6.3 Construction Change Directives (AIA G714)
Key Takeaways
A Construction Change Directive (AIA Document G714-2017) is a written order prepared by the architect and signed by the Owner and Architect directing a change in the Work prior to agreement on adjustment in Contract Sum, Contract Time, or both.
Unlike a Change Order, a CCD does not require contractor consent or signature to be binding; upon receipt of a CCD signed by Owner and Architect, the contractor must promptly proceed with the work under AIA A201 Section 7.3.5.
Under AIA A201 Section 7.3.4, cost adjustments for a CCD are determined through four methods: lump sum, unit prices, cost plus agreed fee, or actual expenditures and savings determined by the architect with an allowance for overhead and profit.
Contractor cash flow is protected under Section 7.3.9, which grants the contractor the right to bill for undisputed amounts of work completed under a CCD in interim Applications for Payment.
If the contractor signs and agrees to the CCD, it converts immediately into a Change Order; if the contractor disputes the architect's determination of cost or time, the contractor must file a Claim under Article 15 with the Initial Decision Maker (IDM).
6.3 Construction Change Directives (AIA G714)
In an ideal construction project, every modification to the design drawings and specifications would be thoroughly analyzed, estimated by the contractor, reviewed by the architect, and formalized into a bilaterally signed Change Order before any field work commences. In reality, unexpected site conditions, supply chain collapses, building code interpretations, and owner-directed scope revisions frequently demand immediate execution to prevent catastrophic schedule delays.
When the owner and contractor cannot reach agreement on the cost or time required for a change—or when the urgency of the work precludes the time required to negotiate a Change Order—the contract administration framework relies upon the Construction Change Directive (CCD). Standardized under AIA Document G714-2017 and governed by AIA Document A201-2017 Section 7.3, the CCD is one of the most powerful administrative instruments available to the owner and architect.
Anatomy and Purpose of the Construction Change Directive: AIA Document G714-2017
AIA Document A201-2017 Section 7.3.1 defines the instrument with precision:
'A Construction Change Directive is a written order prepared by the Architect and signed by the Owner and Architect, directing a change in the Work prior to agreement on adjustment, if any, in the Contract Sum or Contract Time, or both. The Owner and Architect may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions, or other revisions, the Contract Sum and Contract Time being adjusted accordingly.'
The Bipartite Signature Requirement
A defining characteristic of AIA Document G714-2017 is its execution protocol:
- Prepared by: The Architect.
- Signed by: The Owner and the Architect.
- Contractor Signature: NOT REQUIRED for the directive to take legal effect!
This bipartite signature structure (Owner + Architect) distinguishes the CCD from a Change Order (which requires tripartite agreement: Owner + Contractor + Architect). The architect acts as the professional advisor certifying that the directed work falls within the general scope of the original contract and design intent, while the owner exercises ownership authority to mandate the expenditure and assume financial responsibility.
Strategic Purpose: Breaking Schedule Deadlocks
Consider an active jobsite where deep excavation uncovers an unmapped, abandoned municipal storm sewer pipe directly beneath the footprint of the central elevator core. Soil stability is deteriorating, groundwater is filling the pit, and tower crane operations are frozen. The general contractor submits a change order proposal demanding $150,000 and a 30-day schedule extension to bypass the pipe and remediate the subgrade. The owner believes the price is inflated by $70,000 and refuses to sign a Change Order.
Without a CCD, the jobsite would shut down while the parties litigated or negotiated pricing. Every idle day would generate massive delay damages. By issuing an AIA Document G714 CCD signed by owner and architect, the owner commands the contractor to begin immediate pipe removal and soil stabilization, deferring the final pricing and schedule determination until after the work is executed or substantiated.
The Contractor's Mandatory Obligation to Proceed
A critical rule tested on the ARE is found in AIA Document A201-2017 Section 7.3.5:
'Upon receipt of a Construction Change Directive, the Contractor shall promptly proceed with the change in the Work involved and advise the Architect of the Contractor’s agreement or disagreement with the method, if any, provided in the Construction Change Directive for determining the proposed adjustment in the Contract Sum or Contract Time.'
Upon receiving a properly executed CCD signed by the Owner and Architect, the contractor cannot strike, stop work, or refuse to perform the directive. The contractor cannot say: 'We will not touch this excavation until the owner signs a Change Order for our $150,000 lump sum.' Refusal to proceed with work directed by a valid CCD constitutes a material breach of contract, subjecting the contractor to termination for cause under AIA A201 Section 14.2.
