10.4 Local Fertilizer Ordinances, Blackouts & Pollinator Protection

Key Takeaways

  • Locate the city and county requirements for the service address.

  • In Pinellas County, verify the June 1 to September 30 nitrogen and phosphorus restriction, the 50% slow-release provision for granular nitrogen, and the 10-ft fertilizer-free zone.

  • A fertilizer-pesticide mixture has to meet both the applicable fertilizer restrictions and pesticide use directions.

  • Check blooms, bee activity and drift, then read the directions for the site on the exact pesticide label.

Last updated: November 2026

Local Fertilizer Ordinances & Pollinator Protection

Quick answer. Verify the rules at the address before selecting a product. Look for both nutrient restrictions and pesticide use directions. Plan for blooming plants and active pollinators before treating.

Locate the governing ordinance

Florida Statute 403.9337 encourages local adoption of the state model fertilizer ordinance. It requires local adoption at least at the model level for local governments within watersheds of waters listed as nutrient impaired under section 403.067, subject to the statute’s existing-ordinance provision. Additional or stricter standards under that provision require a documented science-based, economically and technically feasible program and consideration of relevant scientific information. Fertilizer use on defined farm operations and classified agricultural lands is outside section 403.9337. Verify that those settings actually apply before relying on the exception.

Example for an ordinary landscape in Pinellas County

SubjectCounty guidance
Seasonal timingDo not apply nitrogen or phosphorus to turf or landscape June 1 through September 30.
Granular nitrogenAt least 50% of the nitrogen is slow release. The County lists a per-application maximum of 1 lb N per 1,000 sq ft for this use.
PhosphorusDocument a deficiency by soil test before applying phosphorus.
Fertilizer-free zoneLeave 10 ft from the top of bank of surface water, the landward edge of a seawall, or the designated wetland.
WeatherCheck year-round local restrictions including advisories listed by the county and a forecast of at least 2 inches of rain within 24 hours.

Pinellas County is a local example. For every location, verify which city and county rules apply, any exemptions, and local limits on timing, permitted nutrients and rates. The statewide direction limits in the previous lesson also matter for the product. Measure the exact local setback reference point.

Check both requirements for a combination product

A product that combines fertilizer and pesticide is subject to applicable nutrient and pesticide requirements. Verify the exact use site, turf species, rate, PPE, environmental conditions, and credential and posting requirements. During a local nitrogen blackout that applies to the address, a nitrogen-containing weed-and-feed is prohibited. The dates on the herbicide portion do not create a fertilizer exception. A label-authorized pesticide-only option may be considered if monitoring and the other applicable restrictions support treatment.

Worked decision

A technician visits a covered Pinellas County lawn on July 15. A bag with a 20-0-8 grade supplies nitrogen even though the phosphate guarantee is zero. The local timing restriction precludes that application. The technician checks whether targeted weed management is needed and reviews product and site restrictions before selecting a lawful option.

Verify the exact pollinator directions

Check the label’s environmental hazards, the directions for the specific site, and any pollinator advisory referenced there. Inspect target plants and nearby drift-sensitive blooms, including flowering weeds in turf. Bee activity, flowering and drift can each affect whether an application is allowed.

The EPA-accepted Merit 2F label illustrates the importance of reading nonagricultural directions: it prohibits application while bees are foraging and prohibits application to flowering plants until flowering is complete and petals have fallen. Dusk alone does not satisfy the flowering condition. Check the wording for the use site and any separate directions on the container. The EPA-accepted Demand CS label also addresses direct treatment or drift to blooming crops or weeds where bees are visiting, with additional timing directions for flowering plants in the turf and ornamental portion.

Watch for routes of exposure through deposits on flowers and contact with spray or residues. Use application timing, equipment and placement permitted by labeling, and prevent drift to adjacent blooms. Where the directions cannot be met, defer the application or choose an appropriate alternative. Formulation abbreviations and mowing alone do not establish whether a product can be used safely at a flowering site.

Record which label directions and local timing rules informed the decision. That record is useful when the same crew serves a different municipality or conditions at the next visit change.

Sources

Test Your Knowledge

A planned July 15 application would put 24-0-11 on a lawn subject to the Pinellas County seasonal restriction, with no applicable exemption. Why must the application be postponed or changed?

A

July nitrogen applications are banned statewide by Rule 5E-1.003.

B

Pinellas requires a soil test for all fertilizers year-round.

C

The fertilizer contains potassium, which is always prohibited in July.

D

It contains nitrogen, which the County prohibits during its June 1 to September 30 restricted season.

Test Your Knowledge

A local nitrogen blackout applies to a homeowner’s lawn. The proposed weed-and-feed contains nitrogen and the herbicide directions otherwise cover the lawn. Which action is permitted?

A

Apply it because the federally approved directions take the place of the nutrient restriction.

B

Decline that combination application because the nutrient restriction and pesticide requirements both apply.

C

Apply it because the technician holds the limited commercial fertilizer certificate.

D

Apply it within a reduced area as long as no granules reach the street.

Test Your Knowledge

At a nonagricultural site, bees have stopped foraging but the target ornamental is still flowering. The selected Merit 2F directions forbid applying to flowering plants before petals have fallen. What is the correct decision?

A

Apply at dusk because bees have stopped foraging.

B

Apply a lower rate to open flowers.

C

Defer treatment until the flowering condition and the other label requirements can be met.

D

Spray the same open flowers with finer droplets.

Sections you finish are checked off in the contents.