20.3 Monitoring and Reporting Financial Performance

Key Takeaways

  • Financial reports are not interchangeable: budget versus actual answers what has been spent, while forecast reports answer whether the project will finish within the approved investment.
  • Commitment reports capture money legally committed but not yet invoiced, which is how apparently sudden overspends actually build up.
  • Reporting cadence must align with the organisation’s financial periods or project and finance figures will never reconcile.
  • Work done but not yet invoiced must be accrued; under-accrual is the most common cause of a project reporting on-budget one month and over the next.
  • A financial report should end in a decision: variance, cause, forecast, options, and the authority required.
Last updated: August 2026

Outcome 22c is separate from the forecasting outcome for a reason: know how to monitor and report financial performance, including different types of financial reports. The syllabus wants the reporting layer — what each report is for, who reads it, and what decision it supports.

Monitoring and types of financial reports

LO22c expects you to monitor and report financial performance using appropriate report types for different audiences.

Report typeTypical contentPrimary audienceUse
Budget vs actualBaseline budget, actuals to date, variance by CBS/WBSPM, PMO, finance partnerPackage-level cost control
Forecast / EAC reportEAC, ETC, VAC, assumptionsSponsor, boardOut-turn and funding decisions
Cash flow reportInflows/funding vs outflows by periodFinance, PMLiquidity; not the same as value performance
Commitments reportPurchase orders and contracts committed but not fully invoicedPM, commercialFuture spend already obligated
Accruals reportWork done not yet invoicedFinance, PMTrue cost of work in period
Earned value summaryPV, EV, AC, CV, SV, CPI, SPI, trendsSponsor, assuranceIntegrated cost–schedule health
Exception / variance narrativeRoot causes, impact, actions, decisions requiredSponsor, boardTurns numbers into governance choices
Funding / drawdown reportReleases vs remaining approved fundsSponsor, financeStage-gate and grant compliance

Good reporting principles:

  1. One data date and consistent coding.
  2. Separate baseline, actuals, commitments, and forecast.
  3. Explain why variances happened and what will change.
  4. Escalate when forecasts breach tolerance or financial authority.
  5. Match detail to audience: board wants exception and decision; package leads need line-item control.

Scenario C — wrong report for the question

A finance committee asks whether the project will finish within the approved investment. The PM only presents last month's invoices (cash). Better answer: EAC vs BAC, remaining commitments, risk contingency status, and change pipeline — a forecast and exception narrative, not a bank statement alone.

Cost control techniques in practice (beyond the formulas)

Earned value is a flagship technique; others support LO22b:

TechniqueWhat you do
Variance analysisCompare actual/EV to baseline; find root causes
Trend analysisWatch CPI/SPI over time — is recovery real?
Change control on costOnly authorised scope/cost enters the baseline
Commitment controlDo not approve POs that break remaining budget without authority
Re-estimating remaining workReplace outdated ETC with bottom-up knowledge
Value engineering / cost reductionReduce cost while preserving required function (not arbitrary quality cuts)
Supplier commercial controlApplications for payment, retention, pain/gain, audit of cost-plus

Choosing the right report for the question being asked

Financial reports are not interchangeable, and a very common exam scenario gives a decision maker the wrong one. Match the report to the question:

Question being askedReport that answers itReport that does not
"How much have we spent?"Budget versus actualForecast report alone
"Will we finish within the approved investment?"Forecast / estimate at completionLast month's invoices
"Do we have the cash when we need it?"Cash flow forecastCumulative spend total
"What have we already legally committed?"Commitment reportActuals report — commitments precede invoices
"Why are we over budget?"Variance / exception report with root causeA status colour
"Is delivery efficient relative to value earned?"Earned value summarySpend against profile

The commitment report is the one candidates most often omit, and it matters. A purchase order raised today is money the organisation has agreed to spend even though no invoice has arrived. A project reporting only actuals can look comfortably under budget while being fully committed — which is exactly how an overspend appears "suddenly".

Cadence, audience and accruals

Three practical disciplines make financial reporting trustworthy:

Cadence. Reporting must align with the organisation's financial periods, or project and finance figures will never reconcile and both will be disbelieved. Agree the data date and stick to it.

Audience. The board needs forecast out-turn, variance from the approved investment, and the decision required. The sponsor needs early warning of anything threatening the business case. The finance function needs accruals, commitments, and reconciliation to the ledger. The delivery team needs cost against the work packages it controls. Sending everyone the same pack means most of them are reading someone else's report.

Accruals. Work done but not yet invoiced must be accrued, or the reported position flatters the project. Under-accrual is the single most common reason a project reports on-budget one month and materially over the next.

Acting on the numbers

Reporting exists to trigger action, so a report should end with the decision it requires. In an answer, follow the same chain used for reviews: state the variance, explain the cause, give the forecast out-turn, present options with their benefit and risk consequences, and name the authority whose decision is needed. A financial report that describes a problem without proposing a response has stopped one step short of governance.

Test Your Knowledge

A project reports actual spend of £1.2m against a £2m budget and declares itself comfortably on track. Purchase orders totalling a further £750,000 have been raised but not yet invoiced. What is the most accurate assessment?

A
B
C
D
Test Your Knowledge

A finance committee asks whether a project will complete within its approved investment. The project manager presents last month’s invoice total. Why is this an inadequate answer?

A
B
C
D