The Four Valuation Methodologies Under AIA A201 Section 7.3.4
When a CCD is issued, the document must state the proposed basis of adjustment in the Contract Sum. AIA Document A201-2017 Section 7.3.4 establishes exactly four contractual methods for determining the cost adjustment:
- Mutual Acceptance of a Lump Sum: A lump sum properly itemized and supported by sufficient substantiating data to permit evaluation (A201 § 7.3.4.1).
- Unit Prices: Unit prices stated in the Contract Documents or subsequently agreed upon (A201 § 7.3.4.2). (For example, a contractually established unit price of $65 per cubic yard for mass excavation and backfill).
- Cost to Be Determined in a Manner Agreed Upon by the Parties and a Mutually Acceptable Fixed or Percentage Fee: (A201 § 7.3.4.3). (For example, negotiated time-and-materials with an agreed 10% fee).
- Actual Cost Determined by the Architect (A201 § 7.3.4.4): If the contractor does not respond promptly or disagrees with the method of adjustment, the Architect determines the adjustment on the basis of reasonable expenditures and savings of those performing the Work attributable to the change, including an allowance for overhead and profit (O&P).
The Force Account / Architect's Determination (§ 7.3.4.4)
When the parties cannot agree on a lump sum or unit price, Section 7.3.4.4 governs. The contractor must keep an itemized, daily open-book accounting of all actual expenditures, substantiated by daily work tickets, material invoices, equipment rental receipts, and certified payroll records signed by the architect's field representative.
Under Sections 7.3.4.1 through 7.3.4.5, allowable costs are strictly limited to:
- Direct Labor: Wages of construction workers directly performing the change, including social security, old age and unemployment insurance, fringe benefits, and workers' compensation insurance.
- Materials & Equipment: Costs of materials, supplies, and equipment incorporated into the work, including transportation and storage.
- Machinery Rental: Rental costs of machinery and equipment rented from third parties (exclusive of hand tools), or contractor-owned equipment at standard industry rates (AED Green Book).
- Bonds, Permits & Taxes: Additional premiums for payment and performance bonds, permit fees, and sales/use taxes directly related to the changed work.
- Supervision: Additional costs of field supervisory personnel directly assigned to the site during the execution of the changed work.
- Overhead and Profit (O&P): A reasonable allowance for overhead and profit as stipulated in the agreement or supplementary conditions.
Net Credit Rule for Deleted Work (§ 7.3.8)
If a CCD results in both additions and deletions of work, the allowance for overhead and profit is calculated based on the net increase, if any. If the change results in a net deletion of scope, the amount of credit allowed to the owner is the actual net cost confirmed by the architect. The contractor does not forfeit their overhead and profit on deleted work; the contractor retains the original anticipated profit on the omitted scope.
Direct Allowable Costs vs. Excluded Overhead under Section 7.3.4
The following table outlines what costs the architect may certify under Section 7.3.4.4 versus costs that must be absorbed within the contractor's overhead allowance:
| Cost Category | Allowable as Direct CCD Cost | Excluded (Covered by Contractor O&P Markup) |
|---|---|---|
| Trade Labor | Hourly wages, union fringes, FICA, FUTA, SUTA, Workers' Comp for workers executing the change. | Executive salaries, corporate officer compensation, off-site accounting/estimating staff. |
| Materials | Actual purchase invoice cost, freight, off-loading, and consumable supplies used in work. | General office supplies, drafting paper, home office printing, administrative software. |
| Equipment | Third-party equipment rental invoices (excavators, boom lifts, generators) and fuel. | Hand tools of nominal value (shovels, drills, hammers, tool belts) owned by workers. |
| Supervision | Verified overtime or dedicated field superintendent hours directly necessitated by the change. | Principal-in-charge oversight, branch office management visits, routine company executives. |
| Insurance & Bonds | Actual incremental increases in performance/payment bond premiums and builder's risk. | General commercial liability policy baseline annual premiums already carried. |
Interim Billing Rights and Payment Certification (A201 § 7.3.9)
A common fear among contractors is that performing work under an unpriced CCD will drain their operating cash flow while disputes linger. AIA Document A201-2017 Section 7.3.9 provides robust financial protection:
'Pending final determination of the total cost of a Construction Change Directive to the Owner, the Contractor may request payment for Work completed under the Construction Change Directive in Applications for Payment. The Architect will make an interim determination for purposes of monthly certification for payment for those costs and certify for payment the amount that the Architect determines, in the Architect’s professional judgment, to be reasonably justified.'
This provision is essential. The contractor does not have to wait until the entire CCD is completed, audited, and converted to a Change Order to get paid. Each month, the contractor submits documented direct expenditures for the CCD on AIA Document G702/G703 (Application and Certificate for Payment). The architect must review the backup tickets, certify the undisputed amounts, and issue the payment certificate. The owner must disburse funds for all certified undisputed work.
