12.2 Worked Example: Four-Hazard Assessment

Key Takeaways

  • Walk a generic warehouse/office hybrid with four hazards from different categories: manual handling, trip (trailing cable), chemical solvent cleaning, and forklift/pedestrian interface.
  • For each hazard, score current L×C with existing controls, add ERICPD-aligned further controls, then re-score residual risk so the band improves for a credible reason.
  • Specific, auditable controls beat vague phrases such as “more training” or “be careful.”
  • Managers justify scores with short scenario logic (task frequency, exposure, energy/severity) rather than inventing zeros or political inflation.
  • Use this worked pattern on your real site: describe activity → who/how → existing → current rating → further controls → residual → review.
Last updated: August 2026

12.2 Worked Example: Four-Hazard Assessment

Quick Answer: On a small warehouse/office hybrid, assess four hazards from different categories — e.g. manual handling of a pallet load, a trailing cable trip, solvent cleaning, and a forklift/pedestrian interface. For each: state who is at risk, existing controls, current L×C, specific ERICPD-aligned further controls, residual L×C (lower), and a review date. Specific engineering and system controls outscore vague “more training.”

This section is a model answer pattern, not a copy-paste for your own site. Change the details to match your workplace. Markers credit realism. The thinking — categories, scores, residual drop, control quality — is what transfers.

Workplace context (introduction block)

Site: “Northbay Parts” — a small distribution unit with a packing warehouse and a mezzanine office (18 employees + occasional agency pickers and visiting drivers).

Scope of this assessment: goods-in / packing floor and shared vehicle aisle during normal day shifts. Assessor: packing team leader (Managing Safely candidate). Date: course week + 3 days.

Why this site works for practice: it naturally supports physical/handling, physical trip, chemical, and mechanical/transport hazards without inventing drama.

Hazard 1 — Manual handling of palletised cartons (physical / handling)

Description

During peak dispatch, operatives manually break down mixed pallets and lift 15–22 kg cartons from low pallet height to a packing bench for 2–3 hours per shift. Some cartons are bulky and block the view of the feet.

Who might be harmed and how

  • Permanent packing staff and agency pickers: musculoskeletal injury (back, shoulder) from lifting/twisting
  • New starters: higher likelihood due to unfamiliar technique and pace pressure
  • Pathway: lift → awkward twist while turning to the bench → acute strain or cumulative MSD

Existing controls

  • Basic induction mentions “lift with care”
  • One manual pallet truck available (not always used for short moves)
  • No formal TILE assessment for this peak task
  • No job rotation rule written down

Current risk (existing controls)

FactorScoreReasoning
Likelihood4 LikelyHigh frequency; awkward heights; production pressure; weak systematic control
Consequence3 ModerateCredible absence-level back/shoulder injury (could be higher for vulnerable individuals)
Current rating12Action band — improve within a set timescale

Further controls (ERICPD-aligned)

ControlERICPD levelWhy it helps
Introduce a scissor-lift pallet positioner so cartons are handled near waist heightReduce / Control (engineering)Lowers force and stooping → cuts likelihood
Redesign packing layout so the bench abuts the pallet face (less twisting)ReduceReduces hazardous movement
Written short SSoW: max individual carton weight policy; two-person rule above threshold; use of pallet truck mandatory for full stack movesControlStandardises safe method
TILE-based practical coaching + observed competence check within 10 working daysControlCompetence for residual handling
Job rotation every 60 minutes during peakControlLimits exposure time
Team leader weekly check that the positioner is used (not bypassed)DisciplineKeeps engineering control alive

Avoid relying on “send everyone on a video about lifting” as the only further control.

Residual risk

FactorScoreReasoning
Likelihood2 UnlikelyEngineering + layout + rotation make harm much less probable
Consequence3 ModerateIf a bad lift still occurs, harm can still be significant
Residual rating6Monitor band — maintain controls; review

Owner / timescale example: Operations supervisor to order positioner and implement SSoW within 4 weeks; interim two-person rule starts immediately.


