5.1 Stringing, Material Identification & Handling
Key Takeaways
- Stringing distributes pipe along the right-of-way per the pipe tally and alignment sheet so the correct wall thickness, grade, and coating land at the right station
- Every joint is verified against its Mill Test Report (MTR)/Mill Test Certificate (MTC) for diameter, wall thickness, grade (SMYS), seam type, heat number, and coating
- Coated pipe must be handled with nylon slings or padded forks; bare chains, cables, or hooks directly on coated pipe are a violation
- Defects found in stringing (dents, gouges, arc burns, coating damage) are tagged HOLD and dispositioned in writing before the joint advances
5.1 Stringing, Material Identification & Handling
Quick Answer: Stringing is the controlled distribution of pipe along the right-of-way (ROW) per the pipe tally and alignment sheet so that the correct wall thickness, grade, and coating land at the right station. The inspector verifies each joint against its Mill Test Report (MTR)/Mill Test Certificate (MTC), checks for shipping and handling damage, confirms proper handling equipment (nylon slings, padded forks — never bare chains on coated pipe), and reports any discrepancy before the pipe is committed to the trench.
What "Stringing" Means on a Pipeline Spread
Stringing is the first construction activity in API 1169 Body of Knowledge Area 3 — Installation Construction, the largest BOK area (an unofficial practice-weighted estimate near 36%). After pipe is trucked from the mill or coating yard to the ROW, each joint is laid out along the surveyed centerline in the sequence the line will be built. The driver document is the pipe tally (also called the joint tally), cross-referenced to the alignment sheet. The alignment sheet tells the crew, station by station, what wall thickness, grade, and coating is required — for example, a heavier wall at a road crossing, a class-location change, or a directional-drill tie-in. If a joint lands at the wrong station, a pressure boundary can be built with the wrong material; the inspector's job is to prevent that.
Material Identification: Verifying the Joint Against the MTR/MTC
Every joint arrives with a Mill Test Report (MTR) or Mill Test Certificate (MTC). Before the joint is accepted into the string, the inspector confirms the markings on the pipe match the MTR and the alignment-sheet requirement for that station:
| Attribute | What to Verify | Why It Matters |
|---|---|---|
| Diameter | Outside diameter (OD) matches design | Mismatched OD prevents fit-up or changes hydraulics |
| Wall thickness (WT) | Nominal WT and tolerance per spec | Under-thickness at a crossing violates design stress |
| Grade (SMYS) | Specified Minimum Yield Strength (e.g., X52, X65) | Grade governs allowable hoop stress; a low-grade joint in a high-stress station is a defect |
| Seam type | ERW, SAW (longitudinal or spiral), or seamless | Seam type drives weld procedure and NDE acceptance |
| Heat number | Stenciled heat/lot number ties pipe to MTR | Provides traceability from finished weld back to the melt |
| Coating type/condition | FBE, 3LPE, coal tar, or bare; holiday-free | Wrong coating in the wrong soil corrosivity class causes external corrosion |
| Length & joint number | Joint ID stenciled on the bore matches tally | Closes the material-traceability loop |
If any attribute is missing, illegible, or inconsistent with the MTR, the joint is quarantined — set aside and tagged — until the discrepancy is resolved in writing.
Defect and Damage Inspection
Pipe can be damaged in transit, in handling, or while stacked on the ROW. The inspector walks each load and joint and looks for:
- Dents — any visible indentation; dents in the weld seam or exceeding code depth limits are rejectable.
- Gouges and grooves — metal removal that thins the wall or concentrates stress; grind out and verify remaining wall.
- Arc burns — stray electrical arc strikes (often from ground clamps) that create hard, crack-prone spots; must be ground smooth and inspected.
- Coating damage — holidays, disbondment, lapping wrinkles, or bare spots; repaired per the coating specification before lowering-in.
- Lamination indications — visible surface separations; hold for engineering review.
- End/bevel damage — deformed bevels prevent proper fit-up; re-bevel or cut back.
Handling Equipment and Stacking Rules
How pipe is moved and stored on the ROW is itself an inspectable item:
- Lift with nylon or web slings, padded forks, or cradles — never bare chains, cables, or hooks directly on coated pipe, which cut the coating and dent the steel.
- Dunnage between layers — timber dunnage of the right size, placed so weight is distributed and bevels are protected.
- Stack height limits — follow the project pipe-handling specification (commonly 3–4 layers for large-diameter pipe); excessive stacks deform the bottom joints and risk rolling.
- End protection — bevel protectors stay on until just before welding; the inspector checks they are present and undamaged.
- Weather protection — keep FBE-coated pipe out of prolonged sun where the spec requires tarping; keep bevels dry before welding.
- Support spacing — dunnage placed close enough to the ends to prevent sagging and to keep the pipe round.
Reporting Discrepancies
The inspector does not approve "use as is" for off-spec material. When a discrepancy is found:
- Tag the joint as "HOLD — discrepancy" and record the joint number, heat, station, and the nature of the issue.
- Notify the contractor and company representative in accordance with the project inspection plan.
- Document on the daily inspection report and, where the project uses one, a nonconformance report (NCR).
- Do not release the joint until the discrepancy is dispositioned in writing (use-as-is, rework, or reject).
Key Takeaways Recap
- Stringing places the right pipe at the right station per the pipe tally and alignment sheet.
- MTR/MTC verification closes the traceability loop from mill heat to finished weld.
- Chains on coated pipe are a classic handling violation; nylon slings and padded forks are required.
- Discrepancies are held, tagged, and dispositioned in writing — never silently accepted.
What is the primary reference the inspector uses to confirm that the correct wall thickness and grade of pipe are placed at a given station?
Which handling practice is a violation for coated pipe on the ROW?
What does the heat number stenciled on a pipe joint provide?
An inspector finds a joint with the correct diameter and wall thickness but an SMYS grade stamp that does not match the MTR. What is the correct action?