14.2 Checklists, Alarms & Time to Terminate

Key Takeaways

  • Location and setup checklists verify power, thrusters, PRS, sensors, mode, ASOG, and worksite readiness before critical DP work starts
  • Alarm prioritisation separates critical (immediate threat to position, power, or life) from advisory (degraded margin requiring attention)
  • Time to terminate (TTT) is the remaining time needed to safely stop the external activity and move the vessel to a safer condition
  • Blackout TTT thinking asks how long residual drift or recovery allows before the worksite becomes unsafe after power loss
  • Exam TTT items are conceptual — compare recovery duration to residual margin; they are not heavy formula papers
Last updated: July 2026

Checklists turn CAM/ASOG theory into a start gate

You can know Class 2 philosophy perfectly and still enter critical DP work with the wrong bus state, a thruster deselected, or a single PRS family online. Location and setup checklists exist to stop that. They are the operational bridge between planning (capability, ASOG, CAM/TAM) and the moment thrusters take the load near a hazard.

Induction and Simulator assessments reward candidates who treat checklists as verification, not as a tick-box race.

Location / setup checklists before DP

Exact company forms differ. Exam-stable families of checks before entering or continuing critical DP include:

Checklist familyTypical verification
Location / fieldCharted hazards, 500 m / safety zones, escape routes, concurrent vessel traffic, water depth for taut wire/acoustics
PowerGenerators online per mode; bus-tie open/closed as planned; PMS healthy; spinning reserve; blackout recovery readiness
ThrustersRequired thrusters available, deployed (if retractable), enabled for DP; no unexpected inhibits
PRSIndependent references selected; targets/responders confirmed; voting healthy; known blind sectors
SensorsGyros, MRUs, wind sensors available and consistent
DP controlCorrect mode path; setpoints; gains/footprint settings appropriate; consequence analysis reviewed
ASOG / documentationCorrect activity ASOG active; colour status green for entry; defects logged
WorksiteDive/crane/ROV ready; communications tested; SIMOPS agreed
PeopleCompetent DPO (and second person if required) on the desk; Master/ECR informed
Checklist mistakeWhat it causes
Skipping power/bus rows“CAM” label with closed bus and weak residual
Enabling only one PRS familyCommon-mode position error risk
Ignoring thruster out of serviceResidual after WCF weaker than plots
Using yesterday’s standby ASOGWrong abort criteria for today’s dive
No escape route briefPanic heading into the hazard when aborting

[!IMPORTANT] A completed checklist is a snapshot. If the plant changes after the tick, re-verify. Checklists do not freeze the universe green forever.

Alarm prioritisation: critical vs advisory

DP bridges can generate many alarms. Safe operators prioritise:

Priority bandMeaningTypical DPO response
CriticalImmediate threat to position-keeping, power integrity, thruster control, or people/worksite safetyStop non-essential tasks; stabilise position/plant; follow emergency/ASOG red path; communicate worksite stop if required
Advisory / cautionDegraded margin, early warning, single-channel fault with residual still OKInvestigate root cause; notify as ASOG yellow requires; restore redundancy; prepare contingency
InformationalStatus change, completed sequence, low operational impactNote/log; do not let it mask higher alarms

Examples of critical-leaning alarms (context-dependent, but exam-recognisable):

  • loss of multiple PRS / voting collapse toward single-reference control,
  • thruster emergency stop or unexpected full thrust (drive-off suspicion),
  • bus section blackout / generator cascade under critical load,
  • DP process station failure without healthy changeover,
  • consequence analysis residual inadequate during critical work,
  • position excursion beyond agreed limits near a structure.

Examples of advisory-leaning alarms:

  • one of three gyros disagreed and rejected,
  • single generator high temperature with reserve still online,
  • one laser target quality drop while two other PRS families remain healthy,
  • weather approaching but still inside yellow band with actions defined.

Rules of prioritisation under stress:

  1. Position and power first — is the vessel about to move dangerously, or is residual power collapsing?
  2. Do not bury critical alarms under silent-acknowledge spam.
  3. One root cause may spawn many secondary alarms — find the initiating failure.
  4. Link alarms to ASOG rows — many “yellow/red” decisions are alarm-driven.
  5. Never disable critical alarms to keep the screen quiet during client visits.
Bad habitBetter habit
Acknowledge all without readingRead, rank, act on highest risk first
Chase a minor sensor while thruster force is wrongFix drive-off / force anomaly first
Assume green position means ignore power alarmsPower residual is part of position safety
Hide recurring advisoryTreat recurrence as degradation trend

Time to terminate (TTT) — the core idea

Time to terminate (TTT) is the time required to safely conclude the external critical activity and place people, equipment, and the vessel in a safer condition. It is not merely “how long until we hit the platform if we drift now,” though drift/drive timing informs how much TTT margin you still have.

Think of TTT as a clock that starts when you decide to stop (or when conditions force a stop):

TTT componentExamples
Worksite recoveryRecover divers, land a load, disconnect hose, clear ROV from structure
Communication & decisionNotify dive control / crane / Master; get confirmation
Vessel manoeuvre to safe conditionMove clear of 500 m zone, open sea room, change heading to escape route
StabilisationRe-establish comfortable footprint away from hazard

If divers need 35 minutes to recover safely, you cannot wait until weather or residual capability is already beyond limits and then start recovery. You must start termination early enough that recovery finishes while residual safety still exists.

