All Practice Exams

100+ Free TN Electrician Practice Questions

Pass your Tennessee Limited Licensed Electrician (LLE) Exam exam on the first try — instant access, no signup required.

✓ No registration✓ No credit card✓ No hidden fees✓ Start practicing immediately
Not published by the Tennessee Board for Licensing Contractors Pass Rate
100+ Questions
100% Free
Same family resources

Explore More Tennessee Limited Licensed Electrician

Continue into nearby exams from the same family. Each card keeps practice questions, study guides, flashcards, videos, and articles in one place.

More From This Family

Videos and articles for deeper review.

2026 Statistics

Key Facts: TN Electrician Exam

73%

Passing Score

TN Board for Licensing Contractors

40

Exam Questions

Prov

2 hrs

Time Limit

Prov

$53

Exam Fee

Prov

The Tennessee LLE exam has 40 multiple-choice questions, a 2-hour limit, and a 73% passing standard. The current provider is Prov, the exam fee is $53, and Prov permits unlimited retakes with no waiting period. No board preapproval or documented experience is required to sit the exam; license application is a separate step after passing.

Sample TN Electrician Practice Questions

Try these sample questions to test your TN Electrician exam readiness. Each question includes a detailed explanation. Start the interactive quiz above for the full 100+ question experience with AI tutoring.

1According to the NEC, what is the definition of a 'branch circuit'?
A.The circuit conductors between the service point and the main disconnecting means
B.The circuit conductors between the final overcurrent device protecting the circuit and the outlet(s)
C.Any circuit that supplies power to a motor
D.The conductors between the transformer and the first overcurrent device
Explanation: Per NEC Article 100, a branch circuit is defined as the circuit conductors between the final overcurrent device protecting the circuit and the outlet(s). This definition is fundamental to understanding how the NEC organizes and regulates different parts of an electrical system.
2According to the current Tennessee Limited Licensed Electrician (LLE) candidate bulletin, which NEC edition is an authorized exam reference?
A.NEC 2014
B.NEC 2017
C.NEC 2020
D.NEC 2023
Explanation: The current Prov Tennessee contractor candidate bulletin lists the 2017 NEC Handbook as an authorized reference for the LLE exam. This is an exam-reference fact; it should not be confused with a claim about the code edition adopted for every Tennessee jurisdiction.
3Under the 2017 NEC 210.8(A)(6), which dwelling-unit receptacles require GFCI protection?
A.All 125-volt receptacles in living rooms
B.All 125-volt receptacles in bedrooms
C.125-volt, single-phase, 15- and 20-ampere receptacles serving kitchen countertop surfaces
D.All 125-volt receptacles in closets
Explanation: Under the 2017 NEC 210.8(A)(6), GFCI protection is required for 125-volt, single-phase, 15- and 20-ampere receptacles serving dwelling-unit kitchen countertop surfaces. The broader voltage and location scopes in later NEC editions do not apply to this 2017-reference exam.
4What is the minimum size equipment grounding conductor required for a 60-ampere circuit per NEC Table 250.122?
A.14 AWG copper
B.12 AWG copper
C.10 AWG copper
D.8 AWG copper
Explanation: Per NEC Table 250.122, a 60-ampere overcurrent device requires a minimum 10 AWG copper equipment grounding conductor. This table is based on the rating of the overcurrent device protecting the circuit, not the conductor ampacity.
5According to NEC 250.66, what is the minimum size grounding electrode conductor for a 2/0 AWG copper service conductor?
A.8 AWG copper
B.6 AWG copper
C.4 AWG copper
D.2 AWG copper
Explanation: Per NEC Table 250.66, for service conductors sized 2/0 AWG copper (or 4/0 AWG aluminum), the minimum grounding electrode conductor is 4 AWG copper or 2 AWG aluminum. This table correlates the size of the largest service-entrance conductor with the required grounding electrode conductor.
6What is the standard voltage drop recommendation for branch circuits per NEC 210.19(A) Informational Note No. 4?
A.2%
B.3%
C.5%
D.8%
Explanation: NEC 210.19(A) Informational Note No. 4 recommends that voltage drop on branch circuits should not exceed 3%, and the total voltage drop for feeders and branch circuits combined should not exceed 5%. While these are recommendations rather than requirements, they represent good practice.
7Per 2017 NEC Table 310.15(B)(16), what is the ampacity of a 6 AWG THWN-2 copper conductor using the 75°C column?
A.40 amperes
B.55 amperes
C.65 amperes
D.75 amperes
Explanation: Per 2017 NEC Table 310.15(B)(16), 6 AWG copper has an ampacity of 65 amperes in the 75°C column. Although THWN-2 insulation is rated 90°C, the allowable ampacity at a termination cannot exceed the applicable terminal temperature limitation.
8According to NEC 314.16(B), what is the volume allowance for each 12 AWG conductor in a box fill calculation?
A.2.00 cubic inches
B.2.25 cubic inches
C.2.50 cubic inches
D.3.00 cubic inches
Explanation: Per NEC Table 314.16(B), each 12 AWG conductor requires a volume allowance of 2.25 cubic inches in a box fill calculation. This includes equipment grounding conductors counted as one conductor, device yokes counted as two conductors, and clamps counted as one conductor.
9Under 2017 NEC Table 430.52, what initial maximum percentage applies to a dual-element time-delay fuse for motor branch-circuit short-circuit and ground-fault protection?
A.125% of motor FLC
B.150% of motor FLC
C.175% of motor FLC
D.250% of motor FLC
Explanation: Under 2017 NEC Table 430.52, the initial maximum rating for a dual-element time-delay fuse is 175% of motor full-load current. Section 430.52(C)(1) contains rules for a standard size and a further increase when the motor cannot start, so 175% should not be described as an exception-free absolute maximum.
10What is the minimum height above grade for service drop conductors over a residential driveway?
A.10 feet
B.12 feet
C.15 feet
D.18 feet
Explanation: Under 2017 NEC 230.24(B)(2), service-drop conductors must have 12 feet of vertical clearance over residential property and driveways, and over commercial areas not subject to truck traffic, where the voltage limitations in that provision are met.