Resolution Paths: Conversion to Change Order vs. Article 15 Dispute
Once a CCD is issued and work commences, the administrative process follows one of two distinct trajectories depending on whether the contractor agrees with the proposed adjustments.
Path A: Contractor Agreement and Conversion (A201 § 7.3.7)
If the contractor agrees with the adjustments in Contract Sum and Contract Time proposed in the CCD, the contractor signs the designated acceptance line on AIA Document G714 and returns it to the architect. Under Section 7.3.7, such agreement is effective immediately and shall be recorded as a Change Order. The CCD is retired, and an official AIA Document G701 Change Order is executed.
Path B: Contractor Disagreement and IDM Claim (A201 § 7.3.10)
If the contractor objects to the architect's valuation under Section 7.3.4.4 or disputes the time extension, the contractor submits a formal written disagreement. The architect issues an official administrative determination. If the contractor rejects this determination, the contractor must file a Claim under AIA Document A201 Article 15 with the Initial Decision Maker (IDM) within 21 days of the architect's determination (A201 § 15.1.3). The dispute proceeds through IDM ruling, mediation under AIA Document A201 Section 15.3, and binding dispute resolution (arbitration or litigation) under Section 15.4.
During the construction of a hospital emergency room expansion, unmapped subterranean medical gas lines are uncovered that conflict with the foundation footings. Re-routing the lines immediately is critical to keep the project on schedule. The owner and general contractor reach a bitter impasse regarding the cost: the contractor demands $95,000 via a lump-sum Change Order, while the owner's cost consultant estimates the work at $48,000. The contractor threatens to demobilize the excavation subcontractor until a Change Order is signed. How should the architect resolve this operational deadlock under AIA A201 contract terms?
Instruct the owner to accept the contractor's $95,000 demand under duress to avoid compounding critical-path delay damages.
Suspend all site construction activities and refer the matter immediately to the Initial Decision Maker for a binding 60-day adjudication.
Issue an Architect's Supplemental Instruction (G710) ordering the contractor to reroute the medical gas lines at no additional cost to the owner.
Prepare an AIA Document G714 Construction Change Directive signed by the Owner and Architect ordering the contractor to promptly proceed with the work.
A general contractor executes critical foundation underpinning under a valid AIA Document G714 Construction Change Directive (CCD) where the method of cost adjustment is determined under Section 7.3.4 (architect-determined reasonable expenditures and savings). In the subsequent monthly payment application, the contractor includes the following cost items for the underpinning work: (1) Direct trade labor and union fringe benefits: $38,000; (2) Hydraulic jack and underpinning beam rental: $14,000; (3) Home office corporate executive oversight and legal consulting: $12,000; (4) Additional permit fees and engineering inspection bonds: $3,500; (5) Rental of ordinary hand tools for laborers: $1,800. In reviewing the application, which items must the architect disallow as direct CCD costs? Assume the contract contains no modification expanding the default direct-cost categories.
Items 1 and 2 only, because equipment rental and union fringe benefits are classified as non-reimbursable contractor overhead.
Items 3 and 5 only, because corporate home office executive expenses and worker hand tools are non-allowable direct costs and must be absorbed within contractor overhead.
Item 4 only, because statutory permit fees and inspection bonds cannot be billed until the project achieves Substantial Completion.
All items must be disallowed until the entire underpinning scope is completed, audited, and converted into an executed AIA G701 Change Order.
A contractor has been performing deep structural remedial work for two months pursuant to a properly executed AIA Document G714 Construction Change Directive (CCD). The total cost of the work is fiercely contested: the contractor projects final completion at $220,000, while the architect's estimate under Section 7.3.4 is $145,000. On the current month's Application for Payment (G702/G703), the contractor requests $80,000 for verified, documented trade labor and structural steel installed during the billing period. The owner instructs the architect to certify $0 for the CCD line item, arguing that no money is due until the parties reach complete agreement on the final CCD total. How must the architect proceed under AIA A201 Section 7.3.9?
Withhold payment certification for the entire $80,000 as instructed by the owner, because an architect cannot certify funds that exceed the owner's explicit billing authorization.
Issue a Certificate for Payment for $40,000, representing a mandatory 50% statutory reduction for contested change directive line items.
Certify the $80,000 for payment if the architect determines in professional judgment that the costs are substantiated and reasonably justified, because interim billing of undisputed amounts is an explicit contractor right.
Rescind the Construction Change Directive immediately and issue an Architect's Supplemental Instruction directing the contractor to demobilize.
Source and application
A201-2017 official sample. Checked October 16, 2026. Apply the cited form edition and the actual project amendments, adopted codes and supplied scenario assumptions. Numerical examples are teaching inputs unless expressly attributed to a requirement.