DAWIA Contracting Cheat Sheet

Guiding Principles

28%of exam

42 QuestionsRoles + AuthorityIntegrityFAR MapRFO Update

Pre-Award

20%of exam

30 QuestionsMarket ResearchRequired SourcesAcquisition StrategySolicitation

Award

26.7%of exam

40 QuestionsContract TypesPrice + CostSource SelectionNegotiation

Post-Award

25.3%of exam

38 QuestionsAdministrationQuality AssuranceChanges + ClaimsTermination + Closeout

Quick Facts

Exam
CON 3990V
Format
150 multiple-choice
Pass
70%
Time
3 hours
Book
Closed
DoD access
TAS authorization
Civilian access
FAI CSOD request
Delivery
Pearson VUE
Retake
At least 30 days
DoD attempts
3 per 12 months
Civilian attempts
4 before remediation
Distribution
42 / 30 / 40 / 38

Blueprint Counts

42 | 30 | 40 | 38

Guiding: 42Pre-Award: 30Award: 40Post-Award: 38

CO vs COR

CO

  • Holds warrant
  • Binds Government
  • Signs modifications

COR

  • Delegated technical duties
  • Monitors performance
  • Cannot change contract

Authority stays with CO

Current Exam Blueprint

Guiding Principles
42 questions28%
Pre-Award
30 questions20%
Award
40 questions26.7%
Post-Award
38 questions25.3%
Competency model
November 2024 model
Updated exam
Live March 31, 2026
Assessment
Initial readiness measure
Result
Pass or fail

Acquisition Lifecycle

Plan | Solicit | Award | Administer | Close

Plan: 7 and 10Solicit: 12, 13, 15Award: 15 and 16Administer: 42 and 46Close: 4 and 49

Roles + Authority

Contracting officer
Binds the GovernmentCO
Warrant
Defines CO authority
COR
Performs delegated surveillance
Program manager
Owns mission requirements
Legal counsel
Advises legal sufficiency
Finance
Confirms available funding
Small business
Supports participation strategy
Contract file
Documents business judgment

Binding Authority

CO binds only within delegated authority

COR monitorsPM defines needCO authority is limited

Candidate Pathways

Shared assessment
CON 3990V
DoD certification
Contracting Professional
Civilian certification
FAC-C Professional
DoD registration
Agency TAS authorization
Civilian registration
FAI CSOD authorization request
DoD attempts
Three per twelve months
Civilian attempts
Four before remediation
Retake wait
At least thirty days

Integrity + Judgment

Actual conflict
Conflict presently exists
Potential OCI
Organizational conflict may arise
Apparent conflict
Reasonable appearance exists
Procurement integrity
Protect source-selection information
Unauthorized commitment
Lacks binding authority
Ratification
Authorized official approves later
Gratuity
Avoid prohibited benefits
Impartiality
Disclose covered relationships

FAR Map: Foundations

Part 1
System and authority
Part 2
Definitions
Part 3
Improper practices and conflicts
Part 4
Administrative matters
Part 5
Publicizing actions
Part 6
Competition requirements
Part 7
Acquisition planning
Part 8
Required sources
Part 10
Market research
Part 12
Commercial acquisitions

FAR Map: Lifecycle

Part 13
Simplified noncommercial procedures
Part 15
Contracting by negotiation
Part 16
Contract types
Part 19
Small business programs
Part 31
Cost principles
Part 33
Protests and disputes
Part 42
Contract administration
Part 44
Subcontracting policies
Part 46
Quality assurance
Part 49
Termination

March 2026 RFO Update

RFO exam
Live March 31, 2026
Negotiations
Current material exchange term
Clarifications
No proposal revision
Legacy communications category
Removed under RFO
Proposal revision
Follows completed negotiations
Part 12
All commercial acquisitions
Part 13
Noncommercial above MPT through SAT
Evaluation
Use stated factors only
Class deviations
Use applicable deviation text

Supply Source Order

Inventory | Excess | FPI | AbilityOne

Inventory firstExcess secondFPI thirdAbilityOne fourth

Offer vs Quotation

Offer

  • Binding upon acceptance
  • Forms contract
  • Submitted to solicitation

Quotation

  • Not binding offer
  • Invites Government order
  • Supplier may accept order

Acceptance versus order

Acquisition Path Picker

  1. Required source existsApply FAR Part 8
  2. Market facts missingPerform market research
  3. Commercial solution fitsApply FAR Part 12
  4. Noncommercial over MPT through SATApply FAR Part 13
  5. Negotiated selection neededApply FAR Part 15
  6. Competition unavailableDocument Part 6 exception
  7. Small-business opportunityApply FAR Part 19
  8. Strategy settledDocument acquisition plan

