6.6 Time & Work, Speed-Time-Distance, Simple & Compound Interest
Key Takeaways
Time and Work problems are solved using the LCM efficiency method, where Total Work equals and individual daily efficiencies are summed: .
The universal Chain Rule formula reconciles multi-parameter variations in personnel, daily operating hours, efficiency, and project output.
Speed conversions require multiplying by to obtain (and for ); average speed over equal distances equals .
Relative speed equals when two moving bodies travel in opposite directions and when traveling in the same direction; boats moving downstream have speed , and upstream .
Simple interest () accrues linearly, while compound interest () compounds exponentially; the difference between CI and SI for years is .
Time & Work, Speed-Time-Distance, Simple & Compound Interest
Quick Answer: Arithmetic aptitude in Paper 1 relies on structured algebraic formulas. Solve Time and Work via the LCM efficiency method (Total Work , Time ) and the Chain Rule: . For Speed-Time-Distance, convert , apply average speed , and combine train/platform lengths. For Interest, , , and the -year difference between CI and SI is .
1. Time and Work: The LCM / Efficiency Framework
While the unitary method solves work problems via fractions, the LCM (Total Work) Method avoids fractional addition, accelerating speed and accuracy.
The LCM Efficiency Method Steps
- Define Total Work: Let Total Work equal the of the individual completion times.
- Compute Individual Daily Efficiencies ():
- Combine Efficiencies: Add efficiencies for collaborative work; subtract efficiency for negative work (leaks/drainage).
- Calculate Time Taken:
| Worker | Time Taken () | Total Work (LCM) | Daily Efficiency () |
|---|---|---|---|
| Worker A | |||
| Worker B | |||
| Worker C | |||
| A + B + C Together | — |
Two-Worker Algebraic Shortcut
If takes days and takes days:
The Multi-Variable Chain Rule (Man-Days-Hours Formula)
To resolve scenarios involving changing workforce sizes, daily operating hours, differing efficiencies, and varied work quotas:
Pipes and Cisterns
- Inlet Pipe (): Fills tank Positive Efficiency ().
- Outlet / Drainage Pipe / Leak (): Empties tank Negative Efficiency ().
- Net Filling Rate: .
- If an inlet fills a tank in hours and an outlet empties it in hours ():
2. Speed, Time, and Distance Mastery
Unit Conversions and Basic Relations
Average Speed Formulations
- General Definition: .
- Equal Distance Traveled at Two Different Speeds ( and ):
- Equal Distance Traveled at Three Different Speeds ():
Relative Speed Principles
- Opposite Directions (Moving toward or away from each other):
- Same Direction (One pursuing the other):
Train Physics and Distance Rules
| Scenario | Distance Traversed () | Relative Speed () | Time Taken () |
|---|---|---|---|
| Train crossing stationary point (Pole/Tree/Man) | |||
| Train crossing Platform / Bridge / Tunnel | |||
| Two trains crossing in Opposite Directions | |||
| Two trains crossing in Same Direction |
Boats and Streams Vector Mechanics
Let the speed of a boat in still water be , and the speed of the water stream/current be :
- Downstream Speed (): Moving with the current: .
- Upstream Speed (): Moving against the current: .
- Speed of Boat in Still Water ():
- Speed of Stream / Current ():
3. Simple and Compound Interest Formulations
Simple Interest (SI)
Simple interest accrues linearly exclusively on the initial principal :
- Rule of Doubling in SI: If a sum of money doubles itself in years, then .
- Rule of -times in SI: If a sum becomes times itself in years, .
Compound Interest (CI)
Compound interest accrues on both the principal and previously accumulated interest:
Compounding Frequencies Adjustment Table
| Compounding Frequency | Effective Rate () | Number of Periods () | Amount Formula () |
|---|---|---|---|
| Annually | |||
| Semi-Annually (Half-Yearly) | |||
| Quarterly | |||
| Monthly |
Difference Between CI and SI Theorems
For a principal sum invested at annual rate :
- Difference for 2 Years ():
- Difference for 3 Years ():
- Worked Example: Find the difference between CI and SI on ₹ for years at per annum. The calculated difference is ₹.
A can complete a software research project in 12 days, and B can complete the same project in 18 days. They begin working together, but A leaves the project 2 days before its completion. What is the total number of days taken to complete the entire project?
8.4 days
7.2 days
9.6 days
10.0 days
A train 240 metres long is moving at a uniform speed of 72 km/h. How many seconds will it take for the train to completely cross a railway platform 360 metres in length?
25 seconds
30 seconds
20 seconds
35 seconds
A motorized survey boat travels 24 km downstream in 2 hours and covers the same distance upstream in 4 hours. What is the speed of the boat in still water and the speed of the river current?
Still water: 8 km/h, Current: 4 km/h
Still water: 10 km/h, Current: 2 km/h
Still water: 9 km/h, Current: 3 km/h
Still water: 7 km/h, Current: 5 km/h
The difference between the Compound Interest (compounded annually) and Simple Interest on a certain sum of money for 2 years at an annual interest rate of 10% is ₹150. What is the principal sum invested?
₹12,500
₹14,000
₹16,500
₹15,000
Sections you finish are checked off in the contents.