8.2 AIA G702 & G703 Application and Certificate for Payment
Key Takeaways
AIA Document G702-1992 serves as the master payment summary and legal certificate, while AIA Document G703-1992 provides the granular item-by-item continuation sheet matching the approved Schedule of Values.
The nine summary lines of AIA G702 establish a rigorous accounting mathematical reconciliation: Original Contract Sum (Line 1), Net Change Orders (Line 2), Contract Sum to Date (Line 3), Total Completed and Stored (Line 4), Retainage (Line 5), Total Earned Less Retainage (Line 6), Previous Certificates (Line 7), Current Payment Due (Line 8), and Balance to Finish (Line 9).
AIA G703 column mechanics track cumulative progress across Column C (Scheduled Value), Column D (Work Completed from Prior Applications), Column E (Work Completed This Period), Column F (Materials Presently Stored), and Column G (Total Completed and Stored to Date).
Line 2 on G702 only incorporates fully executed Change Orders (AIA G701); pending Change Order Proposals, unresolved Claims, or unexecuted Construction Change Directives without agreed amounts cannot be added to the Contract Sum.
The contractor's application on G702 requires a formal notarized signature under oath, legally certifying that title to all work passes to the owner free of liens and that subcontractors and suppliers have been paid from prior disbursements.
8.2 AIA G702 & G703 Application and Certificate for Payment
The monthly payment application process represents one of the most critical administrative touchpoints during the construction phase. In professional architectural practice and on the ARE 5.0 CE exam, the standardized instruments governing this procedure are AIA Document G702-1992 (Application and Certificate for Payment) and its accompanying continuation sheet, AIA Document G703-1992.
Together, these two companion documents form an integrated accounting and legal framework. G702 summarizes the overarching financial status of the prime contract, calculates current retainage, and records the architect's professional certification. G703 provides the exhaustive, line-item continuation breakdown that supports every dollar claimed on G702. Mastering the mathematical reconciliation and legal boundaries of these forms is essential for construction administration.
The Mathematical Architecture of AIA Document G702
The front face of AIA Document G702 contains nine numbered lines that create an unyielding accounting reconciliation. Every ARE candidate must understand the exact formula governing each line:
Step-by-Step Line Analysis
- Line 1: Original Contract Sum: The initial baseline contract price established in AIA Document A101 (Stipulated Sum) or the initial Guaranteed Maximum Price in AIA Document A102 or A133. This figure remains constant throughout the entire life of the project.
- Line 2: Net Change by Change Orders: The net algebraic sum (additions minus deductions) of all fully executed Change Orders (AIA Document G701). On the bottom-left of G702, a Change Order Summary box tracks total additions and deductions approved in previous months and those approved during the current month. Critical Rule: Pending change orders, proposed change orders (PCOs), unresolved claims, and unexecuted Construction Change Directives (CCDs) without an agreed cost cannot be entered on Line 2.
- Line 3: Contract Sum to Date: Calculated strictly as
Line 1 ± Line 2. This reflects the official, legally binding contract value at the moment of billing. - Line 4: Total Completed and Stored to Date: Transferred directly from the grand total of Column G on the continuation sheet (G703). This represents the cumulative monetary value of all physical work installed plus eligible materials currently stored on- or off-site.
- Line 5: Retainage: The contractual percentage withheld from gross billings. Line 5 is typically divided into two distinct components:
- Line 5a: Retainage on completed work (percentage applied to the sum of G703 Columns D and E).
- Line 5b: Retainage on stored materials (percentage applied to G703 Column F).
- Total Retainage: The sum of Line 5a and Line 5b.
- Line 6: Total Earned Less Retainage: Calculated as
Line 4 minus Line 5 (Total Retainage). This represents the net cumulative amount the contractor is legally entitled to have received from project inception through the current billing period. - Line 7: Less Previous Certificates for Payment: The figure entered here must exactly match Line 6 from the immediately preceding Certificate for Payment that was certified by the architect. It reflects what the owner was previously certified to pay, whether or not the owner has physically transferred the cash.
- Line 8: Current Payment Due: Calculated as
Line 6 minus Line 7. This is the net dollar amount requested by the contractor—and, if certified without adjustment, the amount the owner must disburse for the current billing cycle. - Line 9: Balance to Finish, Including Retainage: Calculated as
Line 3 minus Line 6. This demonstrates to the owner, architect, and surety exactly how much unbilled and unpaid money remains in the Contract Sum to complete the remaining scope. Notice that Line 9 includes all retained funds, because retainage has not yet been paid out to the contractor.
Columnar Mechanics of AIA Document G703 (Continuation Sheet)
While G702 provides the overarching executive summary, AIA Document G703 contains the detailed itemized breakdown that substantiates Line 4. The columns of G703 are organized sequentially from A through I:
Column-by-Column Breakdown
- Column A (Item No.): Numerical sequence (e.g., 001, 002, 003) corresponding to the line items of the approved Schedule of Values.
- Column B (Description of Work): Specific trade, specification section, or work package title (e.g., '04 22 00 - Concrete Unit Masonry - Exterior Walls').
