small the computed neutral load might be, the grounded (neutral) conductor of a feeder must not be sized smaller than the required equipment grounding conductor specified in NEC Table 250.122, based on the rating of the feeder overcurrent protective device.

Step-by-Step Neutral Reduction Problem

Scenario: A 120/240-volt single-phase, 3-wire commercial feeder has a total calculated maximum unbalanced line-to-neutral linear load of 340 amperes. Calculate the minimum demand load for sizing the feeder neutral conductor under NEC 220.61(B).

Step 1: Partition the Load at the 200-Ampere Threshold

  • First 200 amperes: Evaluated at 100% demand factor.
  • Remaining load exceeding 200 amperes: 340 A−200 A=140 Amperes340\text{ A} - 200\text{ A} = 140\text{ Amperes}.

Step 2: Apply the 70% Demand Factor to the Excess Load
Demand on Excess Load=140 A×0.70=98 Amperes\text{Demand on Excess Load} = 140\text{ A} \times 0.70 = 98\text{ Amperes}

Step 3: Combine the Two Portions
Total Calculated Feeder Neutral Load=200 A+98 A=298 Amperes\text{Total Calculated Feeder Neutral Load} = 200\text{ A} + 98\text{ A} = \mathbf{298\text{ Amperes}}

Step 4: Select Conductor
From Table 310.16 (75°C copper), a 300 kcmil copper conductor (rated 285A) is insufficient; a 350 kcmil copper conductor (rated 310 amperes) is required to carry the 298-ampere neutral demand load.


4. Feeder Voltage Drop Engineering (Informational Note to NEC 215.2(A))

Recommended Limits Under the NEC

While the NEC is primarily an electrical safety code rather than a design specification, excessive voltage drop poses significant operational hazards: overheating of motor windings, failure of digital control relays, flickering luminaires, and severe energy waste. An Informational Note to NEC 215.2(A) gives the widely used voltage drop recommendations:

  • Feeder Conductors Alone: Sized to prevent a voltage drop exceeding 3 percent at the farthest outlet of power, heating, and lighting loads.
  • Overall System (Feeder Plus Branch Circuit): Sized so that the maximum total voltage drop on both the feeder and the branch circuit combined does not exceed 5 percent.
Distribution SegmentRecommended Maximum Voltage Drop120V Nominal Circuit Max Drop208V Nominal Circuit Max Drop240V Nominal Circuit Max Drop480V Nominal Circuit Max Drop
Feeder Only3.0%3.6 Volts6.24 Volts7.2 Volts14.4 Volts
Branch Circuit Only3.0%3.6 Volts6.24 Volts7.2 Volts14.4 Volts
Total (Feeder + Branch)5.0%6.0 Volts10.4 Volts12.0 Volts24.0 Volts

Exam Rationale Note: Informational Notes are explanatory and are not enforceable NEC requirements. A voltage-drop limit becomes mandatory only where another adopted code (such as an energy code) imposes one, or where a specific NEC rule sets one, such as the fire pump limits in NEC 695.7.

Voltage Drop Formulas

To calculate voltage drop (VDVD) or determine the required circular mil (CMCM) conductor size, electricians use the standard resistance formulas:

Single-Phase Circuits: VD=2×K×I×DCM⟺CM=2×K×I×DVDallowVD = \frac{2 \times K \times I \times D}{CM} \quad \Longleftrightarrow \quad CM = \frac{2 \times K \times I \times D}{VD_{\text{allow}}}

Three-Phase Balanced Circuits: VD=3×K×I×DCM=1.732×K×I×DCM⟺CM=1.732×K×I×DVDallowVD = \frac{\sqrt{3} \times K \times I \times D}{CM} = \frac{1.732 \times K \times I \times D}{CM} \quad \Longleftrightarrow \quad CM = \frac{1.732 \times K \times I \times D}{VD_{\text{allow}}}

Where:

  • K=Conductor resistivity constantK = \text{Conductor resistivity constant} (12.9 Ω⋅cmil/ft12.9\ \Omega\cdot\text{cmil/ft} for copper; 21.2 Ω⋅cmil/ft21.2\ \Omega\cdot\text{cmil/ft} for aluminum at 75°C).
  • I=Current in amperes flowing through the circuitI = \text{Current in amperes flowing through the circuit}.
  • D=One-way length of the circuit in feetD = \text{One-way length of the circuit in feet} (from supply point to load).
  • CM=Cross-sectional area of the conductor in circular milsCM = \text{Cross-sectional area of the conductor in circular mils} (found in NEC Chapter 9, Table 8).
  • VDallow=Maximum permitted voltage drop in voltsVD_{\text{allow}} = \text{Maximum permitted voltage drop in volts} (e.g., 3%×Vnominal3\% \times V_{\text{nominal}}).

