2.2 Factors Affecting Reliability & the Spearman-Brown Formula

Key Takeaways

  • Spearman–Brown projects reliability for comparable length changes under a parallel-block model. Check precision on the actual form.

  • The Flanagan–Rulon split-half formula can allow unequal half-score variances. For a direct reliability interpretation, the half true scores differ by at most a constant and the errors are uncorrelated.

  • A group’s score spread and error variance can both change. Shared stopping points on a timed test can inflate odd–even associations.

  • The usual attenuation correction assumes cross-score true–error orthogonality and uncorrelated errors. Use the reliabilities for the observed scores and population.

Last updated: November 2026

Predict the effect of changing test length

The Spearman–Brown formula predicts reliability after changing test length by a factor mm. If reliability at the original length is rr, then

rm=mr1+(m−1)r.r_m=\frac{mr}{1+(m-1)r}.

For an integer number of parallel blocks, each block measures the same true score, the blocks have equal error variances, and their errors are mutually uncorrelated and uncorrelated with the common true score. An average of mm blocks preserves true-score variance and divides error variance by mm. Substitution in the CTT reliability ratio gives the formula. In practice use it as a projection for length changes that preserve the content, scoring, timing and population, especially when shortening or adding a fractional number of original-length blocks. Re-estimate precision with the resulting form. Similar item counts or average difficulty alone are insufficient.

  • Lengthening. A 20-item test has reliability .50. At 60 comparable items, m=3m=3 and rm=1.50/2=.75r_m=1.50/2=.75.
  • Shortening. A 100-item test has reliability .90. A representative 25-item version has m=.25m=.25 and projected rm=.225/.325≈.692r_m=.225/.325\approx .692. Retaining one quarter of the items changes error relative to true-score variance.

To plan for a target rtr_t, solve for the required factor: m=rt(1−r)/[r(1−rt)]m=r_t(1-r)/[r(1-r_t)]. A 40-item instrument at .75 needs a projected m=3m=3 to reach .90 under the model, or 120 items total. If the calculation produces a fractional item count, round the total up when the aim is to meet at least the target. The choice of target depends on how the scores will be used and how precision near a decision boundary is evaluated. Spearman · Standards for Educational and Psychological Testing, Ch. 2

Estimate reliability of a sum from two halves

When two parallel halves have uncorrelated errors, their Pearson correlation estimates a half's reliability. Use m=2m=2 to estimate reliability of the sum. If the halves have different error variances, the correlation cannot be interpreted as either half's reliability in this way.

If two half-scores are essentially tau-equivalent (their true scores differ at most by a constant), their observed variances may differ. Assume errors are uncorrelated across halves and with true scores. Let X1X_1 and X2X_2 be the half-scores, S=X1+X2S=X_1+X_2 their sum, and D=X1−X2D=X_1-X_2 their difference. The difference has constant true part, so Var(D)\mathrm{Var}(D) is the sum of both error variances. Under these conditions, the Flanagan–Rulon estimate of full-score reliability is

r^=1−Var(D)Var(S)=4 Cov(X1,X2)Var(S).\hat r=1-\frac{\mathrm{Var}(D)}{\mathrm{Var}(S)} =\frac{4\,\mathrm{Cov}(X_1,X_2)}{\mathrm{Var}(S)}.

Worked comparison. With half variances 9 and 16 and covariance 7, the sum variance is 9+16+2(7)=399+16+2(7)=39 and the difference variance is 9+16−2(7)=119+16-2(7)=11. Use 1−11/39=28/39≈.7181-11/39=28/39\approx .718 under the stated assumptions. Applying Spearman–Brown to 7/9(16)7/\sqrt{9(16)} instead would give about .737. Equal observed variances make the two calculations coincide, but equality of the calculations by itself does not show that either estimate is appropriate. If the halves measure different true-score components, their difference includes genuine variation across examinees. Examine the design and content before attributing the whole difference to error. Cronbach, 1951, split-half derivation · Novick and Lewis

Explain why precision differs across settings

FactorWhat to check
Examinee groupIf the observed-score variance falls from 25 to 9 while error variance stays at 4, reliability falls from .84 to about .556. If error variance changes as well, check both quantities.
Score compositionMore informative items can improve precision. Poorly scored items, redundant content, dependencies or changes in what is being measured can defeat a length-based projection.
Administration and scoringCheck differences in timing, instructions, scoring, interruptions and rater training. Choose a replication design that reflects variation relevant to the intended use.
TimingWhen unreached items all score zero, odd and even halves share the same stopping point. In a 100-item test, a person who answers the first 60 correctly scores 30 out of 50 on each half. That match alone cannot establish reproducibility on a fresh administration.

For a test with meaningful speed demands, consider separately timed, comparable forms or a retest to evaluate reproducibility under the intended conditions. If speed is incidental, examine whether the time limit introduces construct-irrelevant variation. A change that boosts internal consistency does not establish that score interpretation improved. Cronbach and Warrington · Standards, Chs. 1–2

Correct a correlation for attenuation

Let rXYr_{XY} be the observed correlation and rXXr_{XX} and rYYr_{YY} the reliabilities for those scores and their population. Assume each true score is uncorrelated with both errors and the two errors are uncorrelated with one another. Then the observed covariance equals the true-score covariance, but the observed standard deviations include error. The resulting correction estimates the correlation of the two CTT true scores.

Corr^(TX,TY)=rXYrXXrYY.\widehat{\mathrm{Corr}}(T_X,T_Y)=\frac{r_{XY}}{\sqrt{r_{XX}r_{YY}}}.

For rXY=.36r_{XY}=.36 and reliabilities .64 and .81, correcting for the first score only gives .36/.64=.45.36/\sqrt{.64}=.45. This estimates the association between the first true score and the second observed score. Correcting both gives .36/.72=.50.36/.72=.50. These are estimates. An estimate outside [−1,1][-1,1] signals that the observed correlation and reliabilities are incompatible as exact values under the model. Check sampling variability, input population and error assumptions. Correlated errors can inflate or deflate observed correlation, so a numerical adjustment alone is insufficient. Spearman, correction for attenuation

Test Your Knowledge

A 60-item instrument has reliability .60. A developer plans 150 comparable items for the same population under a Spearman–Brown length projection. What is the projected reliability?

A

.69

B

Approximately .79

C

.90

D

.96

Test Your Knowledge

Two essentially tau-equivalent half-scores have variances 14.5 and 28.2, and their covariance is 12. Their errors are uncorrelated with each other and with true scores. What is the Flanagan–Rulon estimate for the summed score?

A

Approximately .59

B

Approximately .28

C

Approximately .72

D

Approximately .89

Test Your Knowledge

In a speeded test, all unreached items score zero. Odd- and even-item scores are very highly correlated. The developer needs evidence of reproducibility on another administration. Which step best addresses that aim?

A

Keep the odd–even estimate and interpret it as agreement across occasions.

B

Treat unreached items as correct and recalculate alpha.

C

Infer that all score differences are due to the skill of interest.

D

Administer separately timed comparable forms and examine score reproducibility.

Test Your Knowledge

Two scores correlate .32. Their reliabilities are .64 and .25 in the same population. Both true scores are uncorrelated with both errors, and the errors are uncorrelated with one another. What is the estimated true-score correlation?

A

.80

B

.32

C

.40

D

Approximately .52

Sections you finish are checked off in the contents.