- Column C (Scheduled Value): The approved dollar allocation for each line item from the Schedule of Values. The sum of Column C must exactly equal G702 Line 3 (Contract Sum to Date). When a Change Order is executed, it is added as a new line item at the bottom of Column C, or incorporated into existing line items.
- Column D (Work Completed from Previous Applications): Cumulative dollar value of work completed in all prior billing periods. This is populated by taking the sum of
Column D + Column Efrom the preceding month's G703. Crucial Rule: Column D never includes stored materials from prior months; it records only physical work incorporated in place. - Column E (Work Completed This Period): The dollar value of physical work installed on site during the current billing period.
- Column F (Materials Presently Stored): The dollar value of eligible materials currently stored on- or off-site that have not yet been incorporated into the physical structure. If an item was billed in Column F last month and installed this month, it moves into Column E, and Column F is reduced accordingly.
- Column G (Total Completed and Stored to Date): Calculated as
Column D + Column E + Column F. The grand total at the bottom of Column G transfers directly to G702 Line 4. - Unlettered percentage column (% Completed): Calculated as
Column G ÷ Column C. Indicates the cumulative percentage of completion for that specific line item. - Column H (Balance to Finish): Calculated as
Column C minus Column G. Indicates the remaining dollar value required to complete that specific work item.
Auditing the G702/G703: Common Errors and Double Billing
During payment application review, architects must perform a rigorous arithmetic and procedural audit. Several recurring errors and contractor billing traps frequently arise:
The 'Stored Materials Rollover' Trap (Double Billing)
A common contractor accounting error—either inadvertent or intentional—occurs when materials move from storage to installation.
Example: In Month 2, a contractor delivers $50,000 of structural steel to the jobsite and bills $50,000 in Column F (Materials Presently Stored). In Month 3, the steel is erected. The contractor enters $50,000 into Column E (Work Completed This Period). However, if the contractor fails to reduce Column F back to $0, the total in Column G becomes $100,000 (Col D [\$0] + Col E [\$50,000] + Col F [\$50,000]), resulting in the owner paying twice for the exact same steel!
Line 7 Mismatch
Contractors sometimes manipulate Line 7 (Less Previous Certificates for Payment) by entering the actual cash amount received from the owner rather than the amount certified on Line 6 of the previous certificate. If the owner withheld a portion of the previous certificate due to a dispute or cash-flow constraint, entering the cash received into Line 7 artificially inflates Line 8 (Current Payment Due), transferring an unapproved dispute back onto the current certificate. Line 7 must strictly match Line 6 of the previous architect-certified G702.
Unexecuted Change Orders on Line 2
A contractor may perform work under an emergency field directive or submit a Change Order Proposal (COP) for $45,000. If the contractor adds this $45,000 to Line 2 before the change order is formally executed with signatures by the Owner, Architect, and Contractor, the application must be rejected or modified. Pending proposals do not establish an adjustment. A201 § 7.3.9 separately permits the architect’s interim CCD determination to adjust the contract sum on the same basis as a change order, subject to claims; reconcile any such authorized adjustment and avoid double counting when a later CO records it.
Contractor's Sworn Certification and Notarization
Directly beneath the summary lines on AIA Document G702 sits the Contractor's Application for Payment block. This is not merely an invoice; it is a sworn legal affidavit executed under oath.
By signing the G702, the contractor formally certifies to the owner that:
- The Work covered by this Application for Payment has been completed in accordance with the Contract Documents;
- All amounts have been paid by the Contractor for Work for which previous Certificates for Payment were issued and payments received from the Owner; and
- The current payment shown herein is now due.
Mandatory Notarization
AIA Document G702 requires a formal Notary Public seal, signature, and commission expiration date. An unnotarized G702 is legally defective and administratively invalid under standard AIA contract protocols. If a contractor submits an application without a notary acknowledgment, the architect should immediately return it for proper execution while promptly communicating the defect and observing the applicable review obligations.
Column I is the optional variable retainage column. The percentage column between G and H is unlettered. Distinguish G703 H (scheduled value minus completed/stored value, excluding retainage) from G702 Line 9 (contract sum minus earned-less-retainage, including retainage).
