22.3 Assessing Options and the Impact of a Change

Key Takeaways

  • A decision maker offered a single option is ratifying rather than deciding — assessments should present genuine alternatives.
  • Always include the do-nothing option, because the consequence of rejecting the change is part of the decision.
  • A typical option set is do nothing, implement in full, implement a reduced version, or defer with the interim risk stated.
  • Impact assessment must span scope, schedule, cost, quality, resources, risk, benefits, stakeholders, and contracts — not cost alone.
  • Assessment effort must be proportionate, and the cumulative effect of many small changes on float and contingency must be assessed alongside each individual request.
Last updated: August 2026

Outcome 24c requires you to know ways to assess options related to a proposed change and the high-level impact of the proposed change. Two things are being tested: generating genuine options rather than a single proposal, and assessing impact across every dimension rather than only cost.

Assessing options and high-level impact

Detailed evaluation turns a request into decision-ready evidence. Two complementary activities matter: impact assessment and options analysis.

Impact assessment dimensions

Assess the proposed change (and each serious option) across the integrated project:

DimensionQuestions to ask
Scope / requirementsWhat is added, removed, or altered? Which requirements or exclusions change?
Time / scheduleEffect on critical path, milestones, float, release dates?
Cost / budgetDirect cost, contingency draw, whole-life cost, contract variations?
QualityEffect on acceptance criteria, performance, rework, test burden?
RiskNew threats/opportunities, residual exposure, secondary risks from the change itself?
Benefits / business caseDoes value rise, fall, or shift timing? Still aligned to strategy?
ResourcesSkills, availability, overtime, supplier capacity?
StakeholdersWho gains/loses; communication and training needs; resistance?
Compliance / safety / sustainabilityLegal, regulatory, H&S, environmental obligations?
Configuration / interfacesWhich CIs, documents, interfaces, and data sets are affected?

High-level impact is not a 200-page report for every CR. It is proportionate: small changes get light assessment within PM authority; material changes get deeper multi-discipline analysis and higher approval.

Options analysis

Rarely is the only choice "do exactly what was asked" versus "do nothing." Useful options often include:

Option typeIntentExample
Approve as requestedFull acceptance of the proposalAdd the mandated regulatory field to the next release
Approve modified / partialCapture most value with less impactDeliver a simplified report now; full analytics later
Alternative solutionMeet the need differentlyProcess change or training instead of a system build
DeferDelay decision or delivery to a better windowPark until after a critical milestone or funding review
RejectDo not proceedRequest conflicts with strategy, exceeds value, or duplicates existing capability
Combine with other changesPackage for efficient implementationBundle related CRs into one release to cut retest cost

Compare options using impact, value, risk, urgency, and strategic fit — not the loudest stakeholder alone. Document trade-offs so the recommendation is transparent.

Scenario B — multi-dimensional impact

A change request could improve customer satisfaction dashboards but adds cost and delays a contractual milestone. Impact assessment must include scope (new reports and data feeds), time (milestone slip), cost (build and licence), quality (extra UAT), risk (penalty clauses, residual data-quality risk), benefits (satisfaction and retention), stakeholders (operations training), and configuration (report pack versions). Options might be: full approve with re-baseline; slim MVP now and phase 2 later; defer until the milestone is met; reject if benefits do not cover delay risk. Decision makers need that balanced picture — not only "the customer likes it."

Always include the do-nothing option

The most common assessment failure is presenting a single course of action and asking for approval. A decision maker offered one option is not deciding; they are ratifying. A defensible assessment offers a small set of genuine alternatives, always including do nothing — because the consequences of rejecting the change are part of the decision.

A workable option set for most change requests:

  1. Do nothing — reject the change and state the consequence: the risk that remains, the benefit forgone, or the obligation unmet.
  2. Implement in full — the requested change with its full cost, schedule, and risk impact.
  3. Implement a reduced version — the part of the change that captures most of the value for materially less impact.
  4. Defer — implement later, in a subsequent phase, release, or project, with the interim risk stated.

Assessing impact across every dimension

High-level impact assessment must cover more than cost. A change that looks cheap can be expensive once its resource and risk consequences are traced.

DimensionQuestion to answer
ScopeWhich requirements and configuration items change, and what is displaced?
ScheduleDoes it touch the critical path, consume float, or move a milestone?
CostCapital, operating, and whole-life cost — including the cost of the change process itself
QualityDoes it alter acceptance criteria, testing effort, or the standard achieved?
ResourcesAre the skills available when needed, and what is displaced to free them?
RiskWhat new risks are introduced, and which existing risks change?
BenefitsDoes the expected benefit rise, fall, or shift in time?
StakeholdersWho is affected, and whose expectations must be re-set?
ContractsDoes it require a variation, and what will the supplier charge for it?

Proportionate assessment

Assessment costs money, so the effort must match the change. That is exactly what the initial evaluation stage is for: it screens requests so that only those worth full analysis proceed to detailed evaluation. Running a full multi-dimensional impact assessment on a trivial change wastes the capacity needed for the significant ones — and slow change control is one of the main reasons teams start bypassing it.

The cumulative view matters too. Several individually small changes can together consume all the float or contingency, so assess the aggregate position, not just the request in front of you.

Test Your Knowledge

A change request could improve customer satisfaction but adds cost and delays a milestone. What should the impact assessment include?

A
B
C
D
Test Your Knowledge

A project has approved eleven individually minor changes this quarter, each assessed as having negligible schedule impact. The project has now lost all its float on the critical path. What assessment discipline was missing?

A
B
C
D