18.2 Dependencies and What Drives the Schedule

Key Takeaways

  • Dependencies determine sequence, and a schedule with missing dependencies produces dates that cannot be achieved.
  • Business-as-usual constraints — operational freezes, seasonal peaks, shift patterns, and staff availability — routinely drive project dates more than internal logic does.
  • Cost constraints affect the schedule by limiting how much work can run in parallel and how much resource can be bought in.
  • Quality requirements affect the schedule through the time needed for testing, review, and rectification of defects.
  • Adding mandatory scope without changing the end date or removing other work is not a plan — it is an unresolved constraint that will surface as a late overrun.
Last updated: August 2026

Outcome 20b asks you to understand there are links and dependencies between activities within a project and business-as-usual activities, and states plainly that business-as-usual activities, costs, quality, risks and scope can all impact the schedule. The examinable idea is that a schedule is not an independent artefact — it is the place where every other constraint shows up.

Dependencies between project activities

A dependency is a logical or imposed relationship that constrains the order or timing of activities.

Common dependency types (conceptual)

TypeMeaningSimple example
Finish-to-Start (FS)Successor cannot start until predecessor finishesPour foundations → erect steel
Start-to-Start (SS)Successor cannot start until predecessor startsBegin documentation when design starts
Finish-to-Finish (FF)Successor cannot finish until predecessor finishesTesting finishes with final defect fix delivery
Start-to-Finish (SF)Rare; successor finish constrained by predecessor startSpecialised shift handover patterns

Most project logic is finish-to-start. Lags (delays) and leads (overlaps) refine timing (for example, cure time lag after concrete pour).

Internal vs external dependencies

CategoryDescriptionManagement focus
Internal (within project)Between project activities/teamsTeam coordination, integrated schedule
ExternalOn suppliers, regulators, other projects, utilitiesInterface agreements, lead times, escalation
Mandatory / hard logicPhysical or contractual necessityCannot "wish away"; plan around it
Discretionary / soft logicPreferred practice or policyChallenge if optimisation needs re-sequence
Resource dependenciesSame scarce people/equipment needed by parallel workResource smoothing/levelling (resource LO)

Critical path (conceptual)

The critical path is the longest path of dependent activities through the network that determines the earliest project completion (for a given logic and durations). Activities on the critical path have zero (or least) total float — delay to them delays the end date unless logic or duration changes.

You do not need deep network mathematics for PMQ, but you must reason:

  • Adding scope or quality gates on the critical path extends duration unless compensated elsewhere.
  • Fast-tracking overlaps critical activities (more risk); crashing shortens critical durations (usually more cost) — next section.
  • Monitoring critical and near-critical paths is essential because float can disappear when reality changes.

Links and dependencies with BAU

Projects rarely run in a vacuum. BAU (operations) creates dependencies that pure project networks often miss:

BAU interactionSchedule impactExample
Blackout / peak periodsForbidden cutover windowsNo retail go-live before Christmas peak
Shared resourcesOperations staff needed for testing/trainingClinic nurses cannot leave wards for five-day workshops
Operational data / environmentsAccess only in maintenance windowsNight-only database migrations
Regulatory / reporting cyclesExternal calendarsYear-end freeze on finance system changes
Hypercare capacityPost-go-live support loadingCannot launch three sites the same week
Parallel changeOther projects contending for the same BAUTwo programmes training the same call centre

Scenario B — BAU dependency ignored

A hospital IT project schedules user acceptance testing in the first week of a major winter pressures period. Clinical BAU cannot release staff; testing slips four weeks and the critical path moves. Integrated schedule management would have treated clinical availability as an external dependency with a named operational owner and alternative windows — not as an infinite resource pool.

How cost, quality, risk, and scope impact the schedule

The schedule is not independent. Syllabus LO20b expects you to explain links among these factors.

FactorHow it impacts scheduleReverse link (schedule → factor)
ScopeMore/less product or work changes activity count and path lengthCompressed dates force scope trade-offs or phased delivery
Cost / budgetFunding profile and cash constraints delay starts; cheap slow methods vs expensive fast methodsAcceleration usually increases cost (crashing, overtime, dual teams)
QualityReviews, testing, rework loops, certifications add duration and dependenciesRushed schedules raise defect risk and rework (quality cost later)
RiskRisk response activities, contingency time, and threat materialisation alter forecastsTight schedules increase risk exposure; float is a risk buffer when used deliberately
ResourcesAvailability and skill constrain parallel workSchedule density drives resource peaks and conflict with BAU
ProcurementLead times and award dates set early constraintsLate package definition pushes supply onto the critical path

Scenario C — quality and risk on the path

A medical device software release is scheduled for a fixed regulatory submission date. Scope growth adds features without extending test cycles. Quality risk rises: either defects escape or the submission slips. Integrated planning would re-estimate test effort, re-sequence or descope features, and escalate the scope–quality–schedule trade-off to the sponsor with options — not silently steal test float.

Scenario D — cost-driven delay

A capital project’s funding arrives in two financial years. Even if technical work could start now, the CBS/budget profile forbids major spend until April. The schedule must show constrained starts, not a fantasy early start that finance cannot fund.

Practical tips for PMQ long responses

When a scenario mentions late delivery or dependency failure:

  1. Clarify outputs vs outcomes vs benefits relevant to the scope.
  2. Use PBS / WBS / CBS language to show structure and missing work/cost.
  3. Identify dependency types (internal, external, BAU, resource).
  4. Discuss critical path conceptually: what is driving the end date?
  5. Explain impacts from scope, cost, quality, and risk both ways.
  6. Recommend integrated re-planning with named owners and governance.

That chain satisfies LO20a–b and sets up continuous re-estimating and schedule optimisation (LO20c) in the next section.

Test Your Knowledge

Why must project schedules consider business-as-usual (BAU) dependencies?

A
B
C
D
Test Your Knowledge

A project adds mandatory safety testing without changing the end date or removing other work. What is the most accurate integrated analysis?

A
B
C
D