PracticeVideosBlogFlashcards

2.4 Permissible Pressure Drops, Calculations & Tracing Gas Leaks

Key Takeaways

  • Meter IVm values: U6/G4 diaphragm = 0.008 m³; E6 ultrasonic = 0.0024 m³; U16 = 0.025 m³ — never treat E6 as 0.008 m³.

  • NICEIC copper pipe volumes: 15 mm = 0.00014 m³/m; 22 mm = 0.00032 m³/m; 28 mm = 0.00054 m³/m; 35 mm = 0.00084 m³/m; fittings ≈ 10% of IVp.

  • IGEM/UP/1B Edition 4 Table 3 (natural gas) keys maximum permissible drop to Installation Volume: ≤0.005 → 8 mbar; >0.005–≤0.010 → 4 mbar; >0.010–≤0.015 → 2.5 mbar; >0.015–≤0.035 → 1 mbar.

  • Any perceptible movement with appliances connected that is within Table 3 still requires a pipework-only re-test with no perceptible movement; smell of gas is always a fail, and new work / pipework-only tests also require no perceptible movement.

  • Uncorrected leaks exceeding limits are managed under GIUSP (ID or AR) with isolation, warning notices, and labels.

Last updated: July 2026

2.4 Permissible Pressure Drops, Calculations & Tracing Gas Leaks

Once a 2-minute tightness test is completed under IGEM/UP/1B Edition 4, the gas operative must evaluate whether any recorded pressure movement is within acceptable safety thresholds. Determining whether a gas system passes or fails requires calculating the Installation Volume (IV), checking for the smell of gas, applying the Edition 4 perceptible-movement rules, and executing systematic diagnostic leak tracing if a leak is present.


Calculating Total Installation Volume (IV)

The Installation Volume (IVIV) represents the combined internal volume of the gas meter and all downstream pipework up to appliance controls (plus an allowance for fittings).

Total IV=IVm+IVp(+fittings allowance)\text{Total } IV = IV_m + IV_p (+ \text{fittings allowance})

Where:

  • IVmIV_m = meter badged volume (see table below — meter type matters).
  • IVpIV_p = ∑(Length of pipe in metres×Internal volume per metre)\sum (\text{Length of pipe in metres} \times \text{Internal volume per metre}).
  • Fittings: allow approximately 10% of IVpIV_p for elbows, tees, and couplings unless a more detailed volume schedule is used.

Meter Internal Volumes (IVmIV_m)

Meter TypeTechnologyBadged Volume (IVmIV_m)
U6 / G4Diaphragm0.008 m³ (8 litres)
E6Ultrasonic smart0.0024 m³ (2.4 litres)
U16Diaphragm (commercial)0.025 m³ (25 litres)

Do not group U6, G4, and E6 as all 0.008 m³. E6 ultrasonic meters are 0.0024 m³.

Internal Pipe Volumes per Metre (NICEIC copper values)

Copper Pipe Size (Outside Diameter)Internal Volume per Metre (vpv_p)
15 mm0.00014 m³/m (0.14 L/m)
22 mm0.00032 m³/m (0.32 L/m)
28 mm0.00054 m³/m (0.54 L/m)
35 mm0.00084 m³/m (0.84 L/m)

Worked Calculation Example

Problem: A property contains a U6 meter (IVm=0.008 m3IV_m = 0.008\text{ m}^3), 5 metres of 28 mm copper pipe, 12 metres of 22 mm copper pipe, and 8 metres of 15 mm copper pipe. Calculate the total Installation Volume (IVIV), including a 10% fittings allowance on pipe volume, and confirm it falls within the IGEM/UP/1B scope limit (IV≤0.035 m3IV \le 0.035\text{ m}^3).

Solution:

  1. IVm=0.008 m3IV_m = 0.008\text{ m}^3
  2. IV28=5 m×0.00054 m3/m=0.00270 m3IV_{28} = 5\text{ m} \times 0.00054\text{ m}^3/\text{m} = 0.00270\text{ m}^3
  3. IV22=12 m×0.00032 m3/m=0.00384 m3IV_{22} = 12\text{ m} \times 0.00032\text{ m}^3/\text{m} = 0.00384\text{ m}^3
  4. IV15=8 m×0.00014 m3/m=0.00112 m3IV_{15} = 8\text{ m} \times 0.00014\text{ m}^3/\text{m} = 0.00112\text{ m}^3
  5. Straight pipe IVp=0.00270+0.00384+0.00112=0.00766 m3IV_p = 0.00270 + 0.00384 + 0.00112 = 0.00766\text{ m}^3
  6. Fittings ≈ 10%×0.00766=0.000766 m310\% \times 0.00766 = 0.000766\text{ m}^3
  7. Total IV=0.008+0.00766+0.000766=0.01643 m3\text{Total } IV = 0.008 + 0.00766 + 0.000766 = \mathbf{0.01643\text{ m}^3}

Conclusion: Since 0.01643 m3≤0.035 m30.01643\text{ m}^3 \le 0.035\text{ m}^3, the installation is within IGEM/UP/1B scope. Looking ahead to Table 3, this IV sits in the > 0.015 – ≤ 0.035 band (maximum 1 mbar drop if movement is perceptible and there is no smell of gas).

E6 contrast: Replacing the U6 with an E6 (IVm=0.0024 m3IV_m = 0.0024\text{ m}^3) on the same pipework gives IV≈0.0024+0.00843=0.01083 m3IV \approx 0.0024 + 0.00843 = 0.01083\text{ m}^3 — a different Table 3 band (> 0.010 – ≤ 0.015 → 2.5 mbar). Meter volume errors therefore change the permitted drop.


