Business & Law
Not publishedof exam
Contract Law
Not publishedof exam
Safety & Codes
Not publishedof exam
Project Management
Not publishedof exam
Financial Management
Not publishedof exam
Quick Facts
- Exam
- NC General Contractor
- Board
- NCLBGC
- Vendor
- PSI Exams
- Format
- Open book (approved refs)
- Business & Law
- 40 Q / 90 min
- Trade Exam
- 90 Q / 200 min
- Pass Score
- 70% each exam
- License Threshold
- $40,000+ per project
- Classifications
- 5 license types
- Building Code
- 2018 (until Jul 2026)
License Classifications
Building, Residential, Highway, Utilities, Specialty
Limited vs Unlimited License
Limited
- $750K project cap
- $17K working capital
- $175K bond alternative
Unlimited
- No project cap
- $150K working capital
- $1M bond alternative
Cap grows with capital
License Class Picker
- Only build homes→Residential Contractor(Homes only)
- Any building type→Building Contractor(Broadest scope)
- Roads or bridges→Highway Contractor(Highway scope)
- Water or sewer work→Public Utilities Contractor(5 subclasses)
- One specialty trade→Specialty Contractor(Narrow scope)
- Project under $40,000→No license needed(Below threshold)
License Classifications
- Building
- All building construction types
- Residential
- Homes and residential work
- Highway
- Roads, bridges, airport runways
- Public Utilities
- Water, sewer, power, gas
- Specialty
- Specialized trade-only work
License Limitations
Limited < Intermediate < Unlimited
Performance Bond vs Payment Bond
Performance Bond
- Protects the owner
- Guarantees job completion
- Covers finishing costs
Payment Bond
- Protects subs and suppliers
- Guarantees they get paid
- Covers unpaid invoices
Owner risk vs sub risk
License Limit Picker
- Project under $750K→Limited license($17K working capital)
- Project under $1.5M→Intermediate license($75K working capital)
- No project cap needed→Unlimited license($150K working capital)
- Can't show net worth→Surety bond(Meets capital alternative)
License Limitations
- Limited
- $750K project cap
- Intermediate
- $1.5M project cap
- Unlimited
- No project value cap
- Limited Capital
- $17K working capital
- Limited Bond Alt
- $175K surety bond
Lien & Payment Clock
7 days pay | 120 days lien | 180 days sue
Lien vs Bond Claim
Mechanics Lien
- Attaches to real property
- 120-day filing deadline
- Private project remedy
Bond Claim
- Claims against surety bond
- Used on public projects
- No property attachment
Property vs bond remedy
Bond Type Picker
- Owner wants completion guaranteed→Performance bond
- Subs want payment guaranteed→Payment bond
- Local project over $300K→Bond required(Little Miller Act)
- State project over $500K→Bond required(State threshold)
Licensing Thresholds
- Project Threshold
- $40,000+ requires a license
- Unlicensed Contracting
- Class 1 misdemeanor
- Qualifier
- Exam-passer supervising the license
- NASCLA Credit
- Accepted for Building only
Building vs Residential Classification
Building
- All building types
- Broadest classification scope
- Covers commercial work
Residential
- Homes only
- Narrower classification scope
- No commercial work
Broad vs homes-only scope
Lien Timeline Picker
- Last furnished labor materials→Start 120-day clock(File and serve lien)
- First furnish on lien-agent job→Notice within 15 days(Protects lien rights)
- Lien filed and served→180 days to enforce(File lawsuit)
- Payment received by prime→Pay sub in 7 days(GS 22C-3)
Lien Law
- Lien Deadline
- 120 days last furnishedGS 44A
- Lien Enforcement
- 180 days to sue
- Lien Agent Notice
- 15 days after first furnish
- Claim of Lien
- Filed with Clerk of Court
Bonds & Insurance
- Performance Bond
- Guarantees project completion
- Payment Bond
- Guarantees sub and supplier pay
- Local Bond Trigger
- $300K contract threshold
- State Bond Trigger
- $500K contract threshold
- Workers Comp
- Required by state law
Fees
- Application
- $75 to $125 tiered
- Exam Fee
- $100 per attempt
- License Fee
- $279 after passing
- Renewal
- $75 annually
Contract Pricing Types
Lump Sum | Cost-Plus | Unit Price | GMP
Mediation vs Arbitration
Mediation
- Non-binding
- Neutral facilitator only
- Parties keep control
Arbitration
- Binding decision
- Arbitrator decides outcome
- Limited appeal rights
Suggests vs decides
Contract Types
- Lump Sum
- Fixed total price
- Cost-Plus
- Cost plus a fee
- Unit Price
- Price per measured unit
- Time & Materials
- Labor plus materials billed
- GMP
- Guaranteed maximum price cap
Subcontractor Payment
- Payment Deadline
- 7 days after receiptGS 22C
- Late Interest
- 1% per month
- Pay-if-Paid
- Unenforceable in NC
- Retainage Cap
- Matches owner's retainage rate
Change Orders & Disputes
