Guiding Principles
28%of exam
Pre-Award
20%of exam
Award
26.67%of exam
Post-Award
25.33%of exam
Quick Facts
- Exam
- CON 3990V
- Credential
- Civilian FAC-C Professional
- Questions
- 150 multiple-choice
- Total time
- 3 hours including tutorial and review
- Passing score
- 70% minimum
- Format
- Proctored, closed book
- Delivery
- Pearson VUE center or OnVUE
- Authorization
- One attempt per 90-day authorization
- Retakes
- At least 30 days apart
- Experience
- 12 months full-time representative contracting experience
FAR Parts 1 Through 4
Authority, words, conduct, records
CO vs COR
CO
- Holds written appointment
- Binds within warrant limits
COR
- Has written designation
- Monitors delegated performance duties
Authority to bind vs monitor
42 Questions
- Skills and roles
- 6 questions
- Contract principles
- 18 questions
- Standards of conduct
- 6 questions
- Situational assessment
- 3 questions
- Team dynamics
- 3 questions
- Communication and documentation
- 6 questions
Civilian Exam and Certification
- Core exam training
- CON 1100V, 1200V, 1300V, 1400V
- Exam authorization
- Request through FAI CSOD
- Cancel or reschedule
- At least 48 hours before appointment
- After four unsuccessful attempts
- Review feedback and prep materialsCON 3910 and FCN 3920
- Additional attempt endorsement
- Career manager or small-agency representative
- Additional attempt first-attempt wait
- One year after first attempt
- Additional attempt last-attempt wait
- At least 30 days post-attempt
- Additional attempt request
- After endorsement, file WarU ticket
- CON 7300V for exam
- Optional before sitting
- CON 7300V for new certification
- Required since November 1, 2026
- Continuous learning
- 80 points per two-year common period
Solicitation Sections L and M
L tells how. M tells what counts.
Provision vs Clause
Provision
- Solicitation only
- Applies before award
Clause
- Contract term
- May appear in solicitation too
Time of application distinguishes them
Acquisition Method Picker
- Unclear commercial availability→Conduct market research(Identify capable sources)
- Applicable mandatory source available→Buy through required source(Follow Part 8 priority)
- Rule of two above MPT→Small business set-aside(Check Part 19 applicability)
- Purchase at or below MPT→Consider micro-purchase procedures(Use applicable threshold exceptions)
- Commercial products or services→RFO Part 12(Includes simplified procedures)
- Noncommercial, above MPT through SAT→RFO Part 13(Apply governing exceptions)
- Sealed bidding conditions met→Part 14 IFB(Price and price-related factors)
- Need competitive negotiated selection→Part 15 RFP(Publish evaluation factors)
- RFP requirements or terms change→Amend the RFP(Substantial changes may require resolicitation)
30 Questions
- Plan solicitation
- 12 questions
- Request offer
- 12 questions
- Plan sales
- 3 questions
- Prepare offer
- 3 questions
Acquisition Planning
- Market research
- Test availability and industry capabilityPart 10
- Acquisition planning
- Start when need is identifiedPart 7
- Mandatory supply priorities
- Inventory, excess, prison industries, AbilityOnePart 8 model
- Full and open competition
- All responsible sources may competePart 6
- Rule of two
- Expect two responsible small-business offersCompetitive price, quality, delivery
- General micro-purchase threshold (MPT)
- $15,000Exceptions apply
- General simplified acquisition threshold (SAT)
- $350,000Exceptions apply
- Commercial simplified ceiling
- $9 million generallyRFO Part 12
- Governmentwide point of entry
- SAM.gov contract opportunitiesPart 5
Solicitation and Offer
- Request for quotations (RFQ)
- Seeks supplier quotations
- Invitation for bids (IFB)
- Seeks sealed bids
- Request for proposals (RFP)
- Seeks proposals under announced factors
- Uniform contract format L
- Proposal preparation instructions
- Uniform contract format M
- Award evaluation factors
- Solicitation provision
- Applies before award
- Contract clause
- Applies after award, sometimes earlier
- Seller sales planning
- Assess opportunity before pursuing it
- Seller offer preparation
- Address requirements and evaluation factors
Three Pricing Questions
How much? Made of what? Likely cost?