Current Acquisition Thresholds

Micro-purchase
$15,000General
Simplified acquisition
$350,000General
Certified data
At least $2.5 million
Adequate price competition
Certified data exception
Commercial products or services
Generally certified-data exception
Law or regulation
Certified data exception
Approved waiver
Certified data exception
Subcontracting plan
Over $900,000Other-than-small prime
Construction plan
Over $2 millionPublic facility
Threshold effective
October 1, 2025

Planning + Strategy

Requirement
Defines mission need
Funding
Must be available and proper
Market research
Informs acquisition strategy
Acquisition plan
Integrates major decisions
Competition
Full and open default
Justification
Supports statutory exception
Set-aside
Reserves small-business competition
Presolicitation notice
Publicizes proposed action
Sources sought
Tests market capability
Evaluation factors
Match acquisition objectives

Required Source Order

Specific mandates
Check FAR 8.101 first
Agency inventory
First supply source1
Excess property
Second supply source2
FPI
Third supply source3
AbilityOne
Fourth supply source4
AbilityOne-listed service
Mandatory service source
Required-use contract
Must use when suitable
Existing governmentwide contract
Consider when suitable
Shared service
Consider when suitable
Commercial sources
Use after mandatory sources

Solicitation + Methods

Part 12
Commercial products and services
Part 13
Noncommercial above MPT through SAT
Part 15
Negotiated acquisitions
RFP
Requests contract offers
RFQ
Requests nonbinding quotations
Offer
Acceptance forms contract
Quotation
Not a binding offer
Amendment
Changes solicitation before award
Solicitation
Requests offers or quotations

Analysis Triad

Price total | Cost elements | Realism probable

Price: totalCost: elementsRealism: probable cost

Price vs Cost Analysis

Price

  • Total amount
  • No element breakdown
  • Competition often supports

Cost

  • Individual elements
  • Certified data often supports
  • Tests allocability and allowability

Total versus elements

Analysis Picker

  1. Adequate competitionPrice analysis
  2. Cost elements providedCost analysis
  3. Cost-reimbursement offerCost realism
  4. Data threshold metCertified data(Unless exception applies)
  5. Commercial product or serviceCheck certified-data exception
  6. Price seems excessiveReasonableness test
  7. Costs seem understatedRealism test
  8. Objectives establishedNegotiate and document

Contract Type Signals

FFP
Price stays fixed
FPEPA
Defined economic adjustment
FPI contract
Target sharing formulaFixed-price
CPFF
Allowable costs plus fixed fee
CPIF
Cost incentive sharing
CPAF
Subjective award fee
T&M
Labor rates plus materials
Labor-hour
Labor rates only
T&M limitation
No suitable alternative type
T&M ceiling
Contractor exceeds at own risk
IDIQ
Orders within contract scope
Risk rule
Contractor bears FFP cost risk

RFO Exchanges

Clarify without revision | Negotiate then permit revision

Clarify: explain without revisionNegotiate: address material issuesRevision opportunity follows negotiation

Reasonableness vs Realism

Reasonableness

  • Is price too high
  • Protects Government
  • Required award judgment

Realism

  • Are costs believable
  • Predicts probable cost
  • Required for cost-reimbursement

High versus believable

Contract Type Picker

  1. Stable requirementFFP
  2. Economic uncertaintyFPEPA
  3. Target sharing desiredFPI
  4. Uncertain allowable costsCPFF
  5. Cost incentive desiredCPIF
  6. Subjective incentive neededCPAF
  7. Labor extent unknownT&M(Only when no other type fits)
  8. Labor only neededLabor-hour(Only when no other type fits)
  9. Recurring uncertain quantityIDIQ

Pricing + Analysis

Price analysis
Evaluates total price
Cost analysis
Evaluates cost elements
Cost realism
Predicts probable performance cost
Reasonableness
Protects against overpricing
Unbalanced pricing
Overstated and understated line items
Certified data
Current accurate complete
Other data
Supports fair pricing
Technical analysis
Validates labor and quantities
Negotiation objective
Government's initial position
PNM
Records negotiated result

Clarification vs Negotiation

Clarification

  • Explains proposal aspects
  • No proposal revision
  • Cannot cure material defects

Negotiation

  • Material issues discussed
  • Revision opportunity follows
  • After competitive range

Revision separates negotiation

Source Selection

SSA
Makes selection decision
SSEB
Evaluates proposals
Stated factors
Control proposal evaluation
Tradeoff
Permits higher-priced selection
LPTA
Lowest acceptable evaluated price
Competitive range
Best suited for negotiation
Clarification
No proposal revision
Negotiation
Addresses material proposal issues
Proposal revision
Opportunity follows completed negotiations
Debriefing
Explains award decision
Responsibility
Contractor can perform
Best value
Optimizes stated factors