- Change Order
- Written scope or price change
- Claim
- Formal dispute notice
- Mediation
- Non-binding, neutral facilitator
- Arbitration
- Binding, private decision-maker
- Litigation
- Court-based dispute resolution
OSHA Trigger Heights
Fall 6ft | Cave-in 5ft | Egress 4ft
Fall Protection vs Trench Cave-In
Fall Protection
- Triggers at 6 feet
- Guardrails, nets, or PFAS
- Open-sided or edge work
Cave-In Protection
- Triggers at 5 feet
- Sloping, shoring, or shielding
- Trench and excavation work
Height differs by hazard type
Fall & Trench Safety
- Fall Protection
- Triggers at 6 feetOSHA
- Excavation Edge
- Barricade at 6 feet
- Trench Cave-In
- Protection at 5 feet
- Trench Egress
- Ladder needed at 4 feet
- Open Excavation
- Cover or barricade required
Building Code & Permits
- NC Building Code
- 2018 edition current
- 2024 Code
- Effective July 31 2026
- Permit
- Required before construction starts
- Inspection
- Required at code milestones
- Sedimentation Control
- Erosion plan required
Employee vs Subcontractor
Employee
- W-2 wages
- Employer withholds taxes
- Employer controls the work
Subcontractor
- 1099 payment
- Self-pays taxes
- Controls own methods
Control test decides status
Delivery Method Picker
- Want one point of contact→Design-Build(Single contract)
- Want separate design control→Design-Bid-Build(Two contracts)
- Need price guarantee early→CM at Risk(GMP contract)
- Small single-trade scope→Direct subcontract(No GC layer)
Estimating & Scheduling
- Takeoff
- Quantities from plans and specs
- Bid
- Price offer to owner
- CPM Schedule
- Critical path method
- Gantt Chart
- Bar chart timeline
- Float
- Schedule slack time
Design-Bid-Build vs Design-Build
Design-Bid-Build
- Separate design and build
- Two contracts, sequential phases
- Owner holds both contracts
Design-Build
- One firm, both roles
- Single contract, overlapping phases
- Faster overall delivery
Split vs single responsibility
Delivery & Roles
- Design-Bid-Build
- Separate, sequential contracts
- Design-Build
- One firm, both roles
- CM at Risk
- CM guarantees the price
- Superintendent
- On-site daily supervision
- Subcontractor
- Hired for specialty trade
Accrual vs Cash Accounting
Accrual
- Records when earned or incurred
- Matches income to expenses
- Required for larger contractors
Cash
- Records when cash moves
- Simpler for small contractors
- Common for very small firms
Timing of recognition differs
Business Finance
- Accrual Accounting
- Records when earned or incurred
- Cash Accounting
- Records when cash moves
- Retainage
- Withheld percent until completion
- Overhead
- Indirect business costs
- Net Worth
- Assets minus liabilities
Taxes & Payroll
- Sales Tax
- Charged on materials
- 1099
- Independent contractor reporting
- W-2
- Employee wage reporting
- Payroll Tax
- Employer withholding requirement
- Financial Statement
- CPA-prepared for higher tiers
Common Traps
Limitation vs Classification
Limitation = dollar cap tier ≠ Classification = work type
NASCLA Covers Trade Exam Only
NASCLA replaces trade exam ≠ Business & Law still required
Cave-In vs Fall Protection
Cave-in triggers at 5ft ≠ Fall protection triggers at 6ft
Lien Deadline vs Enforcement
File lien within 120 days ≠ Enforce lien within 180 days
Performance vs Payment Bond
Performance protects the owner ≠ Payment protects subs, suppliers
Pay-if-Paid Clauses Unenforceable
NC bans pay-if-paid clauses ≠ Owner nonpayment isn't a defense
Public Bond Thresholds Differ
Local bond triggers at $300K ≠ State bond triggers at $500K
Accrual vs Cash Basis
Accrual records when earned ≠ Cash records when received
Last Minute
- 1.Classifications: Building, Residential, Highway, Utilities, Specialty
- 2.Limited license caps at $750K
- 3.Intermediate license caps at $1.5M
- 4.Unlimited license has no cap
- 5.$40,000+ project value needs license
- 6.NASCLA covers Building trade exam only
- 7.Business & Law exam still required
- 8.Both exams: 70% passing, open book
- 9.Lien deadline: 120 days last furnished
- 10.Lien enforcement: 180 days to sue
- 11.Pay subs within 7 days received
- 12.Pay-if-paid clauses are unenforceable in NC
- 13.Fall protection triggers at 6 feet
- 14.Trench cave-in protection starts at 5ft
- 15.2018 NC Building Code is current
- 16.2024 code takes effect Jul 31
- 17.Local public bonds trigger at $300K
- 18.State public bonds trigger at $500K
- 19.Employees get W-2s, subs get 1099s
Explore More General Contractor License
Continue into nearby exams from the same family. Each card keeps practice questions, study guides, flashcards, videos, and articles in one place.
More From This Family
Videos and articles for deeper review.