Responsiveness vs Responsibility
Responsiveness
- Tests sealed bid
- Meets material solicitation terms
Responsibility
- Tests prospective contractor
- Can perform and has integrity
Bid conformity vs contractor capability
Pricing Method Picker
- Need overall price reasonableness→Price analysis(Compare offers or adjusted history)
- Certified cost or pricing data required→Cost analysis(Test separate elements and profit)
- Considering cost-reimbursement award→Cost realism analysis(Evaluate probable cost)
- Pricing action reaches applicable threshold→Screen for certification exceptions(Use RFO if applicable)
- Reviewing a proposed cost element→Check Part 31 allowability
- Negotiated price reached→Document negotiation and price basis
40 Questions
- Price or cost analysis
- 10 questions
- Plan negotiation
- 10 questions
- Select source
- 10 questions
- Manage disagreements
- 10 questions
Price vs Cost Analysis
Price analysis
- Looks at overall price
- Uses suitable price comparisons
Cost analysis
- Looks at discrete cost elements
- Evaluates proposed profit or fee
Whole price vs component costs
Source Selection Picker
- Minor proposal ambiguity→Consider clarification(Material proposal stays unchanged)
- Competitive negotiations needed→Establish competitive range(Then negotiate with remaining offerors)
- Offeror remains when negotiations end→Invite written proposal revision
- Extra technical merit has value→Consider tradeoff approach(Document value of higher price)
- Minimums clear, little value above→Consider LPTA approach(Confirm civilian LPTA restrictions)
Pricing and Negotiation
- Price analysis
- Evaluate overall proposed price
- Cost analysis
- Evaluate cost elements and profit
- Cost realism
- Test estimates against proposed performance
- Probable cost
- Realism-adjusted cost for reimbursement evaluation
- Historical price comparison
- Adjust for material differences
- Certified cost or pricing data
- $2.5 million general thresholdPrime award from 2018-07-01
- Older prime pricing data threshold
- $950,000 generallyPrime award before 2018-07-01
- Certified data exceptions
- Adequate competition, regulated prices, commercial, waiver
- Prenegotiation objectives
- Establish Government position before negotiation
- Price negotiation memorandum
- Records basis and negotiated outcome
- Allowable cost
- Reasonable, allocable, within governing rulesAccounting standards, contract, FAR limits
Clarifications vs Negotiations
Clarifications
- Resolve minor errors or ambiguities
- Proposal revision prohibited
Competitive negotiations
- Begin after competitive range established
- Remaining offerors may revise proposals
Negotiations can change material terms
Source Selection
- Responsibility
- Contractor capability, resources and integrity
- Bid responsiveness
- Bid meets material IFB terms
- LPTA
- Lowest price technically acceptable
- Tradeoff
- Weigh price against nonprice benefits
- Clarifications
- Explain proposal without permitting revision
- Competitive range
- Evaluated proposals suited for negotiation
- Competitive negotiations
- Address deficiencies and significant weaknesses
- Source selection decision
- Document evaluation and award rationale
- Debriefing
- Explain evaluation and award rationale
- Bid protest
- Challenges solicitation or award actionPart 33
LPTA vs Tradeoff
LPTA
- Technical acceptability is pass/fail
- Lowest evaluated price wins
Tradeoff
- Compare announced price and nonprice factors
- Document benefits justifying added cost
Acceptability vs comparative merit
Contract Type Risk
- Firm-fixed-price (FFP)
- Contractor bears cost overrun risk
- Fixed-price with economic price adjustment
- Adjusts for specified economic changes
- Cost reimbursement
- Pays allowable incurred costs
- Cost-plus-fixed-fee
- Negotiated fee generally stays fixed
- Time-and-materials
- Fixed hourly rates, materials costsCeiling and oversight
- Labor-hour
- Time-and-materials without contractor-supplied materials
- Indefinite quantity (IDIQ)
- Orders between stated minimum and maximum
Protest vs Claim
Bid protest
- Challenges procurement action
- Forum-specific rules apply
Contract claim
- Seeks relief under the contract
- CO decides unresolved claims
Procurement challenge vs contract relief
Closeout Cues
Confirm performance. Clear funds. Close file.
