9.7 Measurement System Reanalysis

Key Takeaways

  • Observed variance is the sum of true process variance and measurement system variance, so shrinking the process makes the gauge a larger share of what remains.
  • Percent study variation compares measurement variation with total observed variation; percent tolerance compares it with the specification width.
  • The AIAG guidance is that under 10% is acceptable, 10 to 30% is conditionally acceptable, and above 30% is unacceptable.
  • The number of distinct categories should be at least 5, computed as 1.41 times the part standard deviation divided by the gage R&R standard deviation.
  • Measurement system reanalysis is triggered by improved capability, gauge or fixture changes, new operators, tightened tolerances, and at a defined periodic interval.
Last updated: August 2026

Why capability improvement degrades the measurement system

Observed variation always contains both the process and the gauge:

σobserved2=σprocess2+σmeasurement2\sigma^2_{observed} = \sigma^2_{process} + \sigma^2_{measurement}

A successful project reduces $\sigma^2_{process}$ and leaves $\sigma^2_{measurement}$ untouched. The gauge's share of what remains therefore rises, sometimes dramatically.

Worked example. Baseline: $\sigma_{observed} = 0.50$, of which $\sigma_{measurement} = 0.15$.

  • $\sigma^2_{process} = 0.50^2 - 0.15^2 = 0.2500 - 0.0225 = 0.2275$, so $\sigma_{process} = 0.477$.
  • Measurement share of observed variance $= 0.0225 / 0.2500 = 9.0%$, and %Study Variation $= 0.15/0.50 = 30%$ -- marginal but workable.

The project halves the process standard deviation to $\sigma_{process} = 0.2385$:

  • New $\sigma^2_{observed} = 0.2385^2 + 0.15^2 = 0.05688 + 0.0225 = 0.07938$, so $\sigma_{observed} = 0.2818$.
  • Measurement share of variance $= 0.0225 / 0.07938 = 28.3%$, and %Study Variation $= 0.15/0.2818 = 53%$ -- now unacceptable.

Nothing about the gauge changed. The project's own success made it inadequate, and every subsequent capability figure computed with it will be understated, because measurement noise is being counted as process variation.

Acceptance criteria

MetricFormulaCompares against
%Study Variation (%SV)$100 \times \sigma_{R&R} / \sigma_{total}$Total observed variation
%Tolerance (P/T)$100 \times 6\sigma_{R&R} / (USL - LSL)$The specification width
%Contribution$100 \times \sigma^2_{R&R} / \sigma^2_{total}$Total observed variance
Number of distinct categories (ndc)$1.41 \times \sigma_{part} / \sigma_{R&R}$Resolving power

AIAG guidance, applied to %SV or %Tolerance:

ValueVerdict
Under 10%Acceptable
10% to 30%Conditionally acceptable, based on the criticality of the application, the cost of the gauge, and the cost of repair
Over 30%Unacceptable; the measurement system must be improved

ndc should be at least 5, meaning the gauge can distinguish at least five distinct levels of part variation. An ndc below 5 signals inadequate resolving power even when the percentage figures look borderline acceptable.

Note that %Contribution uses variance while %SV uses standard deviation, so the two numbers differ substantially for the same study: 30% study variation corresponds to 9% contribution. Quoting one and comparing it against the other's threshold is a common error.

Which criterion to use when

  • Use %Tolerance when the gauge is used to accept or reject product against a specification, because the question is whether the gauge can distinguish good from bad.
  • Use %Study Variation when the gauge is used to study and improve the process, because the question is whether the gauge can see the process variation.
  • A gauge can pass one and fail the other. A wide tolerance with a tightly controlled process gives a good P/T ratio and a poor %SV, which is precisely the situation a Six Sigma team encounters after a successful project.

Triggers for reanalysis

TriggerReason
Process capability has improved materiallyThe gauge's share of observed variation has risen
Tolerance has been tightenedThe P/T ratio changes even though the gauge did not
Gauge, fixture, or software has been changed or repairedThe system is not the one that was validated
New operators or a new locationReproducibility may differ
Out-of-tolerance found at calibrationThe validated state was not maintained
Unexplained shift in the control chartThe measurement system is a candidate cause
Defined periodic intervalStandard practice, typically annually for critical characteristics
Before a capability study is used for a customer submissionThe result must be defensible

The first row is the one the Body of Knowledge specifically emphasizes and the one teams most often miss.

What to do when reanalysis fails

Work in order of cost:

  1. Improve the procedure. Standardize the fixturing, the clamping force, the location of the measurement, and the operator's technique. Reproducibility problems are often pure method problems and cost nothing to fix.
  2. Retrain the appraisers. A large reproducibility component with a small repeatability component points at people, not the instrument.
  3. Improve resolution. The gauge discrimination should be no coarser than one tenth of the process variation or of the tolerance, whichever is tighter. A gauge reading to 0.01 mm cannot support a study of a process whose total spread is 0.03 mm.
  4. Average repeated readings. Averaging $m$ readings reduces the repeatability standard deviation by $\sqrt{m}$. This is a legitimate short-term measure with an ongoing cost, and it does nothing for reproducibility or bias.
  5. Replace the gauge or automate the measurement. The last resort by cost, and sometimes the only real answer.

Recording the reanalysis

The Control phase deliverable is not the number but the decision. Record: the date and reason for the reanalysis, the study design (parts, appraisers, trials), the resulting %SV, %Tolerance, %Contribution, and ndc, the verdict against the criteria, any action taken, and the next scheduled review. Put the review interval into the control plan itself, so the reanalysis happens by schedule rather than by memory.

Test Your Knowledge

A project halves the process standard deviation. The measurement system, unchanged, previously contributed 30% study variation. What happens to the percent study variation, and why does it matter?

A
B
C
D
Test Your Knowledge

A gage R&R study reports 9% contribution and 30% study variation for the same measurement system. Why do these figures differ so much?

A
B
C
D
Test Your Knowledge

A gage R&R fails with a large reproducibility component and a small repeatability component. Which corrective action should be tried first?

A
B
C
D