10.2 Integrated Ledgers with Under- and Over-Absorption and Standard Cost Variances

Key Takeaways

  • Under-absorbed overhead is debited to the statement of profit or loss and credited to the production overhead control account; over-absorbed overhead is the reverse.

  • In a standard costing ledger, inventories are held at standard cost and each variance is recorded in a separate variance account where it arises.

  • Adverse variances are debit balances and favourable variances are credit balances; at the period end they are transferred to the statement of profit or loss.

  • The material price variance is usually recorded when materials are purchased, and the usage variance when materials are issued to work-in-progress.

  • Labour rate variance arises in the wages control account, while labour efficiency variance arises when standard hours for actual output are charged to work-in-progress.

Last updated: September 2026

Why this topic is examined

Syllabus area C4(b) asks you to prepare a set of integrated accounts, showing standard cost variances, including "accounting for over and under absorption of production overhead" and "the treatment of variances in integrated ledger systems". Questions usually ask for the double entry for a particular variance or for the balance transferred to the statement of profit or loss. Section 10.1 introduced the control accounts; this section adds absorption adjustments and variances.


Recording under- and over-absorbed overhead

Production overhead is charged to WIP at a predetermined rate (Section 3.2), so at the period end the production overhead control account usually has a balance:

SituationBalance on overhead control accountEntry to clear itEffect on profit
Under-absorbed (absorbed < actual)Debit balanceDebit statement of profit or loss; credit production overhead controlReduces profit
Over-absorbed (absorbed > actual)Credit balanceDebit production overhead control; credit statement of profit or lossIncreases profit

Tip

Picture the overhead control account: actual overhead is debited, absorbed overhead is credited. If more was spent than absorbed, the debit side is bigger; clear it with a credit and send the debit to profit or loss as an extra cost.


Standard costing in the ledger: the principles

In a standard costing system:

  1. Inventories are carried at standard cost. Raw materials are held at standard price, and WIP and finished goods at the standard cost of the units they contain.
  2. Each variance is recorded in its own variance account, at the point where it arises.
  3. Adverse variances are debits (extra cost); favourable variances are credits (cost saving).
  4. At the end of the period, variance accounts are transferred to the statement of profit or loss, so actual profit equals standard profit adjusted for variances.
VarianceWhere it arisesEntry if adverse
Material price (recorded at purchase)Raw materials controlDebit material price variance; credit payables
Material usageIssue of materials to WIPDebit material usage variance; credit raw materials control
Labour rateWages controlDebit labour rate variance; credit wages control
Labour efficiencyCharging labour to WIPDebit labour efficiency variance; credit wages control
Overhead expenditureOverhead controlDebit expenditure variance; credit overhead control
Fixed overhead volume (absorption costing)Overhead controlDebit volume variance; credit overhead control

For a favourable variance, reverse the entry: credit the variance account.


Worked example: Merlin Ltd, April

Standard cost card (per unit)

ElementStandard$
Direct materials4 kg at $520
Direct labour2 hours at $1224
Fixed production overhead2 hours at $816
Standard production cost60

Budgeted production is 1,000 units, so budgeted fixed overhead is $16,000.

Actual results for April

  • Production: 1,100 units (no opening or closing WIP).
  • Materials bought on credit: 5,000 kg for $24,000 ($4.80 per kg). Materials used: 4,500 kg.
  • Labour: 2,300 hours paid at $12.50 = $28,750.
  • Fixed production overhead incurred: $17,000.

Step 1: calculate the variances

VarianceCalculation$
Material price (at purchase)($5.00 − $4.80) × 5,000 kg1,000 F
Material usage(4,400 kg − 4,500 kg) × $5500 A
Labour rate($12.00 − $12.50) × 2,300 hours1,150 A
Labour efficiency(2,200 hours − 2,300 hours) × $121,200 A
Fixed overhead expenditure$16,000 − $17,0001,000 A
Fixed overhead volume(1,100 − 1,000 units) × $161,600 F

(Standard quantity for actual output is 1,100 × 4 kg = 4,400 kg; standard hours are 1,100 × 2 = 2,200.)

Step 2: record the entries

Raw materials control (at standard price)

Debit$Credit$
Payables: 5,000 kg at standard $525,000WIP: 4,400 kg at $522,000
Material usage variance500
Closing balance: 500 kg at $52,500
Total25,000Total25,000

The purchase is recorded as: debit raw materials $25,000 (standard), credit payables $24,000 (actual), credit material price variance $1,000 (favourable).

Wages control

Debit$Credit$
Bank: actual wages28,750WIP: 2,200 standard hours at $1226,400
Labour rate variance1,150
Labour efficiency variance1,200
Total28,750Total28,750

Fixed production overhead control

Debit$Credit$
Bank: actual overhead17,000WIP: 1,100 units at $16 absorbed17,600
Fixed overhead volume variance1,600Fixed overhead expenditure variance1,000
Total18,600Total18,600

Overhead was over-absorbed by $600 ($17,600 absorbed − $17,000 actual). In a standard costing system, that $600 is analysed as a $1,600 favourable volume variance and a $1,000 adverse expenditure variance.

Work-in-progress control

Debit$Credit$
Materials at standard22,000Finished goods: 1,100 units at $6066,000
Labour at standard26,400
Overhead absorbed at standard17,600
Total66,000Total66,000

Because WIP is charged with standard cost for actual output, the transfer to finished goods is simply units × standard cost.

Step 3: clear the variance accounts

Variance accountDebit (adverse), $Credit (favourable), $
Material price1,000
Material usage500
Labour rate1,150
Labour efficiency1,200
Fixed overhead expenditure1,000
Fixed overhead volume1,600
Totals3,8502,600

The net adverse $1,250 is transferred to the statement of profit or loss, reducing standard profit to actual profit.


Marginal costing ledgers

If the business uses standard marginal costing (the format of BA2's operating statement in Section 8.1), fixed production overhead is not absorbed into WIP. The actual fixed overhead is charged to the statement of profit or loss in full, and the only fixed overhead variance recorded is the expenditure variance. There is no volume variance and no under- or over-absorption.

Important

Common exam traps: (1) recording the material price variance on the quantity used when the question says it is recorded at purchase; (2) charging WIP with actual hours or quantities instead of standard hours or quantities for actual output; (3) crediting an adverse variance account. Adverse variances are always debits.

Loading diagram...
Where Variances Arise in a Standard Costing Ledger
Test Your Knowledge

At the end of a period, production overhead has been over-absorbed by $7,500. What entry clears the production overhead control account?

A

Debit statement of profit or loss $7,500; credit production overhead control $7,500

B

Debit production overhead control $7,500; credit statement of profit or loss $7,500

C

Debit work-in-progress $7,500; credit production overhead control $7,500

D

Debit production overhead control $7,500; credit finished goods $7,500

Test Your Knowledge

Raw materials are held at standard cost. A company buys 2,000 kg of material on credit for $9,400; the standard price is $4.50 per kg. What entries record the purchase?

A

Debit raw materials $9,400; credit payables $9,400

B

Debit raw materials $9,000; debit material price variance $400; credit payables $9,400

C

Debit raw materials $9,400; credit payables $9,000; credit material price variance $400

D

Debit raw materials $9,000; credit material price variance $400; credit payables $8,600

Test Your Knowledge

In a standard costing system, which amount is debited to work-in-progress for direct labour?

A

Actual hours paid × actual rate

B

Actual hours worked × standard rate

C

Standard hours for actual output × standard rate

D

Budgeted hours × actual rate

Sections you finish are checked off in the contents.