12.1 Time, Work & Pipes and Cisterns
Key Takeaways
Use a total of one job or an integer common multiple of the individual completion times.
Split the timeline whenever a participant starts or stops. Use only the active rates in each interval.
For alternating shifts, count complete cycles and calculate the remaining fraction of the final shift.
Use an output-based payment split when the problem states that agreement.
A tank fills only if the signed net rate is positive over the filling interval.
12.1 Time, Work & Pipes and Cisterns
For a constant work rate, output equals rate multiplied by time. Use rates in the same unit and add them when the workers’ outputs are independent and additive:
Reciprocal-Rate vs. LCM Total-Work Method
Two equivalent frameworks solve time-and-work problems:
- Reciprocal-Rate Method: Set total work to job. If A finishes in days, A's one-day work is . Together, A and B complete per day, finishing in days.
- LCM Total-Work Method: When the completion times are positive whole numbers in the same time unit, set Total Work in work units. Daily rates become exact integers in units/day, preventing fraction errors.
| Method | Total Work | Rate of A (12 days) | Rate of B (18 days) | Combined Rate |
|---|---|---|---|---|
| Reciprocal-Rate | job | job/day | job/day | job/day |
| LCM Total-Work | units | units/day | units/day | units/day |
Worked Example 1: Anita paints a room in days and Bharat in days. Working together, take units. Their rates are and units/day (sum units/day), so they finish in days.
Leaving Midway: Forward vs. Backward-Addition Trick
- Leaves days after start (Forward Subtraction): Subtract from , then divide the remainder by the remaining worker’s rate. First check that the job is still unfinished when the worker leaves.
- Leaves days before completion (Backward-Addition Trick): Pretend the departing worker stayed for those final days. Add to , then divide by the combined rate of everyone. This gives the total time. Verify that it exceeds when both workers are stated to have started.
Worked Example 2: A ( days) and B ( days) start together, and A leaves days before completion. Take units, giving rates A and B units/day. Adding A's missing days contributes units. Total time days.
Alternate-Day Work Cycles
When workers take turns on alternate days, treat one full rotation as a cycle. Multiply whole cycles until just under , then finish the remaining work day by day in turn order. For leftover work, use the rate of the worker on the current shift. The cycle’s average rate describes complete cycles.
Worked Example 3: A ( days) and B ( days) work alternate days starting with A. With units, A and B units/day, so each -day cycle completes units. Five full cycles ( days) complete units, leaving unit. On Day 11, A's turn needs day, giving days total.
Efficiency Ratios and Wage Distribution
Efficiency is work per unit time. For a fixed job, time is inversely proportional to efficiency:
For instance, if Worker X is more efficient than Worker Y (), then X needs only of Y's time (). If Y finishes a task in days, X finishes it in days.
If a problem says pay is shared in proportion to work done, multiply each worker’s rate by their own time before forming the ratio. When everyone works for the same duration, the output ratio is just the daily rate ratio. If one worker works days at units/day ( units) and another works days at units/day ( units), they split the pay in the ratio .
Worked Example 4: A ( days) and B ( days) take a ₹4,200 contract and, working with C throughout, finish in days. They agree to share the contract fee by work done. With units, rates are A , B , and , so C units/day. Since all worked days, shares follow , giving C ₹1,400.
Chain Rule (Man-Days) & AND/OR Equivalence
When workers , days , daily hours , efficiency , and work change across scenarios, use:
For interchangeable workers, headcount times hours gives worker-hours. Multiplying by output per worker-hour gives total output. For groups with different rates, add the groups’ outputs separately.
- Either team can complete the job. Four type-A pumps or eight type-B pumps drain the same basin in 15 hours. If the output of one pump is or , then , so . Six type-A pumps and four type-B pumps have rate , and the job takes hours.
- Both types work together. Four type-A pumps and six type-B pumps together take eight hours, while three type-A pumps and seven type-B pumps take ten hours for the same job. Equate . This gives , or . NCERT, direct and inverse proportions
Pipes and Cisterns
Inlet pipes carry positive rates (filling), while outlet pipes and leaks carry negative rates (emptying). These problems model each rate as constant. If the combined rate from an empty tank is zero or negative, the tank does not fill under that model. If an inlet fills a tank in hours and with a leak takes hours, the leak's solo emptying rate is:
Worked Example 5: An inlet fills a tank in hours, but a leak extends filling to hours. With capacity units, the inlet rate is units/hour and net rate is units/hour, so the leak empties unit/hour and empties a full tank in hours.
A can complete a piece of work in 12 days and B can complete the same work in 15 days. They start working together, and after 4 days A leaves. How many more days will B take to finish the remaining work?
5 days
6 days
7.5 days
8 days
Eighteen workers working 6 hours a day build a 120-metre wall in 15 days. At the same output per worker-hour, how many workers working 9 hours a day are needed for a 180-metre wall of the same design in 10 days?
22 workers
24 workers
27 workers
30 workers
Pipe P can fill a cistern in 15 hours and Pipe Q can fill it in 20 hours, while an outlet Pipe R can empty the full cistern in 12 hours. If all three pipes are opened together, how long will it take to fill the empty cistern?
30 hours
24 hours
40 hours
60 hours