Cheat sheet

North Carolina General Contractor Cheat Sheet

Business & Law

Not publishedof exam

Contract Law

Not publishedof exam

Safety & Codes

Not publishedof exam

Fall & Trench SafetyBuilding Code & PermitsOSHA SafetyPermits & Inspections

Project Management

Not publishedof exam

Estimating & SchedulingDelivery & RolesSupervisionQuality Control

Financial Management

Not publishedof exam

Quick Facts

Exam
NC General Contractor
Board
NCLBGC
Vendor
PSI Exams
Format
Open book (approved refs)
Business & Law
40 Q / 90 min
Trade Exam
90 Q / 200 min
Pass Score
70% each exam
License Threshold
$40,000+ per project
Classifications
5 license types
Building Code
2018 (until Jul 2026)

License Classifications

Building, Residential, Highway, Utilities, Specialty

B: broadest scopeR: homes onlyH: roads and bridgesPU: water and sewerS: single trade only

Limited vs Unlimited License

Limited

  • $750K project cap
  • $17K working capital
  • $175K bond alternative

Unlimited

  • No project cap
  • $150K working capital
  • $1M bond alternative

Cap grows with capital

License Class Picker

  1. Only build homesResidential Contractor(Homes only)
  2. Any building typeBuilding Contractor(Broadest scope)
  3. Roads or bridgesHighway Contractor(Highway scope)
  4. Water or sewer workPublic Utilities Contractor(5 subclasses)
  5. One specialty tradeSpecialty Contractor(Narrow scope)
  6. Project under $40,000No license needed(Below threshold)

License Classifications

Building
All building construction types
Residential
Homes and residential work
Highway
Roads, bridges, airport runways
Public Utilities
Water, sewer, power, gas
Specialty
Specialized trade-only work

License Limitations

Limited < Intermediate < Unlimited

Limited: $750K, $17K capitalIntermediate: $1.5M, $75K capitalUnlimited: no cap, $150K capital

Performance Bond vs Payment Bond

Performance Bond

  • Protects the owner
  • Guarantees job completion
  • Covers finishing costs

Payment Bond

  • Protects subs and suppliers
  • Guarantees they get paid
  • Covers unpaid invoices

Owner risk vs sub risk

License Limit Picker

  1. Project under $750KLimited license($17K working capital)
  2. Project under $1.5MIntermediate license($75K working capital)
  3. No project cap neededUnlimited license($150K working capital)
  4. Can't show net worthSurety bond(Meets capital alternative)

License Limitations

Limited
$750K project cap
Intermediate
$1.5M project cap
Unlimited
No project value cap
Limited Capital
$17K working capital
Limited Bond Alt
$175K surety bond

Lien & Payment Clock

7 days pay | 120 days lien | 180 days sue

7 days: pay sub after receipt120 days: file and serve lien180 days: deadline to enforce lien

Lien vs Bond Claim

Mechanics Lien

  • Attaches to real property
  • 120-day filing deadline
  • Private project remedy

Bond Claim

  • Claims against surety bond
  • Used on public projects
  • No property attachment

Property vs bond remedy

Bond Type Picker

  1. Owner wants completion guaranteedPerformance bond
  2. Subs want payment guaranteedPayment bond
  3. Local project over $300KBond required(Little Miller Act)
  4. State project over $500KBond required(State threshold)

Licensing Thresholds

Project Threshold
$40,000+ requires a license
Unlicensed Contracting
Class 1 misdemeanor
Qualifier
Exam-passer supervising the license
NASCLA Credit
Accepted for Building only

Building vs Residential Classification

Building

  • All building types
  • Broadest classification scope
  • Covers commercial work

Residential

  • Homes only
  • Narrower classification scope
  • No commercial work

Broad vs homes-only scope

Lien Timeline Picker

  1. Last furnished labor materialsStart 120-day clock(File and serve lien)
  2. First furnish on lien-agent jobNotice within 15 days(Protects lien rights)
  3. Lien filed and served180 days to enforce(File lawsuit)
  4. Payment received by primePay sub in 7 days(GS 22C-3)

Lien Law

Lien Deadline
120 days last furnishedGS 44A
Lien Enforcement
180 days to sue
Lien Agent Notice
15 days after first furnish
Claim of Lien
Filed with Clerk of Court

Bonds & Insurance

Performance Bond
Guarantees project completion
Payment Bond
Guarantees sub and supplier pay
Local Bond Trigger
$300K contract threshold
State Bond Trigger
$500K contract threshold
Workers Comp
Required by state law

Fees

Application
$75 to $125 tiered
Exam Fee
$100 per attempt
License Fee
$279 after passing
Renewal
$75 annually

Contract Pricing Types

Lump Sum | Cost-Plus | Unit Price | GMP

Lump sum: fixed total priceCost-plus: cost plus a feeUnit price: price per unitGMP: capped maximum price

Mediation vs Arbitration

Mediation

  • Non-binding
  • Neutral facilitator only
  • Parties keep control

Arbitration

  • Binding decision
  • Arbitrator decides outcome
  • Limited appeal rights

Suggests vs decides

Contract Types

Lump Sum
Fixed total price
Cost-Plus
Cost plus a fee
Unit Price
Price per measured unit
Time & Materials
Labor plus materials billed
GMP
Guaranteed maximum price cap