LPTA vs Tradeoff

LPTA

  • Acceptability only
  • Lowest evaluated price
  • No strength premiums

Tradeoff

  • Relative merits matter
  • Higher price permitted
  • Rationale required

Acceptability versus relative merit

FFP vs CPFF

FFP

  • Price fixed
  • Contractor cost risk
  • Stable requirement

CPFF

  • Allowable costs reimbursed
  • Fixed fee
  • Government cost risk

Risk follows uncertainty

Convenience vs Default

Convenience

  • Government choice
  • Fault not required
  • Settlement costs possible

Default

  • Unexcused contractor failure
  • Excess costs possible
  • Excusable causes matter

Need versus fault

Post-Award Action Picker

  1. Direction changes scopeStop and notify CO
  2. Within-scope changeContract modification
  3. Work fails requirementsInspection remedies
  4. Performance endangeredCure notice
  5. Default consideredShow-cause notice
  6. Government need endsTermination for convenience
  7. Unexcused contractor failureTermination for default
  8. Written demand assertedClaim process
  9. Performance completeContract closeout

Administration + Quality

COR delegation
Written limited authority
Surveillance
Monitors contractor performance
QASP
Defines surveillance approach
Inspection
Examines contract conformance
Acceptance
Acknowledges conforming delivery
Nonconformance
Apply contractual remedies
CPARS
Records contractor performance
Invoice review
Verifies payable performance
Government property
Track contractor accountability
Subcontract consent
CO approval when required
Privity
Government lacks subcontract privity

Protest vs Claim

Protest

  • Challenges acquisition action
  • Preaward or postaward
  • Forum deadlines control

Claim

  • Contract performance dispute
  • Demand asserted as right
  • CO decision required

Acquisition versus contract

Changes + Disagreements

Unilateral mod
One Government signature
Bilateral mod
Both parties sign
Change order
Directs within-scope change
Constructive change
Government conduct changes performance
REA
Requests equitable adjustment
Claim
Written demand asserted as right
CO final decision
Triggers appeal rights
Cure notice
At least ten days remain
Show-cause notice
Termination appears appropriate
Protest
Challenges acquisition action

Unilateral vs Bilateral Modification

Unilateral

  • One Government signature
  • Exercises existing authority
  • May direct change

Bilateral

  • Both parties sign
  • Reflects agreement
  • Often settles adjustment

Authority versus agreement

Termination + Closeout

Termination convenience
Contractor fault not required
Termination default
Unexcused contractor failure
Excusable delay
May prevent default liability
Excess costs
Possible default remedy
Settlement proposal
Proposes allowable termination costs
Termination notice
Stops authorized work
Final payment
Required before closeout
Release
Extinguishes covered claims
Property clearance
Resolves Government property
Commercial termination
Cause or convenience
Closeout
Confirms all obligations complete

Common Traps

Certification vs warrant

Certification shows competence Warrant grants authority

FAR vs DFARS

FAR is Government-wide DFARS supplements DoD

Quotation vs offer

Quotation is nonbinding Offer binds upon acceptance

COR authority

COR monitors delegated duties COR cannot change contract

Reasonableness vs realism

Reasonableness tests high price Realism tests believable costs

Justification vs research

Research informs strategy Justification supports competition exception

Clarification vs revision

Clarification explains without revision Revision opportunity follows negotiation

Convenience vs fault

Convenience needs no fault Default needs unexcused failure

Direction vs authority

Contractor request is not direction Only CO changes contract

FPI acronym

Source: Federal Prison Industries Type: fixed-price incentive

RFO terminology

Use negotiations now Legacy communications category removed

Last Minute

  1. 1.Counts: 42 / 30 / 40 / 38
  2. 2.150 questions; 70%; three hours
  3. 3.Closed book; internalize FAR map
  4. 4.March 2026 exam uses RFO
  5. 5.MPT $15K; SAT $350K
  6. 6.Certified data at least $2.5M
  7. 7.Part 12 means commercial
  8. 8.Part 13: noncommercial above MPT
  9. 9.Part 15 uses negotiations
  10. 10.Supply order ends at AbilityOne
  11. 11.CO binds; COR monitors
  12. 12.Price total; cost elements
  13. 13.Realism predicts probable cost
  14. 14.LPTA acceptability; tradeoff merits
  15. 15.Clarification allows no revision
  16. 16.Convenience choice; default fault
  17. 17.Retakes wait at least 30 days
  18. 18.DoD: three per 12 months
  19. 19.FAI: four before remediation
Same family resources