5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk

Key Takeaways

  • An incomplete client request — missing site, program, budget, schedule, or delivery method — must be completed before a fee can responsibly be quoted.
  • Stipulated sum places scope-growth risk on the architect; unlimited hourly places it on the owner; an hourly fee with an upper limit places it on the architect above the cap.
  • Design-bid-build fixes price only after design is complete, while CM at Risk sets a guaranteed maximum price during design and design-build fixes price earliest.
  • Under design-build the architect may contract with the design-builder rather than the owner, which removes the architect’s traditional role as impartial interpreter of the contract documents.
  • Contractual terms disqualify commissions more often than technical fit does, because uninsurable warranties, duties to defend, and uncapped indemnity are not covered by professional liability insurance.
Last updated: September 2026

Practice Management Section 3 looks at projects from the firm's side of the table: which commissions to pursue, how to respond to a client's request, what form of agreement and compensation to propose, how the project will be delivered, and what risk the project brings into the practice.

Responding to a Client Services Request

Before a fee is quoted, the architect has to evaluate the request itself.

  • Is the request complete? A request that omits the site, the program area, the budget, the schedule, or the delivery method cannot be priced. The correct first action is almost always to obtain the missing information, not to quote a defensive number.
  • What scope of services is actually needed? Basic services for one client may need to be supplemented with programming, existing-conditions documentation, civil engineering, cost estimating, commissioning, or record modeling. Each is priced separately.
  • Is there a conflict? The NCARB Rules of Conduct and the AIA Code both require disclosure of any actual or potential conflict of interest. A firm holding a financial interest in a competing development, or representing two bidders on the same site, must disclose and often must decline.
  • Is there a public interest conflict? Work that would require the architect to conceal a code violation, misrepresent a condition to an authority having jurisdiction, or design around a known safety hazard is refused, not negotiated.

The Go / No-Go Decision

Pursuit costs money — proposal preparation, interviews, and sometimes conceptual design are unbillable overhead. A disciplined go/no-go screen weighs:

FactorFavorableUnfavorable
Technical fitFirm has completed comparable project typesFirst-of-type with no in-house expertise
ClientKnown, creditworthy, experiencedNo track record, litigation history, unfunded
Contract termsStandard agreement, standard of care preservedOwner form with warranties, uncapped indemnity, no LoL
Fee and scheduleSupports the firm's target net multiplierFee below break-even, compressed schedule
CapacityStaff available when the work landsRequires speculative hiring
Strategic valueOpens a target market or client relationshipDistracts from core practice

Compensation Methods

The form of compensation allocates risk between owner and architect.

MethodHow it worksWhere the risk sits
Stipulated (fixed) sumA lump sum for a defined scopeArchitect — any scope growth erodes profit unless authorized as an additional service
Percentage of the cost of the workFee set as a percentage of construction costShared — fee tracks cost, but disputes arise when the owner reduces scope
Hourly, unlimitedRate per hour, no capOwner
Hourly with an upper limitRate per hour, cappedArchitect above the cap
Unit costFee per unit (per bed, per key, per square foot)Architect if units are redefined

Whatever the method, the agreement must define what triggers additional services, or scope growth becomes uncompensated work.

Project Delivery Methods

Delivery method determines who holds which contract, when price is fixed, and what the architect's construction-phase role is. Expect items that give you an owner's priority — lowest first cost, earliest completion, single point of responsibility — and ask which method fits.

Delivery methodContract structurePrice certaintyOwner priority it serves
Design-Bid-Build (DBB)Owner holds separate contracts with architect and contractorFixed at bid, after design is completeLowest first cost, open competition, fully documented scope
CM as Adviser (CMa)Owner holds architect, CM, and contractor(s); CM is a fee-based consultantLateIndependent cost and schedule advice, multiple prime contracts
CM at Risk (CMAR)Owner holds architect and CM/GC; CM/GC delivers a guaranteed maximum priceGMP set during designEarly price certainty with preconstruction input
Design-Build (DB)Owner holds one contract with a design-build entityEarlySingle point of responsibility, speed
Integrated Project Delivery (IPD)Multi-party agreement among owner, architect, and contractorCollaborative, shared risk and rewardCollaboration, shared incentives, waived claims among parties

Two consequences the exam returns to repeatedly:

  • Under design-build, the architect may be a subconsultant to the contractor. Privity runs to the design-builder, not the owner, and the architect's traditional role as the owner's impartial interpreter of the contract documents is compromised.
  • Under CM at Risk and IPD, design and construction overlap. Documents get issued for pricing at levels of completeness that design-bid-build never uses, which changes the firm's internal documentation and quality-control protocol.

Screening a Project for Risk

Objective 3.3 asks how a practice evaluates and mitigates the risk a prospective project brings. The recurring exposures:

RiskMitigation
Project type outside firm experienceAssociate with an experienced firm, or decline
Owner-drafted agreement with warranties or guaranteesNegotiate standard-of-care language; the exposure is uninsurable
Uncapped or broad-form indemnity, duty to defendLimit indemnity to the architect's negligence; strike the duty to defend
Condensed or fast-tracked schedulePrice the coordination risk; document the compression in the agreement
Unfunded or thinly capitalized ownerRequire retainer, verify financing, shorten payment terms
Consequential damages exposurePreserve the mutual waiver of consequential damages

Exam Tip: When an item asks whether a firm should pursue a commission, the disqualifying facts are usually contractual, not technical. An uninsurable warranty clause, a duty to defend, or a missing limitation of liability outweighs an attractive fee — because the firm's professional liability policy will not respond to a liability it assumed by contract.

Joint Ventures (JVs) and Teaming Agreements

For large-scale, complex institutional or public projects, firms often associate through Joint Ventures or Teaming Agreements.

Joint Ventures (AIA C101)

A Joint Venture is a distinct legal entity (typically a partnership or LLC) formed by two or more independent firms under AIA C101 to pursue and execute a specific project.

  • Pass-Through Entity: Functions as a partnership for tax purposes, distributing profits and losses according to agreed ownership percentages.
  • Joint and Several Liability: Under standard prime contracts with the client, all joint venture partners are jointly and severally liable for 100% of the contract's performance. Even if the internal JV agreement allocates work 70/30, if one firm commits a catastrophic design error or defaults, the client can legally recover the entire 100% judgment from the other firm.

Teaming Agreements & Prime-Consultant Alternative

As a lower-risk alternative, firms frequently enter into a Teaming Agreement during proposal development, transitioning to a standard Prime-Consultant relationship. One firm acts as Prime Architect under AIA B101 and retains the associate firm as an independent consultant under AIA C401. This preserves contractual privity strictly between the owner and prime architect, insulating the consultant from direct owner claims and eliminating joint and several prime liability.

Test Your Knowledge

Two independent architecture firms—Firm Alpha (a renowned national stadium design firm) and Firm Beta (a well-established local firm)—execute an AIA C101 Joint Venture Agreement to design a $180 million municipal arena. Firm Alpha holds a 70% share of profits and losses, while Firm Beta holds 30%. During construction, severe water infiltration occurs due to a detailing flaw on the building enclosure designed exclusively by Firm Alpha. The municipality incurs $12 million in remedial damages and files a lawsuit against Firm Beta alone for the entire $12 million. What is Firm Beta's legal liability to the municipality?

A
B
C
D