9.3 Work Plans, Method Selection Documentation, and Pre-Abatement Walkthrough

Key Takeaways

  • 745.227 does not number a separate work-plan form. The later abatement report must include a detailed written description of the abatement: methods used, locations of rooms and/or components, the reason for selecting particular abatement methods for each component, and any suggested monitoring of encapsulants or enclosures (745.227(e)(10)(vi)).
  • Convert the inspection or risk-assessment report into a component-by-component method matrix with those reasons before the first strip of containment; do not invent reasons at clearance week.
  • Restricted practices in 745.227(e)(6) must be planned out of the job (no open-flame torching; machine sanding/grinding/blasting only with HEPA exhaust; dry-scrape limits; heat guns below 1100°F). Chapter 13 teaches the how; this chapter refuses illegal methods in the bid.
  • The certified supervisor shall be onsite during all work-site preparation (745.227(e)(2)). The pre-abatement walkthrough confirms components against the report, occupant status against the OPP, utilities, access, and the waste path.
  • Write methods first, then the unique occupant protection plan (Chapter 8) and containment (Chapter 10) around those methods. If the walkthrough changes quantity or location, apply Section 9.2's update clocks.
Last updated: August 2026

Method-by-component plans, reasons on paper, and the pre-abatement walkthrough

Quick Answer: 40 CFR 745.227 does not number a separate "work plan" form. The abatement report you will sign later must include a detailed written description of the abatement: methods, locations of rooms and/or components, the reason for selecting particular abatement methods for each component, and any suggested monitoring of encapsulants or enclosures (745.227(e)(10)(vi)). Supervisors who wait until the report to invent those reasons fail the job and the exam. Turn the inspection / risk-assessment report into a component-by-component method list before the first strip of containment, plan restricted practices out of the work (745.227(e)(6); Chapter 13), and walk the site as the supervisor who must be on-site during all work-site preparation (745.227(e)(2)).

This section is the bridge from Chapter 7 (reading the reports) and Chapter 8 (occupant protection) into Chapter 10 (containment). Notification told EPA when and where. The work plan — whatever you title the internal document — tells the crew what will be done to which component and why.

There is no 745.227 "Form W," but the report will demand the plan

745.227(e)(10) says an abatement report shall be prepared by a certified supervisor or project designer. Among the required contents, (e)(10)(vi) is the method paragraph:

"A detailed written description of the abatement, including abatement methods used, locations of rooms and/or components where abatement occurred, reason for selecting particular abatement methods for each component, and any suggested monitoring of encapsulants or enclosures."

Read the nouns. Methods (not "we abated the house"). Locations of rooms and/or components (not "interior"). Reason for selecting particular abatement methods for each component (not a single blanket "because the owner said so"). Suggested monitoring if you enclosed or encapsulated.

If those sentences do not exist until Friday afternoon of clearance week, they will be fiction. The professional practice is to write them before mobilization, using the inspection and risk-assessment reports Chapter 7 taught you to read. Call that document a work plan, a scope-of-work attachment, a method matrix, or a job hazard analysis — EPA does not give it a section number. The report is what 745.227 numbers. The plan is how a supervisor makes the report true.

The occupant protection plan is separate and is numbered: 745.227(e)(5) requires a written OPP, unique to each residential dwelling or child-occupied facility, developed prior to the abatement, by a certified supervisor or project designer. Chapter 8 owns OPP uniqueness, relocation, isolation, and re-occupancy. This chapter owns the method choices the OPP has to protect people from.

Turn the risk-assessment report into a component matrix

A risk-assessment report (745.227(d)(11)) already lists hazards and "a description of interim controls and/or abatement options for each identified lead-based paint hazard" plus a suggested prioritization, and if encapsulant or enclosure is recommended, a maintenance and monitoring schedule. An inspection report lists which components are LBP. Neither report is a work order. The supervisor (or project designer) converts options into the method for this contract.

Build a table before the walkthrough, then correct it on site:

Component / roomHazard in the RA/inspectionMethod selectedWhy this method (what you will later put in (e)(10)(vi))Restricted-practice checkMonitoring after?
Living-room lower sash, frictionPaint-lead on friction surface; dust on sillComponent replacement of the window assemblyFriction will grind any remaining film; replacement permanently removes the painted slideNo dry sanding of the old sash on site; score, wet, remove wholeNo encapsulant; none
Stair-riser, impact, deterioratedImpact-surface paint-lead hazardComponent replacement of risersRepeated shoe impact would fail an encapsulant or thin enclosureHeat gun, if any, below 1100°F; no torchingNo
Intact living-room wall, no chew marksLBP present, not a current paint-lead hazard, but in the abatement scopeEnclosure with mechanically fastened rigid material, or encapsulation if the substrate passesIntact, low-abuse surface; enclosure/encapsulant can be a permanent barrier if monitoredNo machine grinding without HEPA exhaustYes — suggested monitoring schedule
Play-area bare soil 1,800 ppmSoil-lead hazard (≥ 400 ppm play area)Remove and replace with soil as close to local background as practicable, ≤ 400 ppm; do not reuse as residential topsoilConcentration is a play-area hazard; grass/mulch is not permanent coveringWaste path planned so excavated soil does not re-enter the yardNo, if soil is gone; yes if you instead permanently cover with pavement/concrete
Kitchen floor dustDust-lead hazard (any reportable level on or after Jan. 12, 2026)Interior dust abatement / specialized cleaning to below action levels (5 / 40 / 100) after other methodsDust is the remaining reservoir after paint workHEPA / wet sequence (Chapter 14); no dry sweepingNo encapsulant

Reasons must be particular. "Replacement because it is abatement" is not a reason. Friction surfaces fail film-forming products because abrasion recreates dust. Chewable sills fail encapsulants that a toddler can mouth through. Deteriorated plaster may not hold an encapsulant. Historic-window owners may still choose replacement of stops and parting beads rather than the whole frame — that is a component-level reason, and it still has to be written for each component. Soil gets remove-and-replace or permanent cover (pavement/concrete), not landscaping dressed up as abatement (Chapter 15).

