3.1 Impact of Six Sigma Projects on Customers, Suppliers, and Stakeholders

Key Takeaways

  • A process change propagates to customers, suppliers, internal downstream processes, support functions, and regulators.
  • Tightening an internal tolerance without notifying the supplier converts your improvement into their non-conformance.
  • Customers can be harmed by improvements that change lead time predictability, packaging, documentation, or minimum order quantity.
  • A stakeholder impact table in the charter forces the team to state the expected effect and the risk for each affected party.
  • In regulated environments a process change triggers change control and possible customer or regulatory notification, and that lead time belongs in the project plan from Define.
Last updated: August 2026

Impact propagates in every direction

A Six Sigma project changes a process, and processes sit inside a network. The Body of Knowledge asks Black Belts to describe that propagation at the Understand level, but the practical requirement is harder: predict it before it happens and design for it.

StakeholderTypical positive impactTypical negative impact if unmanaged
External customersFewer defects, shorter and more predictable lead time, lower costChanged packaging or documentation; changed minimum order quantity; a transition period with mixed old and new product
SuppliersClearer requirements, more stable demand signal, longer-term relationshipTightened tolerances imposed without notice; smaller more frequent orders; new inspection or certification burden
Internal downstream processesBetter inputs, less rework, less firefightingNew handling requirements; different arrival pattern; retraining they did not request
Internal upstream processesClearer specification of what is neededNew data collection duties; changed schedule
Support functionsFewer escalations and corrective actionsNew maintenance intervals, new calibrations, new system changes, new reports
Operators in scopeLess rework, less frustration, safer workChanged standard work; loss of familiar workarounds; perceived job risk
Regulators and certification bodiesBetter documented, more capable processesAn unnotified change to a validated process

Suppliers are inside the system

The most common and most damaging propagation failure is treating a supplier as external to the project.

A team tightens an incoming dimensional tolerance from $\pm 0.15$ mm to $\pm 0.08$ mm to raise downstream assembly yield. Internally the project succeeds. At the supplier, a process with a Cpk of 1.4 against the old tolerance now has a Cpk of 0.75, so their scrap rate rises from near zero to several percent. Within two months the cost arrives back as a price increase, a delivery shortfall, or an incoming quality problem, and the net effect on the enterprise is negative.

The rule: any change to a requirement that a supplier must meet is a supplier project as well as yours. Practically that means:

  • Share the capability data and the reason for the change, not just the new number.
  • Confirm the supplier's capability against the proposed requirement before committing to it.
  • Consider whether the assembly can be made robust to the existing tolerance instead -- parameter design is often cheaper than buying tighter components.
  • Agree the transition: effective date, existing stock disposition, first-article requirements.

The same logic runs the other way for demand: a project that reduces batch size improves your flow and converts the supplier's steady monthly order into weekly orders, which may raise their setup cost. That is a legitimate change but it must be negotiated, not imposed.

Customers can be harmed by improvements

Improvements that look unambiguously good internally can still create customer impact:

ChangeUnintended customer impact
Shorter lead timeCustomer planning systems and safety stock were tuned to the old lead time; a change in variability matters more than a change in mean
Reduced packaging materialHandling or storage at the customer changes; their automation may not accept it
Consolidated shipmentsFewer deliveries per week disrupts a customer running to a daily schedule
Changed component supplierRequires customer requalification in regulated or safety-critical applications
Revised documentation formatCustomer receiving systems and their audit records must be updated

The test is simple and often skipped: would the customer notice this change, and would they need to do anything about it? If yes, they must be told before it happens, not discovered afterwards.

The stakeholder impact table

Build it in Define, alongside the SIPOC, and revisit it at every toll gate.

StakeholderInternal / externalCurrent experienceExpected impactRiskMitigationOwner
Assembly cell 2InternalReceives 4% of kits shortComplete kits; new pick sequenceOperators must learn a new layoutStandard work plus 2-week hypercareCell supervisor
Moulding supplierExternalShips to $\pm 0.15$ mmRequirement tightens to $\pm 0.10$ mmTheir Cpk falls below 1.0Joint capability study before commitmentSupply quality engineer
Fleet customersExternal6-day lead time3-day lead timeBatch reduction may raise unit priceModel total cost with the customerAccount manager
Field serviceInternalHandles miswired-unit reworkFar fewer calloutsLoses visibility of failure modesShare the new defect data monthlyService manager
Notified bodyExternalProcess validated in 2024Process parameter changeRequires change control and possible notificationRegulatory review in AnalyzeRegulatory affairs

The rows that carry a risk entry are the ones worth reviewing with the sponsor. The row types most often missing are the internal downstream process that absorbs the change without being asked, and the support function that inherits a new recurring obligation.

Regulated environments

Where the process is validated -- medical devices, pharmaceuticals, aerospace, food, automotive safety -- a process change is not merely an engineering decision. It triggers formal change control, may require revalidation, and in some cases requires customer or regulatory notification before implementation. Those steps have lead times measured in weeks or months.

The failure mode is discovering this in the Improve phase, when the solution is designed and the sponsor expects implementation. Regulatory and change-control lead times belong in the project plan from Define, and the regulatory function belongs on the stakeholder list from the first charter review.

Measuring the impact

Where impact is expected, measure it rather than assuming. Two mechanisms:

  • Consequential metrics in the project's measure set, so degradation elsewhere is visible while the primary metric improves.
  • A short post-implementation check with each affected stakeholder, at 30 and 90 days, asking specifically what changed for them. Suppliers and internal downstream processes rarely volunteer that a change hurt them; they absorb it and the cost surfaces later as something else.
Test Your Knowledge

A team tightens an incoming component tolerance from plus or minus 0.15 mm to plus or minus 0.08 mm to raise assembly yield. What is the most likely system-level consequence if the supplier is not involved?

A
B
C
D
Test Your Knowledge

Which change is most likely to disrupt a customer even though it appears to be an unambiguous improvement?

A
B
C
D
Test Your Knowledge

In a validated, regulated process, when should the change control and possible regulatory notification lead time be entered into the project plan?

A
B
C
D