Hazard 2 — Trailing power cable across walkway (physical / trip)

Description

A temporary packing printer is powered by an extension lead that crosses the marked pedestrian route between packing benches and the rest area. The cable is used daily and sometimes partially covered with gaffer tape.

Who might be harmed and how

  • Packers, supervisors, visitors, cleaners: trip and fall → sprain, fracture, head injury depending on fall
  • People carrying loads: higher severity if they cannot break the fall

Existing controls

  • Yellow/black hazard tape on part of the cable
  • Verbal reminders in toolbox talks
  • No fixed power point at the printer location

Current risk

FactorScoreReasoning
Likelihood4 LikelyCable on a busy route every day; tape is a weak control
Consequence3 ModerateForeseeable lost-time injury from a trip on a hard floor
Current rating12Action band

Further controls

ControlERICPD level
Eliminate temporary lead by installing a floor box / wall socket at the printer locationEliminate / Reduce of the trip hazard source
Until install: re-route cable overhead on a proper cable hanger or run inside a commercial cable protector ramp rated for the trafficIsolate / Control
Housekeeping standard: no taped cables on pedestrian routes; daily opening checkControl + Discipline
Remove unused temporary equipment after the shiftControl

“More training to watch where you walk” alone is a weak residual strategy when a socket move is reasonably practicable.

Residual risk

LCRBand
1 Very unlikely (after fixed socket)33Monitor / maintain

Interim with a proper cable ramp only: L2 × C3 = 6 still better than 12.


Hazard 3 — Solvent-based cleaning of metal jigs (chemical)

Description

Once per shift, a designated packer degreases small metal jigs at an open bench using a solvent cleaner poured from a 5 L can into an open tray. The area has general warehouse ventilation only. Nitrile gloves are sometimes available.

Who might be harmed and how

  • Task packer: skin irritation / dermatitis, dizziness from vapour, eye splash
  • Nearby workers: inhalation of vapour
  • Cleaners: contact with residues if spill not cleared
  • Pathway: pour/splash → skin/eye contact; evaporation → inhalation

Existing controls

  • Occasional use of generic disposable gloves
  • SDS somewhere in a filing cabinet (not at point of use)
  • No local exhaust; no eye protection rule enforced
  • Open tray storage overnight sometimes

Current risk

FactorScoreReasoning
Likelihood4 LikelyDaily open-tray use; weak PPE consistency; poor ventilation at source
Consequence3 ModerateDermatitis / significant irritation credible; worse if eye contact
Current rating12Action band

(If the solvent were highly toxic or used in bulk without any PPE, consequence could be scored higher — stay realistic to the product SDS.)

Further controls

ControlERICPD level
Substitute with a water-based or lower-hazard cleaner approved for the jigs (check performance first)Reduce (substitution)
If solvent still needed: enclosed parts washer or LEV booth for degreasingIsolate / Control
Decant into labelled small dispensers; bund tray; no open bulk pourControl
Point-of-use SDS summary, glove type specified, safety spectacles mandatory for pouringControl + PPE
Spill kit + trained response; store locked, labelled, away from ignition sourcesControl
Supervisor weekly check of glove stock and that substitution trial is followedDiscipline

Residual risk (after substitution + closed process)

LCR
2234–6

Likelihood falls sharply if the high-volatility solvent is removed or enclosed; consequence may fall if the substitute is milder.


Hazard 4 — Forklift and pedestrian shared aisle (mechanical / transport)

Description

Counterbalance FLT collects pallets from goods-in. The same aisle is used by pedestrians walking to the canteen and by visiting drivers on foot. Mirrors are missing at the corner. High-visibility vests are “encouraged.”