AIA G702 Summary Lines & G703 Column Mapping Master Reference
The following table outlines the cross-document mathematical integration between AIA Document G702 and AIA Document G703:
| Document Line / Column | Title / Identifier | Mathematical Formula / Source | Audit Check / Verification Standard |
|---|---|---|---|
| G702 Line 1 | Original Contract Sum | Contract Agreement (A101 / A102 / A103) | Must match baseline contract sum exactly; never changes. |
| G702 Line 2 | Net Change by Change Orders | Algebraic sum of Change Order Summary table | Reconcile executed COs and any § 7.3.9 authorized interim CCD adjustment. |
| G702 Line 3 | Contract Sum to Date | Line 1 ± Line 2 | Must equal the sum total of G703 Column C. |
| G702 Line 4 | Total Completed & Stored | Grand Total of G703 Column G | Reconcile against field observation percentages. |
| G702 Line 5a | Retainage on Work Completed | (Col D + Col E) × Retainage % | Verify against contract retainage terms (e.g., 5% or 10%). |
| G702 Line 5b | Retainage on Stored Materials | Col F × Retainage % | Ensure stored materials carry appropriate retainage withholding. |
| G702 Line 5 Total | Total Retainage Withheld | Line 5a + Line 5b | Check arithmetic sum of lines 5a and 5b. |
| G702 Line 6 | Total Earned Less Retainage | Line 4 minus Line 5 Total | Represents cumulative net earnings from project start. |
| G702 Line 7 | Previous Certificates | Line 6 of Prior Certificate | Must exactly match prior certified Line 6, regardless of owner cash paid. |
| G702 Line 8 | Current Payment Due | Line 6 minus Line 7 | Net disbursement authorized for the current billing cycle. |
| G702 Line 9 | Balance to Finish w/ Retainage | Line 3 minus Line 6 | Tracks remaining funds available in the Contract Sum. |
| G703 Column C | Scheduled Value | Approved Schedule of Values (SOV) | Sum of Col C must reconcile to G702 Line 3. |
| G703 Column D | Previous Completed Work | Col D + Col E of Prior G703 | Never includes stored materials; reflects prior physical work in place. |
| G703 Column E | Work Completed This Period | Field installed work in current cycle | Audit against architect's field reports and site observations. |
| G703 Column F | Materials Presently Stored | Validated on-site & off-site inventory | Ensure items installed this month are deducted from Column F. |
| G703 Column G | Total Completed & Stored | Col D + Col E + Col F | Grand total must equal G702 Line 4. |
| G703 percentage column | % Completed | Col G ÷ Col C | Check for individual line item overbilling (>100%). |
| G703 Column H | Balance to Finish | Col C minus Col G | Remaining value to be billed on each specific line item. |
A general contractor submits Application and Certificate for Payment No. 4 using AIA Documents G702 and G703. On Line 1, the Original Contract Sum is listed as $3,000,000. On Line 2, the contractor lists $65,000 for 'Net Change by Change Orders,' bringing Line 3 (Contract Sum to Date) to $3,065,000. During document audit, the project architect discovers that while Change Order No. 1 for $20,000 was signed by the Owner, Architect, and Contractor, the remaining $45,000 represents Change Order Proposal No. 2, which has been agreed to verbally by the owner and architect but has not yet been formally signed or executed. How should the architect address Line 2 and Line 3?
Certify the payment application as submitted because verbal approval from the owner constitutes a binding constructive change order under common law principles.
Disallow the unexecuted $45,000 proposal, modify Line 2 to $20,000, recalculate Line 3 as $3,020,000, adjust subsequent calculations accordingly, and notify the owner and contractor in writing.
Reject the entire payment application package immediately and require the contractor to halt all construction until Change Order No. 2 is executed.
Allow the $45,000 on Line 2 but withhold an equivalent $45,000 on Line 5b under stored materials retainage to protect the owner.
On Application for Payment No. 5, G703 Column F (Materials Presently Stored) listed $40,000 for fabricated structural steel trusses stored securely on site. During the month covered by Application No. 6, the contractor fully erected these trusses into the roof framing and also erected an additional $30,000 of newly delivered structural steel beams. In preparing G703 for Application No. 6, how should the contractor record these transactions to accurately reflect progress and prevent double billing?
Enter $70,000 in Column D, enter $0 in Column E, and maintain $40,000 in Column F.
Maintain $40,000 in Column F, enter $30,000 in Column E, and leave Column D unchanged.
Transfer $40,000 from Column F directly into Column D, and enter $70,000 into Column E.
Enter $70,000 in Column E (representing all work installed this period), reduce Column F to $0 (or the value of remaining uninstalled steel), and carry forward only previously installed work in Column D.
An architect is auditing a contractor's draft AIA G702 pay application and verifies the following figures: Original Contract Sum (Line 1) = $2,000,000; Net Change by Change Orders (Line 2) = $50,000; Total Completed & Stored to Date (Line 4) = $1,000,000; Retainage at 10% (Line 5) = $100,000; Total Earned Less Retainage (Line 6) = $900,000; Previous Certificates for Payment (Line 7) = $600,000; Current Payment Due (Line 8) = $300,000. In reviewing Line 9 (Balance to Finish, Including Retainage), the contractor entered $1,050,000. What is the mathematically correct figure that must be entered on Line 9?
$1,150,000, calculated as Line 3 (Contract Sum to Date of $2,050,000) minus Line 6 (Total Earned Less Retainage of $900,000).
$1,050,000, calculated as Line 3 (Contract Sum to Date of $2,050,000) minus Line 4 (Total Completed & Stored of $1,000,000).
$950,000, calculated as Line 1 (Original Contract Sum of $2,000,000) minus Line 4 (Total Completed & Stored of $1,000,000) minus Line 5 ($100,000).
$1,450,000, calculated as Line 3 (Contract Sum to Date of $2,050,000) minus Line 7 (Previous Certificates of $600,000).
Source and application
A201-2017 official sample; AIA payment-form instructions. Checked October 16, 2026. Apply the cited form edition and the actual project amendments, adopted codes and supplied scenario assumptions. Numerical examples are teaching inputs unless expressly attributed to a requirement.