7.3 Changes and Supply Disruptions

Key Takeaways

  • MRP nervousness is the ripple of date and quantity changes through dependent demand when MPS, inventory, or open-order status shifts.
  • Firm planned orders stabilize timing and quantity so regeneration cannot freely rewrite near-term supply.
  • Pegging traces where a requirement or supply order came from—up to parents and customers or down to components—so planners can target disruption responses.
  • Exception and action messages prioritize release, reschedule, cancel, and shortage conditions; planners must validate before acting.
  • Supply disruption response combines pegging, firming, ATP revision, alternate supply, lot splitting, and honest customer date recovery—not silent schedule denial.
Last updated: July 2026

Quick Answer: Small MPS or supply changes can cascade through the BOM as MRP nervousness. Planners dampen it with time fences, firm planned orders, and controlled regeneration. Pegging shows which parents and customers are hit; exception messages flag what to fix first. When disruptions hit, revise ATP/promises, re-peg critical shortages, firm recoverable orders, and choose substitutes, splits, or alternate sources with clear customer communication.

Execution rarely matches the last regenerative run. CPIM expects you to manage change deliberately: stabilize what must not thrash, illuminate where a shortage came from, and respond to disruptions with prioritized, pegged actions.

MRP Nervousness

System nervousness is excessive replanning—orders that repeatedly change date or quantity across MRP runs even when the business change is small. Because dependent demand is calculated from parent releases, a one-week shift at the top level can reschedule dozens of component orders below.

Common nervousness drivers:

DriverWhy it thrashs the plan
Late MPS edits inside the planning time fenceRevises independent demand that explodes everywhere
Lot-sizing that amplifies small nets (FOQ/EOQ)Tiny net changes trigger whole extra lots
Unconstrained regenerative replanning of near-term planned ordersReleases oscillate between adjacent weeks
Frequent inventory adjustment / scrap postingsChange projected available and nets immediately
Supplier early/late receipts without firming logicOpen supply timing fights the algorithm

Damping techniques:

  • Respect demand and planning time fences; route near-term MPS changes through master schedulers.
  • Convert near-term planned orders to firm planned orders.
  • Prefer L4L or controlled POQ in volatile zones if FOQ amplification is the culprit.
  • Use net-change MRP carefully, but still review action messages—net change reduces volume of churn, not the need for judgment.
  • Stabilize BOMs and avoid unnecessary phantom or engineering changes in the freeze horizon.

Firm Planned Orders

A firm planned order (FPO) is a planned order whose quantity and/or due date the planner has locked. MRP may still explode from it and may still generate messages, but it should not automatically rewrite the firmed fields the way it rewrites ordinary planned orders.

Order stateMRP freedomTypical use
Planned orderFully adjustable each runHorizon beyond planner control window
Firm planned orderTiming/qty protectedNear-term supply you intend to keep stable
Released / open order (scheduled receipt)Quantity/date changed only by receiving, shop-floor, or purchase transactions (plus deliberate maintenance)Execution underway

When to firm: inside the planning time fence; after promising a customer from specific supply; when setup sequencing on a bottleneck must not thrash; when a long-lead purchase must stay aligned to a supplier commitment.

When not to firm everything: over-firming freezes bad plans and suppresses legitimate reschedule messages. Firm selectively, then watch exceptions on firmed objects.

Pegging

Pegging links a requirement or supply order to its sources. Single-level pegging shows immediate parents or children; full pegging walks to end items and customer orders (where the system supports it).

Pegging directionQuestion it answers
Bottom-up / where-used demand peg“Which parent order created this component gross requirement?”
Top-down / supply peg“Which components and suppliers feed this parent due date?”
Peg to customer“Whose order is at risk if this receipt slips?”

Disruption example: Supplier advises that a week-4 receipt of 120 Y will slip to week-6. Pegging shows those 120 units support X releases that cover customer shipments in weeks 5–6. Without pegging, a planner might expedite the wrong item or notify the wrong customer.

