1.4 Plumbing System Testing Requirements
Key Takeaways
- DWV systems can be tested with a 10-foot head of water for 15 minutes or with air at 5 psi for 15 minutes.
- Water supply systems must be tested at working pressure with water, or with air at 50 psi for 15 minutes.
- Plastic water piping should not generally be tested with air due to the safety risk of fragmentation, depending on manufacturer specifications.
Before a plumbing system is concealed behind walls or under floors, and before it is put into final use, it must be rigorously tested to ensure it is watertight and gastight. The International Residential Code (IRC) Section P2503 mandates specific testing procedures for both the drainage, waste, and vent (DWV) system and the water supply system. As an inspector, verifying these tests is one of your most critical responsibilities.
Testing the Drainage, Waste, and Vent (DWV) System
The DWV system must be tested in two phases: the rough-in plumbing test and the final plumbing test. The rough-in test can be performed using either water or air.
Water Test (Rough-In)
The water test is the most common method for testing a DWV system.
- Procedure: The test is applied to the drainage system either in its entirety or in sections. If applied to the entire system, all openings in the piping must be tightly closed, except the highest opening, and the system is filled with water to the point of overflow.
- Testing in Sections: If the system is tested in sections, each opening is tightly plugged except the highest opening of the section under test. Each section must be filled with water, but no section shall be tested with less than a 10-foot head of water. This means the water level must be at least 10 feet above the lowest point being tested.
- Duration: The water must be kept in the system, or in the portion under test, for a minimum of 15 minutes before inspection starts. The system must then be tight at all points.
Air Test (Rough-In)
Alternatively, an air test can be used for the DWV system, except for piping systems constructed of materials that are not approved for air testing (such as certain plastics, depending on manufacturer and local amendments; though the base IRC allows air testing for plastic DWV, safety precautions are crucial).
- Procedure: All openings in the piping must be tightly closed, and air is introduced into the system.
- Pressure: The system must be forced to a uniform gauge pressure of 5 psi (34.5 kPa) or sufficient to balance a 10-foot column of mercury.
- Duration: This pressure must be held without introduction of additional air for a period of not less than 15 minutes.
Final Test
After the plumbing fixtures have been set and their traps filled with water, a final test is performed to ensure gastight and watertight connections. This is typically done using either the peppermint test or the smoke test.
- Peppermint Test: Introduce 2 ounces of oil of peppermint into the system. Add 10 quarts of hot water and seal all vent terminals. The odor of peppermint must not be detectable at any trap or other point in the system.
- Smoke Test: Introduce a pungent, thick smoke into the system. When smoke appears at vent terminals, they are sealed, and a pressure equivalent to a 1-inch water column is built and maintained for the period of the inspection.
Testing the Water Supply System
The water supply and distribution system operates under pressure, so it must be tested to withstand pressures greater than or equal to what it will experience in daily use.
Water Supply Testing Parameters (Section P2503.7)
Upon completion of a section of, or the entire water supply system, the system, or portion completed, must be tested and proved tight under a water pressure not less than the working pressure of the system.
- Working Pressure Test: The system is pressurized with water to the standard working pressure (typically 40 to 80 psi).
- Air Test Alternative: The system can also be tested with air. If air is used, the system must be pressurized to not less than 50 psi (344 kPa).
- Duration: For both water and air tests, the pressure must be held for not less than 15 minutes. The piping must not leak.
Plastic Water Piping
It is vital to note that while the code generally allows air testing, the testing of plastic water distribution piping (such as CPVC or PEX) with air is strictly prohibited by many manufacturers due to the risk of catastrophic failure and fragmentation if the pipe bursts under compressed air. Always verify manufacturer instructions, which supersede the general code allowance when they are more restrictive.
Inspection and Approval
The plumbing contractor must provide the equipment, material, and labor necessary for the tests. The inspector's role is to witness the test.
- The inspector must verify the test pressure gauge.
- The inspector must visually inspect all joints and connections for leaks during the test duration.
- Only after the system has successfully held the required pressure for the specified time (e.g., 15 minutes) without any evidence of leakage can the inspector approve the rough-in or final plumbing installation.
Failing to properly test these systems can result in devastating water damage, structural rot, or the escape of harmful sewer gases into the living space. Strict adherence to these testing parameters is non-negotiable for ensuring public health and safety.
When performing a rough-in water test on a DWV system in sections, what is the minimum required head of water?
If a rough-in air test is used for the DWV system, what uniform gauge pressure must be applied and held?
When testing a water supply system with air, what is the minimum required pressure and duration?