19.1 Determining Resource Requirements and Availability

Key Takeaways

  • Project resources include people, equipment, materials, facilities, funding, and information — not just staff.
  • Resource requirements are derived from the work breakdown structure and the estimates for each activity, so vague scope produces unusable resource plans.
  • Availability is about the right skill, competence, and certification at the right time — twenty generalists do not substitute for one certified specialist.
  • Confirmed availability differs from nominal availability: staff carrying business-as-usual duties are not fully available to the project.
  • Long-lead resources and scarce specialists must be identified early, because their availability constrains the schedule rather than following it.
Last updated: August 2026

Resource management on the APM PMQ

Resource management is how the project identifies, secures, assigns, and adjusts the people, equipment, materials, and facilities needed to deliver planned work. On the PMQ it is learning objective 21 — Resource management in Area D (Planning and managing deployment). This section covers determining resources required and their availability, the organisational breakdown structure (OBS), and how the OBS is used to create a responsibility assignment matrix (RACI).

Weak exam answers list job titles or say "hire more staff." Strong answers compare need versus availability, link roles to work packages through OBS and RACI, and show how unclear accountability creates delivery risk.

Exam frame: Resources make the schedule real. A network with perfect logic still fails if the people, plant, materials, or rooms do not exist when activities need them.

Resource types

Projects consume several categories of resource. PMQ answers should name the type relevant to the scenario and explain how each is planned.

Resource typeWhat it includesTypical planning concerns
People (human resources)Project team, specialists, BAU subject-matter experts, contractors, temporary labourSkills, competence, security clearance, availability calendars, cost rates, induction, fatigue
Equipment (plant and tools)Machinery, test rigs, vehicles, specialised instruments, IT hardwareCapacity, booking lead times, maintenance windows, mobilisation, utilisation
MaterialsConsumables, components, raw materials, free-issue client materialsLead times, storage, wastage, quality certification, single-source risk
FacilitiesOffices, labs, data centres, site compounds, training rooms, clean roomsBooking windows, access control, shared use with BAU, health and safety limits

Some organisations also treat budget/funding and information/data access as constrained resources. For LO21, prioritise the four physical and human categories above, then link money and data constraints when the scenario requires it.

People as more than headcount

People are not interchangeable units. Resource identification for people should capture:

  • Role and skill (for example senior electrical designer, not only "engineer")
  • Competence and certification (regulated work, software platforms, site induction)
  • Full-time equivalent (FTE) or days needed by period
  • Location and working pattern (remote, shift, part-time, secondment)
  • Reporting line and authority (project vs functional matrix)

A plan that needs "two analysts for six weeks" is incomplete if only one analyst has the system access and data-protection training the work requires.

Determining resources required (need)

Resource need is the demand implied by the scope, WBS, schedule, quality approach, and risk responses. It answers: What do we need, how much, with what skills or specifications, and when?

How need is derived

  1. Start from WBS work packages / activities and product acceptance criteria.
  2. Estimate effort (person-days) and duration using suitable techniques.
  3. Identify non-labour inputs (equipment hours, material quantities, facility bookings) per activity.
  4. Aggregate demand by period (week, sprint, month) to see peaks.
  5. Add resources for management, assurance, quality, transition, and contingency responses — not only "build" tasks.
  6. Note dependencies on BAU (operations staff for testing, training, cutover).
Planning inputResource implication
Scope / PBS productsWhat skills and materials create each product
Schedule logic and datesWhen demand occurs and whether work can run in parallel
Quality gates and testsSpecialists, labs, environments, rework capacity
Risk responsesExtra people, plant, or materials for mitigation/fallback
Procurement lead timesWhen materials and hired equipment must be ordered
Transition / trainingBAU time and training facilities near go-live

Example: A data migration work package may need a migration specialist (people), a staging environment (facilities/IT), extract scripts and licences (materials/tools), and overnight batch windows coordinated with operations — not only "developer days."

Determining availability (supply)

Availability is whether the required resource can be obtained for the periods needed. It answers: Who or what is free, bookable, or purchasable in time — and under what constraints?

Sources of availability information include functional managers, resource calendars, supplier capacity, hire fleets, warehouse stock, room booking systems, and framework agreements.

Availability factorWhy it matters
Calendar and holidaysNamed individuals are not 100% available every working day
Competing projects / BAUSame scarce experts appear on multiple plans
Skill matchHeadcount exists but not the right competence
Lead time to recruit or hireExternal fill may take weeks or months
Mobilisation and inductionEven assigned people are not productive on day one
Plant booking and maintenanceEquipment may be committed or offline
Storage and logisticsMaterials available at the supplier but not on site
Financial authorityBudget approved late means people cannot start

Need versus availability — the core comparison

SituationMeaningTypical response
Need ≤ availabilityDemand can be met as plannedAssign, book, confirm calendars
Need > availability (peak)Overallocation in a periodSmooth, level, re-sequence, buy capacity, or change scope/dates
Need with wrong skillQuantity OK, capability gapTrain, reassign, recruit, or outsource
Need with long leadFuture shortage already visibleEarly procurement, advance booking, dual source
Availability uncertainPromised resource not firmEscalate, get named commitment, plan contingency

Exam trap: Treating "the organisation has 200 staff" as availability for a specialist task. Availability is the right resource at the right time, not total headcount.

Scenario A — need without availability check

A project schedule shows three parallel user-acceptance test streams in the same week, each needing the same two clinical leads. Need is six clinical-lead-days in one week; availability is two people with heavy BAU loads (perhaps two days total). The plan is infeasible. The project manager must re-sequence tests, extend the window, add trained deputies, or reduce parallel scope — and update the integrated plan — not report "green" because the Gantt looks short.

Test Your Knowledge

A project plan needs a certified welding inspector for two weeks in month four. The organisation employs twenty project engineers, but none hold the welding-inspector certification, and the hire lead time is six weeks. Which statement best describes the situation?

A
B
C
D