About the TN Electrician Exam

The Tennessee Limited Licensed Electrician (LLE) exam is administered by Prov for the Tennessee Board for Licensing Contractors. The open-book exam uses the references listed in the current Prov bulletin and covers ten domains spanning general knowledge, installation, services and circuits, overcurrent protection, grounding, conductors, raceways, hazardous locations, low-voltage systems, lighting, and general-use equipment. The LLE license applies to electrical work where the total project cost is less than $25,000; Tennessee states that it is not comparable to a journeyman or master license.

Questions

40 scored questions

Time Limit

2 hours

Passing Score

73%

Exam Fee

$53 (Tennessee Board for Licensing Contractors / Prov)

TN Electrician Exam Content Outline

4 questions (10%)

General Electrical Knowledge

General electrical principles and code knowledge listed in the current Prov content outline

3 questions (7.5%)

Installation Requirements

Requirements governing compliant electrical installations

7 questions (17.5%)

Services, Feeders, and Branch Circuits

Service, feeder, and branch-circuit requirements and calculations

2 questions (5%)

Overcurrent Protection

Overcurrent protective devices and their application

5 questions (12.5%)

Grounding and Bonding

Grounding electrode systems, equipment grounding, and bonding

4 questions (10%)

Conductors and Cables

Conductor ampacity, sizing, insulation, and cable requirements

5 questions (12.5%)

Raceways and Boxes

Raceway selection and fill, boxes, and related wiring methods

5 questions (12.5%)

Hazardous Locations

Equipment and installation rules for classified locations

2 questions (5%)

Low Voltage Alarms, Signaling Systems, and Communications

Low-voltage, alarm, signaling, and communications systems

3 questions (7.5%)

Lighting, Signs, and General-Use Equipment

Lighting, signs, and general-use electrical equipment

How to Pass the TN Electrician Exam

What You Need to Know

  • Passing score: 73%
  • Exam length: 40 questions
  • Time limit: 2 hours
  • Exam fee: $53

Keys to Passing

  • Complete 500+ practice questions
  • Score 80%+ consistently before scheduling
  • Focus on highest-weighted sections
  • Use our AI tutor for tough concepts

TN Electrician Study Tips from Top Performers

1Study the 2017 NEC reference set used by the current Prov LLE outline; later-edition article and table numbering can differ
2Give Grounding and Bonding 12.5% of blueprint-weighted review because the current outline assigns it 5 of 40 questions
3Practice dwelling unit load calculations using Article 220 of the 2017 NEC
4Focus on conductor ampacity from Table 310.15(B)(16) in the 2017 NEC and verify the edition before using later table numbering
5Study motor circuits (Article 430) and HVAC compressor requirements (Article 440)

Frequently Asked Questions

What is the Tennessee LLE license?

The Limited Licensed Electrician (LLE) license covers electrical work in Tennessee where the total project cost is less than $25,000. Tennessee expressly says it is not comparable to a journeyman or master license. The current exam is administered by Prov for the Tennessee Board for Licensing Contractors.

Which NEC edition is the current Tennessee LLE exam based on?

The current Prov bulletin bases the LLE exam on the 2017 National Electrical Code Handbook. That is an exam-reference fact, not a claim that every Tennessee jurisdiction has adopted the 2017 NEC as its current construction code.

How hard is the Tennessee LLE exam?

The Board does not publish a candidate pass rate. The current exam has 40 multiple-choice questions in 2 hours and requires 73% to pass. Efficient use of the permitted references and preparation across all ten official domains are important.

How much does the Tennessee LLE exam cost?

The current exam fee is $53 through Prov. No board preapproval is required to sit the exam; the LLE license application is a separate step after passing. Reference-book and licensing costs are separate.