PracticeVideosBlogFlashcards
All Practice Exams

Free Practice Questions for ARE 5.0: CE

Exam-style questions and explanations by OpenExamPrep.

✓ No registration✓ No credit card
Exam pass rate: 61%
130+ Questions
100% Free
Exam Review

Key Facts: ARE 5.0: CE Exam

75

Total Items

NCARB

3 hrs

Test Time

NCARB

61%

Pass Rate

NCARB 2025, all CE candidates

$263

Exam Fee

NCARB

4

Content Sections

NCARB

Version-based

Score Validity

NCARB score validity policy

NCARB ARE 5.0 CE has 75 items (68 scored and 7 pretest), 3 hours testing, an optional 30-minute break and a 3-hour-40-minute appointment. The 2025 CE pass rate was 61% across first-time and repeat candidates. Current Guidelines allow up to seven case studies and up to 16 case-study items. Topics cover bidding, construction observation, administration, closeout and performance evaluation.

Sample ARE 5.0: CE Practice Questions

Try these sample questions to review concepts for the ARE 5.0: CE exam. Each question includes a detailed explanation. Start the interactive quiz above for the full 130+ question experience with AI tutoring.

1Under AIA Document A201-2017 General Conditions, who is responsible for means, methods, techniques, sequences, and procedures of construction?
A.The architect
B.The owner
C.The contractor
D.Jointly by architect and contractor
Explanation: AIA A201-2017 Section 3.3.1 makes the contractor solely responsible for and in control of construction means, methods, techniques, sequences, and procedures. The architect's responsibility is limited to conformance of the completed work with the contract documents, not how the contractor builds it.
2Which AIA document is the standard form of agreement between owner and contractor where the basis of payment is a stipulated sum (lump sum)?
A.AIA A101
B.AIA A102
C.AIA A103
D.AIA A201
Explanation: AIA A101-2017 is the owner-contractor agreement used when the contract sum is a stipulated lump sum. A102 and A103 are cost-plus-fee agreements (with and without GMP), and A201 is the General Conditions, not an owner-contractor agreement.
3An owner is using AIA A102-2017 for a construction project. What is the defining feature of this agreement?
A.Lump sum with no contingency
B.Cost of the work plus a fee with a Guaranteed Maximum Price
C.Cost of the work plus a fee with no Guaranteed Maximum Price
D.Construction management at-risk with multiple prime contractors
Explanation: AIA A102-2017 is the owner-contractor agreement based on the cost of the work plus a contractor's fee, with a Guaranteed Maximum Price (GMP). The GMP caps the owner's exposure while still using cost-plus accounting and shared savings provisions.
4Which AIA document is used by a contractor to submit a statement of qualifications during prequalification or bidding?
A.AIA A305
B.AIA A310
C.AIA A312
D.AIA A701
Explanation: AIA Document A305, Contractor's Qualification Statement, is completed by a prospective bidder to provide the owner information about experience, references, financial standing, and personnel. A310 is a bid bond and A312 is performance/payment bonds.
5Which AIA document is issued to contractors during bidding to provide the rules, requirements, and procedures for submitting bids?
A.AIA A101
B.AIA A201
C.AIA A701 Instructions to Bidders
D.AIA G612
Explanation: AIA A701, Instructions to Bidders, sets out procedures for bidders, including bid form requirements, bid security, bid opening, and how to handle addenda and substitutions. It is part of the bidding documents but is not part of the executed contract.
6During bidding, the architect identifies an error in the drawings that affects scope. What is the correct mechanism to formally communicate this change to all bidders?
A.A request for information (RFI)
B.An addendum issued before the bid opening
C.A change order issued after award
D.An architect's supplemental instructions (ASI)
Explanation: Before bids are opened, modifications to the bidding documents must be issued as an addendum so all bidders price the same scope. RFIs, ASIs, and change orders are construction-phase tools and do not exist before a contract is executed.
7An owner wants to compare base scope against optional scope items at bid time so the award decision can be made based on available budget. Which device should the architect use?
A.Allowances
B.Alternates
C.Unit prices
D.Contingencies
Explanation: Alternates are pre-priced, owner-selectable adds or deducts from the base bid, used precisely to expand or contract the scope after bids are received based on the budget. Allowances cover unspecified items at fixed dollars, unit prices are quantity-based, and contingencies are reserves held by owner or contractor.
8Which project delivery method is MOST appropriate when an owner needs the lowest first-cost bid and the design is complete and well-defined?
A.Construction management at-risk
B.Design-build
C.Design-bid-build (competitive lump sum)
D.Integrated project delivery
Explanation: Design-bid-build with a competitive lump-sum award is the traditional method for getting the lowest first-cost bid on a fully designed project. The owner holds separate contracts with the architect and the lowest qualified bidder, and price competition is maximized.
9Under AIA A101-2017 with A201 General Conditions, who has the authority to bind the owner to a change in the contract sum?
A.The architect alone
B.The contractor alone
C.The owner (or the owner's authorized representative)
D.The construction manager
Explanation: Only the owner — or someone the owner has formally designated — can authorize a change that increases the contract sum. The architect prepares and certifies change documents and may authorize minor changes that do not affect cost or time, but the owner signs change orders.
10A general contractor submits a request for clarification about a dimension on the drawings during construction. Which AIA form is most commonly used to track this request?
A.G701 Change Order
B.G710 Architect's Supplemental Instructions
C.G716 Request for Information
D.G702 Application for Payment
Explanation: AIA G716, Request for Information, is the standard form used by the contractor to ask the architect for clarification of contract documents during construction. Properly logged RFIs become part of the project record and may support later change orders if the answer alters scope.