Step-by-Step Worked Example: Three-Phase Commercial Feeder

Problem: A 3-phase, 208Y/120V commercial feeder supplies a steady load of 120 amperes over a one-way distance of 175 feet using copper conductors installed in steel conduit. The design specifications require that voltage drop on the feeder must not exceed 3 percent. What is the minimum circular mil area required, and what is the minimum standard THHN copper conductor size per NEC Table 8 and Table 310.16?

Step 1: Calculate Maximum Permissible Voltage Drop (VDallowVD_{\text{allow}})
VDallow=208 V×0.03=6.24 VoltsVD_{\text{allow}} = 208\text{ V} \times 0.03 = \mathbf{6.24\text{ Volts}}

Step 2: Calculate Required Circular Mil Area (CMCM)
Using the 3-phase formula with K=12.9K = 12.9 for copper:
CM=1.732×12.9×120 A×175 ft6.24 VCM = \frac{1.732 \times 12.9 \times 120\text{ A} \times 175\text{ ft}}{6.24\text{ V}} CM=469,198.86.24=75,192 Circular MilsCM = \frac{469{,}198.8}{6.24} = \mathbf{75{,}192\text{ Circular Mils}}

Step 3: Check Conductor Ampacity Requirement
For a 120-ampere load, NEC Table 310.16 (75°C column) requires at least a 1 AWG copper conductor (rated 130 amperes).

Step 4: Check NEC Chapter 9, Table 8 for Circular Mil Area
Consulting Table 8 (Conductor Properties):

  • 1 AWG copper has an area of 83,690 circular mils.
  • 2 AWG copper has an area of 66,360 circular mils (too small; <75,192< 75{,}192 cmils).

Conclusion: 1 AWG copper satisfies both the ampacity requirement (130 A≥120 A130\text{ A} \ge 120\text{ A}) and the voltage drop requirement (83,690 cmil≥75,192 cmil83{,}690\text{ cmil} \ge 75{,}192\text{ cmil}). The actual voltage drop will be: VDactual=1.732×12.9×120×17583,690=5.61 Volts(5.61208=2.70%)VD_{\text{actual}} = \frac{1.732 \times 12.9 \times 120 \times 175}{83{,}690} = \mathbf{5.61\text{ Volts}} \quad \left(\frac{5.61}{208} = 2.70\%\right)


5. Feeder Sizing & Neutral Calculation Summary

Calculation ElementNEC ReferenceCore Code RequirementPractical Exam Takeaway
Feeder Minimum Ampacity215.2(A)(1)(a)100% Non-continuous+125% Continuous100\% \text{ Non-continuous} + 125\% \text{ Continuous}Calculate 125% of continuous load before selecting standard OCPD.
Derated Feeder Ampacity215.2(A)(1)(b)Ampacity after adjustment/correction ≥\ge Total actual loadVerify raceway fill and ambient temperature factors against actual load.
Overcurrent Protection215.3 & 240.4OCPD ≥100% Non-cont.+125% Cont.\ge 100\% \text{ Non-cont.} + 125\% \text{ Cont.}Standard OCPD ratings governed by NEC 240.6(A).
Neutral Base Demand220.61(A)Maximum line-to-neutral unbalanced loadExclude pure 208V/240V/480V line-to-line loads from neutral sizing.
Neutral 70% Reduction220.61(B)(2)Portion of neutral load exceeding 200 amperesApply 0.700.70 multiplier only to the amperes above 200A.
Nonlinear Neutral Ban220.61(C)(2)No reduction for nonlinear harmonic loadsComputer, data, and LED lighting loads require 100% full-size neutrals.
Feeder Voltage Drop215.2(A) Informational NoteMaximum 3% feeder, 5% total systemUse 2KID/CM2KID/CM (1-phase) or 3KID/CM\sqrt{3}KID/CM (3-phase) with K=12.9K=12.9 (Cu).
Test Your Knowledge

A commercial feeder supplies a continuous lighting load of 72 amperes and a non-continuous HVAC load of 40 amperes. Under NEC 215.2(A)(1), what is the minimum allowable conductor ampacity before applying any temperature or conduit fill adjustment factors?

A

125 amperes

B

112 amperes

C

140 amperes

D

130 amperes

Test Your Knowledge

A 120/240-volt single-phase dwelling service feeder has a calculated maximum unbalanced neutral load of 320 amperes of linear load, after any range and dryer neutral reductions have already been applied. According to NEC 220.61(B)(2), what is the final calculated feeder neutral demand load?

A

224 amperes

B

320 amperes

C

284 amperes

D

256 amperes

Test Your Knowledge

According to the Informational Note to NEC 215.2(A), what are the maximum recommended voltage drop percentages for a feeder conductor alone and for the total combined system across both the feeder and the branch circuit?

A

3 percent for the feeder, and 5 percent for the combined feeder and branch circuit

B

2 percent for the feeder, and 4 percent for the combined feeder and branch circuit

C

1 percent for the feeder, and 3 percent for the combined feeder and branch circuit

D

5 percent for the feeder, and 8 percent for the combined feeder and branch circuit

Sections you finish are checked off in the contents.