Exception and Action Messages

MRP and related planning systems emit exception (action) messages so planners do not scan every item. Typical categories:

Message typeMeaningFirst-check response
Release orderStart/place date reachedVerify material & capacity, then release
Expedite / reschedule-inNeed earlier datingConfirm true shortage via pegging; then compress LT or split
Defer / reschedule-outSupply earlier than neededDelay to cut inventory if customer risk is low
CancelSupply obsoleteClose or reduce open order
Past dueOrder late versus needRoot-cause and recover or re-promise
Shortage / negative ATPDemand exceeds credible supplyAllocate, substitute, or change promise

Discipline: sort by severity and date proximity; peg before mass rescheduling; never clear messages by blindly accepting every system suggestion—especially across firm orders and supplier-confirmed dates.

Supply Disruption Response Playbook

When yield collapses, a supplier fails, a work center goes down, or inbound freight stalls, use a structured response:

  1. Quantify the hole — what quantity is missing in which buckets?
  2. Peg the impact — which parents, FAS entries, and customer promises fail?
  3. Protect the truth in promising — immediately reduce ATP/CTP; stop sales from booking the ghost supply.
  4. Stabilize the near term — firm orders you will actually chase; unfirm thrashing plans that block clear thinking.
  5. Recover supply — alternate supplier, partial shipment, premium freight, rework, substitute component, overtime, or alternate routing (CRP must confirm capacity).
  6. Rebalance demand — split deliveries, substitute configurations in ATO, prioritize allocations by policy.
  7. Replan and communicate — regenerate or net-change, review new exceptions, notify customer service with honest dates.
DisruptionMaterial-side moveCapacity / schedule moveCustomer-side move
Supplier delayAlternate source; partials; substitute partReschedule parent releases; CRP checkRevise promise; split ship
Scrap spike at assemblyIncrease component releases; emergency PORework capacity; overtime policyHold FAS until yield known
Bottleneck outageDelay noncritical lotsAlternate WC/routing; finite resequencePush low-priority promises first
Sudden large order winCheck ATP/CTP before acceptFAS insert with levelingQuote realistic date, not hope date

Worked Mini-Grid: Disruption and Pegging

Recall component Y from section 7.1: planned order receipt of 120 in week 4 (released in week 3). Suppose purchasing reports the supplier can deliver only 70 in week 4; the remaining 50 arrive in week 6.

WeekOriginal Y receiptDisrupted receiptEffect on parents
412070Short 50 versus plan
500Risk to any X demand relying on full week-4 supply
6050Late recovery of the shortfall

Pegging from the short 50 units shows coverage was intended for X demand tied to later MPS shipments. Planner actions: firm a 70 receipt in week 4; create a firm 50 in week 6 (or expedite if premium freight recovers earlier); reduce ATP for affected end items; issue reschedule messages only to pegged parents; tell customer service which promises move before sales rebooks.

Change Control versus Firefighting

Not every change is a disruption. Engineering change orders, date shifts inside policy, and forecast consumption adjustments are managed changes. Use formal ECR/ECO effectivity, time-fence policy, and master scheduler ownership. Firefighting starts when uncontrolled edits bypass fences, firming is random, and exception queues are ignored until shortages hit the dock.

Exam Pitfalls

  • Calling every reschedule “nervousness” — nervousness is excessive churn, not legitimate response to real demand change.
  • Firming the entire horizon so MRP cannot improve anything.
  • Expediting without pegging, which wastes premium freight on the wrong order.
  • Leaving ATP unchanged after a supplier failure, allowing new orders to steal recovery supply.
  • Treating cancel messages as optional noise while inventory and payables absorb unneeded receipts.
Test Your Knowledge

What is MRP nervousness?

A
B
C
D
Test Your Knowledge

Why do planners convert some planned orders into firm planned orders?

A
B
C
D
Test Your Knowledge

A supplier slips a component receipt. What is the best first use of pegging?

A
B
C
D
Test Your Knowledge

After a confirmed supply shortage, which promising action aligns with good disruption control?

A
B
C
D