IGEM/UP/1B Edition 4 Permissible Drops (Table 3 — Natural Gas)

Edition 4 keys maximum permissible pressure drop during the 2-minute test to Installation Volume, not to a simple pipe-diameter split.

Installation Volume IVIV (m³)Maximum Permissible Drop (mbar)
≤ 0.0058
> 0.005 – ≤ 0.0104
> 0.010 – ≤ 0.0152.5
> 0.015 – ≤ 0.0351

Edition 4 Pass/Fail Sequence (Apply in Order)

  1. No perceptible movement → PASS (gas tight). Perceptible movement ≈ 0.25 mbar on a water gauge; electronic gauges typically 0.25 mbar (0.2 mbar if one-decimal display).
  2. Any perceptible movement and no smell of gas → calculate IVIV; compare measured drop with Table 3.
  3. If within Table 3 limits with appliances connected → isolate all appliances and repeat a pipework-only test. Pipework-only must show no perceptible movement (any movement = fail).
  4. New install / pipework-only / only new appliances → no perceptible movement required (do not use Table 3 relaxations).
  5. Smell of gas → FAIL regardless of IV band or numerical drop.

Transition Note (Edition 3)

During the parallel-use period until 30 September 2026, Edition 3 historically presented meter/pipe tables that many operatives summarised as ≤ 28 mm → 4 mbar and > 28 mm → 2.5 mbar for existing installations with no smell of gas. From 1 October 2026, Edition 4 is mandatory: learn the IV Table 3 method above. Do not treat the old diameter-only matrix as the primary 2026+ exam rule.


Diagnostic Procedures for Leak Location

When a tightness test fails (pressure drop exceeds the Table 3 limit, pipework-only shows movement, or gas smell is detected), the engineer must locate and repair the escape using systematic tracing methods.

+-----------------------------------------------------------------------+
|                   LEAK TRACING & DIAGNOSTIC STEPS                     |
|                                                                       |
|  1. VISUAL INSPECTION: Check joints, meter unions, compression nuts.  |
|  2. APPLIANCE ISOLATION METHOD: Close individual AIVs / all AIVs and  |
|     re-test — Edition 4 pipework-only requires no perceptible move.   |
|  3. LEAK DETECTION FLUID (LDF): Spray BS EN 14291 compliant fluid     |
|     on joints; observe active micro-bubbling.                         |
|  4. ELECTRONIC SNIFFER: Sweep sensor tip at 25mm/sec above pipe run   |
|     (Natural Gas is lighter than air and rises).                      |
+-----------------------------------------------------------------------+

Soap Solution / Leak Detection Fluid (BS EN 14291)

  • Use only approved Leak Detection Fluid (LDF) complying with BS EN 14291.
  • DO NOT use domestic washing-up liquid, as it contains chlorides and high salt content that induce stress corrosion cracking on copper pipework and brass fittings.
  • Apply LDF onto compression joints, capillary solder elbows, threaded fittings, and test point nipples. Watch for growing foam bubbles indicating escaping gas.

Electronic Sniffers & Combustible Gas Detectors

  • Electronic gas detectors utilize semi-conductor sensors tuned to detect methane hydrocarbons in parts per million (ppm).
  • Buoyancy Rule: Natural Gas has a relative density of approximately 0.60 relative to air (1.01.0), making it lighter than air. Escaping gas rises upwards.
  • Sniffing Technique: Move the detector probe along the upper side of horizontal pipe runs and above fittings at a slow rate of 25 mm per second.

Appliance Isolation Method

  • Close all individual Appliance Isolation Valves (AIVs) for a pipework-only re-test.
  • Under Edition 4, pipework-only must show no perceptible movement. Continued movement means the leak is on the fixed installation pipework (or meter), not inside an appliance.

Unsafe Situations Procedure (GIUSP / IGEM/G/11)

If an uncorrected gas leak causes a tightness test failure and cannot be immediately rectified:

  • Immediately Dangerous (ID): An unisolated leak or open end passing gas. The operative must isolate the ECV, disconnect/cap the supply, attach an ID label, and issue a Gas Safety Warning Notice (CP14).
  • At Risk (AR): An installation fault where continued operation presents a safety hazard. Isolate with customer permission, attach an AR label, and issue a CP14 Warning Notice.
Test Your Knowledge

Under IGEM/UP/1B Edition 4 Table 3, what is the maximum permissible pressure drop over 2 minutes for an existing Natural Gas installation with Installation Volume IV in the band > 0.005 m³ to ≤ 0.010 m³ (for example a U6 meter with very little pipework), if NO smell of gas is present and movement is perceptible?

A

2.5 mbar

B

4.0 mbar

C

6.0 mbar

D

8.0 mbar

Test Your Knowledge

If a 2.0 mbar pressure drop is recorded during a 2-minute tightness test on an existing 22mm installation, BUT a distinct smell of gas is detected in the property, what is the pass/fail status of the test?

A

PASS, because the 2.0 mbar drop is below the 4.0 mbar threshold

B

PASS, provided windows are opened to ventilate the property

C

FAIL, because any pressure drop accompanied by a smell of gas is non-compliant and unsafe

D

PASS, subject to re-testing after 24 hours

Test Your Knowledge

In a domestic installation featuring a U6 meter (0.008 m³) and 20 metres of 22 mm copper pipe (NICEIC internal volume = 0.00032 m³/m), ignoring fittings, what is the total Installation Volume (IV)?

A

0.0064 m³

B

0.0080 m³

C

0.0104 m³

D

0.0144 m³

Sections you finish are checked off in the contents.