10.3 Job and Batch Costing: Job Cost Cards, Job Accounts and Pricing a Job

Key Takeaways

  • Job costing accumulates costs for an individual customer order, using material requisitions, time records and predetermined overhead absorption rates.

  • Each job is a sub-account of work-in-progress; when a job is completed and delivered, its cost is transferred to cost of sales (or to finished goods if it is held).

  • Batch costing treats a batch of identical units as a job and calculates cost per unit as total batch cost divided by the number of good units produced.

  • A job quotation adds non-production overheads to production cost to find total cost, then adds profit as either a mark-up on cost or a margin on price.

Last updated: September 2026

Why this topic is examined

Syllabus area C4(c) asks you to prepare appropriate accounts for job and batch costing. Questions ask you to complete a job cost card, calculate the cost or price of a job, find a batch cost per unit, or identify the correct accounting entry when a job is finished. Process costing and contract costing are not part of the BA2 syllabus.


When job and batch costing are used

MethodCost unitTypical industries
Job costingAn individual order made to a customer's specificationPrinting, engineering workshops, vehicle repairs, building work, accountancy and consultancy assignments
Batch costingA batch of identical items made togetherPharmaceuticals, clothing, bakery products, electronic components

Both are forms of specific order costing: each job or batch has its own identity, and costs are collected separately for it.


The job cost card and its source documents

Each job is given a number and a job cost card (or job cost sheet) on which costs are accumulated:

Cost elementSource documentHow it is valued
Direct materialsMaterials requisition (and materials returned notes)Issue price per the inventory valuation method
Direct labourJob time sheets or time recordsHours worked on the job × hourly rate
Direct expensesInvoices for items bought specifically for the jobActual cost
Production overheadHours recorded on the jobPredetermined absorption rate per cost centre (Section 3.2)
Non-production overheadNot recorded until the job is completeOften a percentage of production cost

Note

Materials returned to stores from a job reduce that job's material cost. Overtime premium is normally treated as an overhead, unless the overtime was worked specifically at the customer's request for that job, in which case it is a direct cost of the job.


Worked example: Job 247

A workshop has been asked to quote for Job 247.

ItemDetails
Direct materials400 kg issued at $6 per kg; 20 kg later returned to stores
Direct labour, Department A30 hours at $15
Direct labour, Department B20 hours at $18
Direct expenseHire of a special tool: $200
Overhead, Department AAbsorbed at $12 per direct labour hour
Overhead, Department BAbsorbed at $20 per machine hour; the job uses 25 machine hours
Non-production overhead20% of production cost
Pricing policy25% margin on selling price

Job cost card

Job 247$
Direct materials (400 kg × $6)2,400
Less materials returned (20 kg × $6)(120)
Direct labour: Dept A (30 × $15)450
Direct labour: Dept B (20 × $18)360
Direct expense: tool hire200
Prime cost3,290
Production overhead: Dept A (30 × $12)360
Production overhead: Dept B (25 × $20)500
Total production cost4,150
Non-production overhead (20% × $4,150)830
Total cost4,980
Profit (balancing figure)1,660
Selling price ($4,980 ÷ 0.75)6,640

Check: profit of $1,660 ÷ price of $6,640 = 25%. A 25% mark-up on cost would have given $6,225, so reading "margin" correctly matters. (Section 4.3 covers mark-ups and margins in detail.)


Job accounts in the ledger

In an integrated system (Section 10.1), each job is effectively a sub-account of the WIP control account:

EventDebitCredit
Direct materials issued to Job 247Job 247 (WIP)Raw materials control
Materials returned from Job 247Raw materials controlJob 247 (WIP)
Direct labour charged to Job 247Job 247 (WIP)Wages control
Direct expense for Job 247Job 247 (WIP)Payables
Overhead absorbed by Job 247Job 247 (WIP)Production overhead control
Job 247 completed and deliveredCost of salesJob 247 (WIP)
Invoice raised for Job 247ReceivablesSales

If a completed job is held before delivery, its cost is transferred to finished goods first. The total of all incomplete jobs at the period end equals the closing WIP balance.

Job 247 account

Debit$Credit$
Raw materials2,400Raw materials (returns)120
Wages (Depts A and B)810Cost of sales (on completion)4,150
Payables (tool hire)200
Production overhead absorbed860
Total4,270Total4,270

Non-production overhead is charged to the statement of profit or loss as a period cost; it is included in the quotation to make sure the price covers it, but it is not part of the job's inventory value.


Batch costing

In batch costing, the batch is treated as a job. Costs are collected on a batch cost card, and the cost per unit is found at the end:

Cost per unit=Total batch costNumber of good units in the batch\text{Cost per unit} = \frac{\text{Total batch cost}}{\text{Number of good units in the batch}}

Worked example: batch of circuit boards

A batch of 2,000 circuit boards incurs:

Batch 88$
Direct materials3,600
Direct labour (70 hours × $20)1,400
Machine set-up cost300
Production overhead (70 hours × $25)1,750
Total batch cost7,050
Cost per board=$7,0502,000=$3.525\text{Cost per board} = \frac{\text{\textdollar}7{,}050}{2{,}000} = \text{\textdollar}3.525

Set-up costs are incurred once per batch however many units are made, so larger batches spread set-up cost over more units and reduce the cost per unit. If 50 boards failed inspection and were scrapped with no value, the cost of the 1,950 good boards would be $7,050 ÷ 1,950 = $3.615 each.


Using job costs for control and pricing

  • Quotations: estimated job costs underpin prices. Past job cards help estimate new jobs.
  • Profitability: comparing actual job cost with the price charged shows which jobs and customers are profitable.
  • Control: comparing actual job cost with the estimate highlights overruns in materials or hours while the job is in progress.

Tip

Build the job cost card in the order prime cost, production cost, total cost, price. Most wrong answers come from applying the non-production percentage to prime cost instead of production cost, or from confusing margin with mark-up.

Loading diagram...
Job Costing Flow
Test Your Knowledge

Job 742 has direct materials of $8,000, direct labour of $5,000 and absorbed production overhead of $3,000. Non-production overhead is added at 25% of production cost, and the company prices jobs to earn a 20% margin on selling price. What is the price of Job 742?

A

$20,000

B

$24,000

C

$26,667

D

$25,000

Test Your Knowledge

Job 315 has been completed and delivered to the customer. In an integrated accounting system, what entry records the transfer of its production cost?

A

Debit cost of sales; credit work-in-progress (Job 315)

B

Debit work-in-progress (Job 315); credit cost of sales

C

Debit finished goods; credit cost of sales

D

Debit receivables; credit work-in-progress (Job 315)

Test Your Knowledge

A batch of 5,000 units incurs direct materials of $6,000, direct labour of $4,500, set-up costs of $500 and absorbed production overhead of $3,000. What is the cost per unit of the batch?

A

$2.10

B

$2.80

C

$3.00

D

$2.70

Sections you finish are checked off in the contents.