ConceptQuestion it answers
ASOG limitWhen is status no longer acceptable for the activity?
TTTHow long does a controlled stop take once we decide?
MarginHow long before we hit the ASOG red / residual cliff?
DecisionStart terminate when margin ≤ TTT (plus safety buffer)

Exam language: “Weather is rising; recovery takes 40 minutes; limits will be exceeded in 25 minutes if the trend continues — when do you start recovery?” Correct conceptual answer: now / immediately, not after the limit is crossed.

Drift-off, drive-off, and blackout TTT thinking

TTT interacts with failure scenarios you studied under drive-off / drift-off and blackout recovery:

ScenarioPosition behaviourTTT relevance
Drift-offLoss of thrust/power → environmental forces move vesselEstimate whether remaining sea room / time allows safe worksite recovery before contact
Drive-offUncommanded thruster force moves vesselMay force immediate emergency stop of thrusters/mode change — TTT for people may be shortened by emergency protocols
BlackoutPower loss; thrusters stop until recoveryBlackout TTT thinking: how long can the activity remain safe while black, and how long until power/thrusters restore versus when people must already be clear

Blackout TTT is conceptual on the exam:

  • If blackout recovery typically needs several minutes and divers need much longer underwater recovery, diving is planned on residual capability and early abort, not on hoping blackout never happens mid-dive without margin.
  • If the vessel is already at ASOG red plant status, do not start a long recovery activity that assumes perfect power.
  • After blackout, priorities are safety of people, blackout recovery procedure, and avoiding structure — not finishing commercial task steps.

You are not expected to integrate differential equations of drift. You are expected to reason:

  1. How long does safe termination take?
  2. How fast are conditions or failures eating the remaining margin?
  3. Is residual capability after WCF still enough for that duration?
  4. If not → terminate earlier or do not start the critical phase.

Worked conceptual TTT examples

Example 1 — Rising weather. Wind still green but trend will reach abort limit in ~20 minutes. Divers need ~30 minutes to recover. Start controlled recovery now (or sooner). Waiting for the red weather number guarantees recovery finishes outside safe limits.

Example 2 — Advisory generator loss. Spinning reserve enters ASOG yellow. ROV can be recovered in 8 minutes; structure is 80 m away in light current. Notify worksite, start standby gen, consider early ROV recovery if residual after next failure would be inadequate — do not ignore yellow because position still looks pretty.

Example 3 — Blackout during close approach. Blackout occurs inside the 500 m zone. Immediate actions follow blackout/emergency procedures; worksite stops external critical tasks as planned. TTT for “finish the survey line” is zero — commercial completion is abandoned.

Example 4 — Checklist prevents TTT crisis. Pre-entry checklist catches taut wire not deployed and only GNSS online. Approach delayed. Better to spend ten minutes on the checklist than invent a TTT plan after common-mode GNSS failure mid-approach.

Linking checklists, alarms, and TTT in one loop

Pre-job: location/setup checklist → CAM/TAM true → ASOG active
    │
Watch: prioritise alarms → map to ASOG colour → reassess residual
    │
If margin shrinking: compare remaining safe time vs TTT
    │
    ├─ Margin > TTT + buffer → notify, restore, continue if ASOG allows
    └─ Margin ≤ TTT + buffer → start terminate / abort path now

Exam traps for checklists, alarms, and TTT

TrapCorrect framing
Checklists are optional if experiencedChecklists are required verification, not ego tests
All alarms are equalPrioritise critical threats to position/power/life
TTT starts when you hit the structureTTT is the controlled stop duration you must finish before limits are gone
TTT is only a complex formula examNI-style items are conceptual margin vs recovery time
Blackout TTT means keep diving until UPS diesBlackout forces emergency priorities, not task completion
Green position cancels yellow power alarmsPower residual is part of future position safety

Operator habits

  1. Run the right checklist for this location and activity — not last voyage’s standby list.
  2. Rank alarms: position/power/critical first.
  3. Know the worksite’s realistic TTT before the critical phase starts.
  4. Start termination when remaining margin ≤ TTT plus buffer, not after red is already true.
  5. After any critical alarm or blackout, drop commercial goals and run emergency/ASOG logic.

Bottom line: Setup checklists prove the plant and references match the job before DP critical work. Alarms must be prioritised — critical threats first, advisories managed, never silenced for convenience. Time to terminate is how long a safe stop takes; compare it to remaining weather/plant margin, including blackout/drift thinking, using conceptual judgment rather than heavy maths.

Test Your Knowledge

What is the main purpose of location and setup checklists before critical DP work?

A
B
C
D
Test Your Knowledge

How should a DPO prioritise a cascade of DP alarms during critical work?

A
B
C
D
Test Your Knowledge

Time to terminate (TTT) is best defined as:

A
B
C
D
Test Your Knowledge

Divers need about 30 minutes to recover safely. Weather trend analysis shows ASOG abort limits will be reached in about 15 minutes if the rise continues. What is the correct conceptual decision?

A
B
C
D