Plan restricted practices out of the job

745.227(e)(6) is not a cleanup rule. It is a method rule, so it belongs in the plan:

  • Open-flame burning or torching of LBP is prohibited. Do not put a torch on the method matrix "for paint that will not scrape."
  • Machine sanding, grinding, abrasive blasting, or sandblasting is prohibited unless used with HEPA exhaust control that removes particles of 0.3 microns or larger at 99.97% or greater efficiency.
  • Dry scraping is permitted only with heat guns, around electrical outlets, or when treating defective paint spots totaling no more than 2 ft² in any one room, hallway, or stairwell, or no more than 20 ft² on exterior surfaces.
  • Heat guns only below 1100°F.

Chapter 13 teaches the how. Chapter 9's job is to refuse a bid that assumes torching, open blasting, or whole-room dry scraping. If the only way the crew knows to get paint off a masonry lintel is a torch, that component's method is wrong before notification is even filed. Put the legal method on the matrix (wet scrape, chemical, heat gun below 1100°F, replacement) and make sure the brief description on the EPA notice in 9.1 matches that matrix. A notice that says "wet scrape and replace windows" while the truck is loaded with abrasive pots is a documentation problem waiting for an inspector.

Pre-abatement walkthrough — supervisor's body on site

745.227(e)(2) requires a certified supervisor for each abatement project and requires that supervisor to be onsite during all work-site preparation. The walkthrough is the last chance to make the plan true before preparation starts, and the first hours of preparation are not a telephone job.

Walk with the RA/inspection in one hand and the method matrix and draft OPP in the other. Punch at least this list:

CheckWhat you are confirmingIf it fails
Components vs reportThe sash, radiators, soil patches, and stair parts on the report still exist, still match the XRF/chip IDs, and were not replaced since the inspectionStop and get the inspector/risk assessor, or treat untested look-alikes under the inspection rule for similar painting history — do not invent XRF numbers
Occupant status vs OPPWho is in the building, who is relocating, who is isolated, pregnant occupants, children under 6, pets, and the re-entry ban during work (Chapter 8)Rewrite the unique OPP before prep; a copied OPP with yesterday's address fails uniqueness
UtilitiesWater for wet methods and decon, power for HEPA vacuums and AFUs, HVAC shutdown points so you do not blow dust through the rest of the dwellingYou cannot start wet scrape or negative air on a dead panel you never looked at
AccessCrew entry, occupant exclusion, inspector's later path, elevator/stair use in multi-familyContainment in Chapter 10 has to match this path
Waste pathHow bagged debris, filters, wastewater, and soil leave the regulated area without tracking through occupied rooms or over play-area soilRCRA characterization is Chapter 17; the route is a walkthrough item now
Exterior / weatherGround sheeting layout, wind, and whether the noticed acreage still matches (Chapter 11)A bigger facade than noticed can become a more than 20% update under 9.2
Clearance logisticsWho the certified inspector or risk assessor will be, and that the supervisor will not self-clearSchedule independence now, not after final wet wash

Worked example — report says three windows, field has five. The RA listed living-room windows A, B, and C as friction hazards. The walkthrough finds two additional original sash in the same room that were never XRF'd because a bookcase hid them. You do not assume they are lead-free. You also do not silently add them to the 1,000 ft² notice if the extra work pushes quantity more than 20%. Get testing or treat them as LBP under the inspection "similar painting history" rule as appropriate, revise the method matrix, check the notice quantity, and revise the OPP if isolation zones change. That is the walkthrough earning its keep.

Worked example — OPP says vacant, crib in the corner. The unique OPP assumed relocation. A toddler's crib is still in the adjacent room with a blanket over the doorway. Preparation cannot start on the strength of a PDF. Occupant protection is prior to abatement (745.227(e)(5)). Fix occupancy, then build containment (Chapter 10). The supervisor who is required on site for prep is the person who has to see the crib.

How this feeds Chapters 8 and 10

Write methods first, then write the OPP around those methods: replacement of windows produces whole-unit debris and a different isolation plan than spot encapsulation of a closet. Then design containment (critical barriers, negative air, decon — Chapter 10) to match both. Notification (9.1–9.2) already told EPA the address, dates, supervisor, and a brief description. The walkthrough is where that brief description either survives contact with the building or gets an updated notice the same day you still legally can.

Keep the paper pack together: inspection/RA, method matrix with reasons, unique OPP, received EPA (or State) notice, firm and supervisor certificates. That pack is what 745.227(e)(10) will turn into the abatement report, including the method-and-reason paragraph you already wrote.

Official sources: 40 CFR 745.227(e)(2), (e)(5), (e)(6), (e)(10)(vi).

Loading diagram...
From Risk-Assessment Report to Pre-Abatement Prep
Test Your Knowledge

Under 40 CFR 745.227(e)(10)(vi), what must the abatement report include about how the work was done?

A
B
C
D
Test Your Knowledge

During the pre-abatement walkthrough the crew wants to start hanging 6-mil polyethylene while the certified supervisor is 45 minutes away on a working cell phone. Is that presence legal?

A
B
C
D
Test Your Knowledge

What is the pre-abatement walkthrough for, before work-site preparation begins?

A
B
C
D
Test Your Knowledge

How should 40 CFR 745.227(e)(6) restricted practices enter the pre-job method plan?

A
B
C
D