Who might be harmed and how

  • Pedestrians (staff, visitors, drivers): struck by / crushed by FLT — major injury or fatality possible
  • FLT operator: collision-related injury
  • Pathway: reverse or corner blind spot → contact with person

Existing controls

  • Trained FLT operators (certificates on file)
  • Site speed limit signed but not measured
  • Hi-vis “encouraged,” not enforced in this aisle
  • No physical segregation

Current risk

FactorScoreReasoning
Likelihood3 Fairly likelyShared route daily; blind corner; mixed pedestrians
Consequence5 CatastrophicVehicle/pedestrian contact can kill or permanently disable
Current rating15Urgent action band

High consequence is honest for workplace transport. Do not deflate C to make the form “look fine.”

Further controls

ControlERICPD level
Physical segregation: fixed pedestrian walkway with barrier on one side of the aisle; ban walking in the vehicle laneIsolate
One-way traffic plan; convex mirrors and zone lighting at the cornerControl
Time separation: no pedestrian transit during scheduled FLT goods-in window where practicableControl
Mandatory hi-vis in yard/aisle; banksman for reversing in tight spotsPPE + Control
Enforce speed with supervisor observation; disciplinary process for shortcuts through vehicle laneDiscipline
Reassess layout if volume grows — consider separate pedestrian door to canteenEliminate pedestrian exposure on that route

Residual risk

LCRNotes
2 Unlikely5 Catastrophic10Consequence often stays high (energy of FLT); likelihood must fall. Band still “action” — keep improving segregation and compliance.

This is an important teaching point: residual can remain significant when severity is inherent. Your job is to drive likelihood down with isolation and systems, not to pretend C becomes 1.


Summary scoreboard (manager view)

#HazardCategoryCurrent RResidual RPriority signal
1Manual handling cartonsPhysical / handling126Act, then monitor
2Trailing cablePhysical / trip123Fix socket — easy win
3Solvent cleaningChemical124–6Substitute / enclose
4FLT vs pedestriansMechanical / transport1510Urgent segregation

Resource order: treat the 15 transport risk first, then the three 12s by feasibility and speed of improvement (cable often fastest).

Scoring thinking managers use (and markers reward)

  1. Scenario first, numbers second — describe the hazardous event before picking L and C.
  2. Existing controls change L — do not score as if nothing is in place if training and guards already exist; do not credit paper controls that are unused.
  3. Consequence follows energy and harm type — vehicles, falls from height, and live electricity often keep high C.
  4. Residual must tell a story — each further control should map to a reason L or C moved.
  5. Specific beats vague — “install barrier along bay 3 by 30 June, owner: Site Lead” beats “improve awareness.”
  6. Review date — e.g. 12 months for this hybrid site, or 3 months for the FLT aisle until segregation is proven stable; earlier if any incident.

What not to do (exam project traps)

TrapFix
Four trip hazards onlyDiversify categories when the workplace allows
Residual identical to current after a long control listEither strengthen controls or re-score honestly
“More training” as the only control for high energy risksClimb ERICPD — isolate, engineer, redesign
Copying this warehouse example onto an office-only jobWrite hazards that match your introduction
Leaving owners and dates blankFill every administrative field the template shows

Transfer checklist for your real project

  1. Write a 5–8 line introduction for your site.
  2. Pick four hazards from different categories if possible.
  3. For each, draft who/how in one sentence.
  4. List only true existing controls.
  5. Score current L×C with a one-line reason each.
  6. Add 2–4 specific further controls with ERICPD labels in your notes.
  7. Re-score residual; prioritise the highest current ratings for action first.
  8. Set review date; submit inside the provider window.

Master this worked pattern and the project becomes a structured form, not a mystery — and the same habits make you a safer manager after the certificate is on the wall.

Test Your Knowledge

In the warehouse worked example, a forklift/pedestrian shared aisle is scored likelihood 3 and consequence 5 before further controls. What is the current risk rating and what does that band imply?

A
B
C
D
Test Your Knowledge

Which further control is strongest for a trailing cable that crosses a busy pedestrian route when a fixed power point can be installed?

A
B
C
D
Test Your Knowledge

Why might residual consequence for a forklift/pedestrian risk remain high (for example 5) even after good further controls?

A
B
C
D