10.3 Assets under Construction (AuC) & Settlement
Key Takeaways
An asset under construction (AuC) holds capitalizable costs while construction is in progress. Ordinary depreciation normally starts on the completed asset when it is available for use.
A standalone AuC can be set up for line-item settlement or a summary transfer. A configured investment order or WBS element collects costs and uses its own settlement process.
For standalone line-item settlement, set up the AuC class and assign a settlement profile to the company code. The profile controls the permitted receivers.
Use AIAB to select source lines and maintain distribution rules. Use AIBU to test and post the settlement to the specified receivers.
Use the asset transaction and applicable period control to determine planned depreciation on the receiving asset. Check whether an incorrectly capitalized cost can be corrected through settlement to an allowed receiver.
Choose where to collect construction costs
An asset under construction (AuC) lets the company report qualifying construction costs before the completed asset is available for use. Use the applicable recognition policy to determine which costs should enter the AuC. For property, plant and equipment under IAS 16, costs directly attributable to bringing the asset to the necessary location and condition can be capitalized. Staff training is an expense. The completed asset starts depreciating when available for use under IAS 16. The system's depreciation calculation also depends on the asset value date and period-control settings.
| Design | Where costs go during construction | How capitalization works |
|---|---|---|
| Standalone AuC | Qualifying acquisitions or internal costs are posted to the AuC | Select and settle line items when configured, or transfer in summary |
| Investment measure | Costs initially collected on a configured internal order or work breakdown structure (WBS) element | Periodic settlement transfers qualifying costs to the linked AuC. Settlement of the investment measure moves completed amounts to final assets. |
In the standalone example, the buyer assigns a purchase order to the AuC and posts the receipt and invoice using the appropriate valuation and invoice flow. A direct invoice without a purchase order can be recorded through an integrated FI asset acquisition. In the investment measure example, the investment profile can create the linked AuC when the order or WBS element is released. Use the appropriate settlement process for the sender, such as KO88 for an internal order or CJ88 for a project. Noncapitalizable costs can be routed to permitted Controlling (CO) receivers according to settlement rules. The standalone asset transactions apply to a different sender and workflow.
Set up and use standalone line-item settlement
Set the status for line-item settlement on the standalone AuC asset class when you need to trace and distribute individual debits. Assign the relevant settlement profile to the company code so the system can validate the allowed receivers. For example, a profile can allow completed fixed assets and a cost center for supported corrections. If the company only needs a summary transfer, it can use an AuC without line-item management and transfer the values using the applicable AuC transfer process.
- In
AIAB, select the open lines to be settled and assign distribution rules. Lines with the same allocation can be grouped. For an amount-based distribution, select and distribute each line individually. Percentages work for splitting a line, and equivalence numbers specify relative proportions. - In
AIBU, enter the settlement dates and review the proposed receivers and amounts with a test run. Post when the results and periods are correct. The credit reduces the AuC and the debits go to the eligible receivers. - Check remaining open lines and receiving asset values. You can settle a completed portion and leave unfinished components in the AuC. The asset value date and the receiving asset's period control govern when planned depreciation reflects the capitalized amount.
Worked settlement of a packaging line
During one fiscal year, AuC 900010-0000 received USD 60,000 for a robot, USD 40,000 for a conveyor, and USD 10,000 of staff training mistakenly posted to the AuC. Both components are now available for use. The company has confirmed that the training line is a current-year item eligible for correction to cost center 1100 under the settlement profile. Assume the applicable expense account is configured.
| Source line | Rule in AIAB | Economic posting in AIBU |
|---|---|---|
| Robot, USD 60,000 | Allocate 100% to 300080-0000 | Debit robot APC USD 60,000 |
| Conveyor, USD 40,000 | Allocate 100% to 300085-0000 | Debit conveyor APC USD 40,000 |
| Staff training, USD 10,000 | Allocate 100% to the permitted cost center 1100 | Debit training expense USD 10,000 with the cost center |
Total debits of USD 110,000 offset the USD 110,000 AuC credit, leaving the selected items fully settled. The resulting capitalized total is USD 100,000. If the conveyor is still under construction, leave its line open and settle only the robot and the eligible correction. That leaves USD 40,000 in the AuC and USD 60,000 on the completed asset. A prior-year cost or a receiver not allowed in the profile requires a separate review of the applicable asset correction process. Preserve the original transaction and its audit trail.
A standalone asset under construction must support distribution of individual invoice lines to different completed assets. Which class setting provides this?
Statistical order management
Summary settlement
The AuC setting for line-item settlement
A straight-line depreciation key in the AuC class
An accountant is settling a completed portion of a standalone AuC set up for line-item settlement. Which sequence applies?
Run KO88 and immediately run AFAB
Run ABUMN and enter sale revenue in ABAON
Set recipients in AS02 and credit the AuC with an FB50 journal
Assign distribution rules in AIAB and post the settlement in AIBU
A standalone AuC has a current-year USD 15,000 maintenance line that was incorrectly capitalized. The company confirms it is eligible for settlement to cost center 1100, and the profile and account settings permit it. What should the accountant do?
Assign the line to the permitted cost center in AIAB and settle it with AIBU
Settle it to a completed asset and issue a supplier credit memo for the same amount
Defer the correction until after year-end to use prior-year settlement processing
Post USD 15,000 of unplanned depreciation on the AuC