About the ARE 5.0: CE Exam

The ARE 5.0 Construction & Evaluation (CE) division tests an architect's ability to perform construction-phase services and project closeout activities. The exam covers four content areas: Pre-Construction Activities (17-23%), Construction Observation (32-38%), Administrative Procedures & Protocols (32-38%), and Project Closeout & Evaluation (7-13%). CE relies heavily on AIA contract documents — A101/A102/A103 owner-contractor agreements, A201 General Conditions, A305 contractor qualifications, A701 Instructions to Bidders, and the G-series administrative forms (G701 change orders, G702/G703 payment applications, G704 substantial completion, G706/G706A/G707 final payment, G711 field reports, G712 submittal log, G710 ASIs, G714 construction change directives, G716 RFIs).

Exam sponsor: NCARB (PSI). The requirements and fees below concern the certification or admission exam, separate from our free practice resources.

Questions

75 questions

Time Limit

3 hours (3h 40m total appointment with 30-min break)

Passing Score

Pass/fail by NCARB cut score (typically about 58-66% of scored items correct)

Exam / Certification Fees

$263

Exam sponsor website

Reported exam pass rate: 61%. NCARB 2025 CE pass rate across first-time and repeat candidates This describes exam candidates, not OpenExamPrep users or results from using our resources. Exam sponsor website

Fees, eligibility, and exam policies can change. Confirm them with the exam sponsor before applying or paying.

Our practice resources: topics covered

We aim to reflect publicly available exam outlines and topic information in our study resources. Coverage, format, and difficulty may differ from the actual exam, and we cannot guarantee that every detail is accurate or current. Confirm exam requirements, fees, and policies with the official exam sponsor.

17-23%

Pre-Construction Activities

Bidding procedures, owner-contractor agreements (A101/A102/A103), Instructions to Bidders (A701), contractor qualifications (A305), addenda, alternates, allowances, unit prices, delivery method selection

32-38%

Construction Observation

Site visits, field reports (G711), conformance with contract documents, schedule reviews, RFIs (G716), means and methods, code compliance, concealed conditions

32-38%

Administrative Procedures & Protocols

Submittals (G712), shop drawings, payment applications (G702/G703), schedule of values, retainage, change orders (G701), construction change directives, ASIs (G710), CCDs (G714), claims, dispute resolution

7-13%

Project Closeout & Evaluation

Substantial completion (G704), punch lists, final payment (G706/G706A/G707), lien waivers, warranties, correction-of-work period, record drawings, O&M manuals, post-occupancy evaluation

Preparing for the ARE 5.0: CE Exam

What You Need to Know

  • Passing score: Pass/fail by NCARB cut score (typically about 58-66% of scored items correct)
  • Exam length: 75 questions
  • Time limit: 3 hours (3h 40m total appointment with 30-min break)
  • Exam / certification fees: $263 Official sources

Using Our Practice Resources

  • Work through all 130 available questions
  • Review every answer and explanation
  • Track weak areas and revisit them
  • Use our AI tutor for tough concepts

ARE 5.0: CE: Suggested Study Strategy

1Use NCARB’s free CE practice exam to identify weaknesses and learn the current testing interface.
2Read A201-2017 with the actual clauses: interpret roles, changes, payment, claims and completion rather than memorizing unsupported deadlines.
3Distinguish G710 supplemental instructions, G714 construction change directives and G701 change orders by authority, signatures and cost/time effects.
4Calculate payment applications using G702 and G703; check stored-material rollover, retainage and prior certificates.
5Use the project’s actual supplementary conditions and supplied scenario assumptions; AIA forms do not create one national procurement or lien statute.
6Distinguish the one-year correction period from the general warranty, special warranties and jurisdiction-specific claim limits.
7Study the contractor’s initial punch list, G704 responsibilities, final-payment conditions and first-year facility evaluation.

Frequently Asked Questions

How long is the ARE 5.0 CE exam?

NCARB lists 75 CE items: 68 scored and 7 unscored pretest items. Testing lasts 3 hours, the optional break is 30 minutes, and the total appointment is 3 hours 40 minutes. The current Guidelines list up to seven case studies and up to 16 case-study items; each case has one or two resources.

What is the current ARE CE fee?

NCARB lists $263 for an individual ARE division or retake. An active NCARB Record is also required; licensure-candidate Record application and annual renewal fees are each $105 under the current fee schedule. Check NCARB before purchasing.

How is CE scored, and what is its pass rate?

NCARB’s CE cut-score range is 58–66% of scored items depending on the exam form. This differs from the 2025 CE pass rate of 61%, which covers first-time and repeat candidates. Failing official reports include a scaled score and diagnostic feedback; a pass is reported as pass/fail without a scaled score.

Who can schedule ARE CE?

Request eligibility through your NCARB Record and meet the requirements of the jurisdiction where you seek initial licensure. Jurisdiction rules govern education and experience pathways. Schedule through the NCARB Record with PSI after eligibility is granted.

When can I retake CE, and do scores expire after five years?

A failed division may be retaken after 60 days, with no more than three attempts at the same division in a 12-month period. NCARB replaced the five-year rolling clock with score validity based on the exam version taken and the immediately following version.

How should I plan CE study?

Use the official objectives and a free NCARB practice exam to identify gaps. Review bidding, construction observation, submittal and change workflows, payment calculations, closeout and first-year performance. OpenExamPrep’s suggested 40–80-hour planning budget is an adjustable study recommendation, not an NCARB requirement or guarantee.

Which official resources and contract forms should I use?

Start with NCARB’s current ARE Guidelines, CE division page and free practice exam in your NCARB Record. Consult the contract editions identified in the Guidelines. For change administration, G710 is Architect’s Supplemental Instructions, G714 is a Construction Change Directive and G701 is a Change Order.