4.1 ANSI Device Numbers (27, 50, 51, 59, 86, 87)

Key Takeaways

  • ANSI/IEEE C37.2-2022 assigns each protective function a number; 27 = undervoltage, 50 = instantaneous overcurrent, 51 = AC time overcurrent, 59 = overvoltage, 86 = lockout, 87 = differential.
  • 50 trips with no intentional time delay once current exceeds pickup; 51 trips on an inverse-time characteristic, so the same overcurrent device can do both jobs in a 50/51 unit.
  • Suffixes refine the function: N = neutral (50N/51N measured by residual or neutral CT), G = ground (51G on a separate ground CT), P = phase; 87T, 87G, 87B split differential into transformer, generator, and bus zones.
  • Pickup testing differs by device: a 50 element is checked at one current point (operate / no-operate), while a 51 element must be swept at several multiples of pickup to confirm the time curve.
  • 86 is a lockout (master trip) relay — once it operates it stays operated and blocks reclose until an operator manually or electrically resets it.
Last updated: August 2026

Why Device Numbers Matter on a NETA Job

Quick Answer: Every relay, lockout, and meter on a one-line is labeled with an ANSI/IEEE C37.2 number. Knowing the number tells you what the device does, what test to perform, and what the trip target is before you ever touch the test set.

ANSI/IEEE C37.2-2022 (the active standard; no 2026 revision exists) assigns 95 function numbers plus 22 acronyms. A NETA Level 2 technician meets the same handful on almost every acceptance and maintenance job, so memorize the core set first.

The Core Device Numbers You Must Know

NumberFunctionWhere a Level 2 tech encounters it
27Undervoltage relayUndervoltage load shed, motor bus transfer, generator protection
50Instantaneous overcurrent relayFeeder and motor short-circuit protection; the fast element of a 50/51
51AC time overcurrent relayFeeder/motor overload and backup short-circuit protection; inverse-time curve
59Overvoltage relayBus overvoltage, capacitor can protection, generator V/Hz backup
67Directional overcurrent relayNetworked feeders, tie breakers, generator motoring protection
79Reclosing relayDistribution feeder autoreclose (4-shot cycles common)
86Lockout relayMaster lockout after a fault; blocks reclose until reset
87Differential relayTransformer (87T), generator (87G), bus (87B), motor (87M) zone protection

Suffix Letters That Change the Meaning

A bare number tells you the function; the suffix tells you the application.

  • N — Neutral. 50N and 51N operate on residual or neutral current (3I0). They are sensitive to ground faults a phase element may miss.
  • G — Ground. 51G uses a dedicated ground CT (often a window/zero-sequence CT) rather than the residual connection. The distinction matters during a 50G/51G commissioning test because the shield and ground conductors must be routed back through the window or the scheme will misoperate on through-current.
  • P — Phase. 50P/51P are the phase overcurrent elements; modern numeric relays label each phase explicitly (50P-A, 50P-B, 50P-C).
  • T / G / B / M on 87. 87T = transformer differential, 87G = generator differential, 87B = bus differential, 87M = motor differential. Each zone has its own restraint characteristic and CT requirement.
  • S — Stalled / start. 66/48S-style suffixes appear on motor relays; 46 is phase-balance (negative-sequence) protection.

Why 50 Versus 51 Matters for Pickup Testing

A 50 element is an instantaneous trip. Once current crosses the pickup setting, the relay issues a trip in roughly 1.5 to 4 cycles — there is no intentional delay. Field pickup testing is therefore a single-point operate/no-operate check: inject 0.9 x pickup and confirm no trip, inject 1.1 x pickup and confirm a fast trip, and read the actual drop-out.

A 51 element is time-overcurrent. It follows an inverse-time curve (see Section 4.2), so pickup is verified at several multiples of setting current — typically 2x, 3x, 5x, and 10x — and the measured operate times are compared to the manufacturer curve and the coordination study. A common Level 2 mistake is to test a 51 at one current only; you have missed whether the time dial is correct.

A combined 50/51 relay houses both elements. The instantaneous element is usually set above the maximum through-fault (so it never operates for an external fault), while the time element covers overload and downstream backup. When you inject a current above the 50 pickup, expect an instantaneous trip; below the 50 pickup but above the 51 pickup, expect a timed trip. Reading the wrong target is a frequent cause of misdiagnosed relay tests.

86 Lockout — the Master Trip Relay

The 86 relay is not a protective relay in the sensing sense; it is a lockout/master trip auxiliary. When any protective element (50, 51, 87, etc.) operates, it energizes the 86 coil, which then seals itself in through a contact and trips all required breakers. Because it locks in, the breaker cannot be reclosed until an operator pushes the reset button (or sends a remote reset command). The 86 is why a faulted transformer stays isolated after a trip — without it, autoreclose schemes (79) could re-energize damaged equipment.

Worked Scenario: 50/51 on a 480 V Feeder

A 480 V feeder carries 600 A load and is protected by a 50/51 relay with a 1200:5 CT. Settings: 51 pickup = 1.25 x FLA (750 A primary, 3.125 A secondary), 51 time dial = 0.3 (standard inverse), 50 pickup = 9000 A primary (37.5 A secondary, set above the 7500 A maximum through-fault). During a close-in bolted fault at 25,000 A:

  • The 50 element operates first, tripping the feeder in ~2.5 cycles.
  • The 51 element also starts timing but the breaker is already open, so its target may not pick up.
  • The 86 lockout seals in and blocks autoreclose.

If you mis-set the 50 pickup to 6000 A (below the 7500 A through-fault), the relay will trip for a downstream fault — a coordination failure your injection test will catch if you sweep both elements.

Test Your Knowledge

On a feeder relay labeled 50/51N, the 51N element operates on:

A
B
C
D
Test Your Knowledge

During pickup testing of a 51 time-overcurrent element, the correct procedure is to:

A
B
C
D
Test Your Knowledge

After a transformer differential (87T) operation, the breaker cannot be reclosed because:

A
B
C
D