Subcontractor Payment

Payment Deadline
7 days after receiptGS 22C
Late Interest
1% per month
Pay-if-Paid
Unenforceable in NC
Retainage Cap
Matches owner's retainage rate

Change Orders & Disputes

Change Order
Written scope or price change
Claim
Formal dispute notice
Mediation
Non-binding, neutral facilitator
Arbitration
Binding, private decision-maker
Litigation
Court-based dispute resolution

OSHA Trigger Heights

Fall 6ft | Cave-in 5ft | Egress 4ft

6ft: fall protection required5ft: trench protective system4ft: trench safe egress needed

Fall Protection vs Trench Cave-In

Fall Protection

  • Triggers at 6 feet
  • Guardrails, nets, or PFAS
  • Open-sided or edge work

Cave-In Protection

  • Triggers at 5 feet
  • Sloping, shoring, or shielding
  • Trench and excavation work

Height differs by hazard type

Fall & Trench Safety

Fall Protection
Triggers at 6 feetOSHA
Excavation Edge
Barricade at 6 feet
Trench Cave-In
Protection at 5 feet
Trench Egress
Ladder needed at 4 feet
Open Excavation
Cover or barricade required

Building Code & Permits

NC Building Code
2018 edition current
2024 Code
Effective July 31 2026
Permit
Required before construction starts
Inspection
Required at code milestones
Sedimentation Control
Erosion plan required

Employee vs Subcontractor

Employee

  • W-2 wages
  • Employer withholds taxes
  • Employer controls the work

Subcontractor

  • 1099 payment
  • Self-pays taxes
  • Controls own methods

Control test decides status

Delivery Method Picker

  1. Want one point of contactDesign-Build(Single contract)
  2. Want separate design controlDesign-Bid-Build(Two contracts)
  3. Need price guarantee earlyCM at Risk(GMP contract)
  4. Small single-trade scopeDirect subcontract(No GC layer)

Estimating & Scheduling

Takeoff
Quantities from plans and specs
Bid
Price offer to owner
CPM Schedule
Critical path method
Gantt Chart
Bar chart timeline
Float
Schedule slack time

Design-Bid-Build vs Design-Build

Design-Bid-Build

  • Separate design and build
  • Two contracts, sequential phases
  • Owner holds both contracts

Design-Build

  • One firm, both roles
  • Single contract, overlapping phases
  • Faster overall delivery

Split vs single responsibility

Delivery & Roles

Design-Bid-Build
Separate, sequential contracts
Design-Build
One firm, both roles
CM at Risk
CM guarantees the price
Superintendent
On-site daily supervision
Subcontractor
Hired for specialty trade

Accrual vs Cash Accounting

Accrual

  • Records when earned or incurred
  • Matches income to expenses
  • Required for larger contractors

Cash

  • Records when cash moves
  • Simpler for small contractors
  • Common for very small firms

Timing of recognition differs

Business Finance

Accrual Accounting
Records when earned or incurred
Cash Accounting
Records when cash moves
Retainage
Withheld percent until completion
Overhead
Indirect business costs
Net Worth
Assets minus liabilities

Taxes & Payroll

Sales Tax
Charged on materials
1099
Independent contractor reporting
W-2
Employee wage reporting
Payroll Tax
Employer withholding requirement
Financial Statement
CPA-prepared for higher tiers

Common Traps

Limitation vs Classification

Limitation = dollar cap tier Classification = work type

NASCLA Covers Trade Exam Only

NASCLA replaces trade exam Business & Law still required

Cave-In vs Fall Protection

Cave-in triggers at 5ft Fall protection triggers at 6ft

Lien Deadline vs Enforcement

File lien within 120 days Enforce lien within 180 days

Performance vs Payment Bond

Performance protects the owner Payment protects subs, suppliers

Pay-if-Paid Clauses Unenforceable

NC bans pay-if-paid clauses Owner nonpayment isn't a defense

Public Bond Thresholds Differ

Local bond triggers at $300K State bond triggers at $500K

Accrual vs Cash Basis

Accrual records when earned Cash records when received

Last Minute

  1. 1.Classifications: Building, Residential, Highway, Utilities, Specialty
  2. 2.Limited license caps at $750K
  3. 3.Intermediate license caps at $1.5M
  4. 4.Unlimited license has no cap
  5. 5.$40,000+ project value needs license
  6. 6.NASCLA covers Building trade exam only
  7. 7.Business & Law exam still required
  8. 8.Both exams: 70% passing, open book
  9. 9.Lien deadline: 120 days last furnished
  10. 10.Lien enforcement: 180 days to sue
  11. 11.Pay subs within 7 days received
  12. 12.Pay-if-paid clauses are unenforceable in NC
  13. 13.Fall protection triggers at 6 feet
  14. 14.Trench cave-in protection starts at 5ft
  15. 15.2018 NC Building Code is current
  16. 16.2024 code takes effect Jul 31
  17. 17.Local public bonds trigger at $300K
  18. 18.State public bonds trigger at $500K
  19. 19.Employees get W-2s, subs get 1099s
Same family resources

Explore More General Contractor License

Continue into nearby exams from the same family. Each card keeps practice questions, study guides, flashcards, videos, and articles in one place.