Inspection vs Acceptance
Inspection
- Test or examine performance
- Verify conformity to requirements
Acceptance
- Authorized Government act
- Approves services or assumes ownership
Check conformity vs formally accept
Post-Award Action Picker
- Delivered work needs conformity check→Inspect under contract terms
- Both parties agree to adjustment→Bilateral supplemental agreement
- Changes clause permits in-scope direction→CO issues change order
- Contract requires subcontract consent→Obtain CO consent
- Performance endangered before delivery→Check cure notice requirements
- Contract claim remains unresolved→CO issues written decision(Subject to statutory authority)
- Evidence of physical completion received→Start administrative closeout(Review funds and final records)
38 Questions
- Administer contract
- 10 questions
- Ensure quality
- 10 questions
- Manage subcontracts
- 4 questions
- Manage changes
- 10 questions
- Close out contract
- 4 questions
Unilateral vs Bilateral Modification
Unilateral
- CO signs alone
- Requires independent Government authority
Bilateral
- Both parties sign
- Records agreed changes or adjustment
CO signature vs both signatures
Administration and Quality
- Administration delegation
- Assign applicable post-award functionsPart 42
- Quality assurance surveillance plan
- Sets Government surveillance approachQASP
- Inspection
- Checks compliance with contract requirements
- Acceptance
- Authorized approval of delivered performance
- Nonconforming performance
- Normally reject or require correction
- CPARS
- Contractor Performance Assessment Reporting System
- Subcontract consent
- CO approval when contract requires
- Administrative closeout
- Starts after evidence of physical completion
- Funds review
- Identify excess funds for deobligation
Changes and Remedies
- Bilateral modification
- CO and contractor signatures
- Unilateral modification
- CO signature under applicable authority
- Change order
- Directs change within contract scope
- Equitable adjustment
- Adjusts affected price or schedule
- Contract claim
- Written demand asserting contractual entitlementPart 33
- Cure notice
- Allows time to remedy failure
- Show cause notice
- Requests explanation before possible default
- Termination for convenience
- Ends work in Government interest
- Termination for default
- May follow unexcused performance failure
- Commercial termination for cause
- Apply commercial contract terms
Common Traps
Authority and certification
Certification shows professional qualifications ≠ Warrant delegates contracting authority
Price analysis course
CON 7300V required for certification ≠ CON 7300V optional before exam
RFQ contract formation
Supplier quotation provides pricing ≠ Supplier acceptance binds purchase order
Certified data exceptions
Threshold triggers applicability check ≠ Applicable exception bars certification requirement
Scope and competition
In-scope change under contract authority ≠ Out-of-scope work requires new procurement analysis
Consent and cost
Subcontract consent approves placement ≠ Cost allowability follows separate rules
Termination bases
Convenience needs no contractor failure ≠ Default addresses unexcused failure
Last Minute
- 1.Closed book, 150 questions, 70% passes
- 2.Guiding Principles has 42 questions
- 3.Pre-Award has 30 questions
- 4.Award has 40 questions
- 5.Post-Award has 38 questions
- 6.Check applicable agency FAR deviation
- 7.CO binds within warrant limits
- 8.Clarification preserves material proposal terms
- 9.Price analysis evaluates total price
- 10.Cost realism estimates probable performance cost
- 11.Only contracting officers execute Government modifications
- 12.Verify physical completion before administrative closeout
- 13.Retakes require 30 days between attempts
- 14.CON 7300V required for new certification
Explore More Federal Acquisition Certifications
Continue into nearby exams from the same family. Each card keeps practice questions, study guides, flashcards, videos, and articles in one place.
More From This Family
Videos and articles for deeper review.