11.2 Preheat, Interpass and Post-Heat Calculations for Cold-Crack Prevention
Key Takeaways
Preheat suppresses HICC by retarding the cooling rate through the 800°C to 500°C transformation window (delta t_8/5) to prevent hard martensite formation and by accelerating the solid-state effusion of diffusible hydrogen prior to cooling below 100°C.
Dehydrogenation Heat Treatment (DHT / post-heating) at 200°C to 300°C (400°F to 600°F) immediately following welding exponentially increases hydrogen diffusivity, safely outgassing hydrogen before the joint cools to room-temperature embrittlement ranges.
Post-heating holds a weld at a moderate temperature immediately after welding to let hydrogen diffuse out, and it is not the same operation as stress-relieving post-weld heat treatment.
Hydrogen cracking is delayed, so a weld that passes immediate inspection can crack hours or days later, which is why code hold times before inspection exist.
Removing any one of the four necessary conditions prevents cold cracking, and hydrogen level is usually the cheapest one to control.
Preheat, Interpass, and Post-Heating Engineering Calculations
Physical Mechanisms of Preheat
Preheat alters the welding thermal cycle through two distinct physical mechanisms:
- Cooling Rate Retardation: Reduces the cooling rate through the critical austenite decomposition window (800°C to 500°C, denoted delta t_8/5):
Extending delta t_8/5 promotes the transformation of austenite into benign, ductile ferrite-pearlite or upper bainite rather than hard, brittle martensite.delta t_8/5 is proportional to: Q_net / [2 * pi * k * (T_interpass - T_0)] - Hydrogen Effusion Acceleration: Extends the residence time between 300°C and 100°C, allowing mobile hydrogen atoms to diffuse out of the fusion zone and HAZ into the atmosphere before the steel cools to ambient temperatures where brittle cleavage occurs.
Preheat Calculation Frameworks
- AWS D1.1 Annex H (Method A - Susceptibility Index): Categorizes base metals into Susceptibility Groups (I, II, III) based on composition, combines this with Diffusible Hydrogen Level (H1, H2, H3), and cross-references joint restraint thickness to dictate minimum preheat and interpass temperatures.
- AWS D1.1 Annex H (Method B - Hardness Control Method): Uses Pcm to limit peak HAZ hardness below a specified maximum (HV_max <= 350 to 400 HV) based on critical cooling time:
T_preheat = 1600 * Pcm - 280 (in °C) - EN 1011-2 / BS 5135 Method: Uses combined thickness d_c (sum of all plate thicknesses meeting at the joint line), heat input Q (kJ/mm), carbon equivalent CET, and hydrogen scale to extract preheat from standardized nomograms:
CET = C + (Mn + Mo)/10 + (Cr + Cu)/20 + Ni/40
Dehydrogenation Heat Treatment (DHT / Hydrogen Bakeout)
If a thick, highly restrained weld cannot be maintained at preheat temperature until non-destructive examination or full post-weld heat treatment (PWHT), a Dehydrogenation Heat Treatment (DHT) must be applied immediately upon arc extinction:
- Parameters: Maintain the joint at 200°C to 300°C (400°F to 600°F) for a minimum soak time of 1 to 4 hours (typically 1 hour per 25 mm of joint thickness) prior to cooling below 100°C.
- Diffusion Kinetics: The diffusion coefficient of hydrogen in ferritic iron follows the Arrhenius relationship:
At 250°C, D_H is approximately 1.5 x 10^-5 cm^2/s, which is more than two orders of magnitude faster than at room temperature (20°C, D_H approx 1.2 x 10^-7 cm^2/s). The characteristic diffusion distance x approx 2 * sqrt(D_H * t) ensures that diffusible hydrogen effuses out of the joint before brittle room-temperature conditions are reached.D_H = D_0 * exp(-Q_d / (R * T))
Worked Numerical Example: Carbon Equivalency & Preheat Evaluation
Problem Statement
A welding engineer is qualifying a welding procedure specification (WPS) for a critical structural offshore column connection. The joint is a complete-joint-penetration (CJP) double-V groove butt weld joining 50.0 mm thick plates of thermo-mechanically controlled processed (TMCP) structural steel. The certified mill test report (CMTR) reveals the following ladle chemical composition (all values in weight percent):
- Carbon (C): 0.09%
- Manganese (Mn): 1.45%
- Silicon (Si): 0.28%
- Chromium (Cr): 0.06%
- Molybdenum (Mo): 0.18%
- Nickel (Ni): 0.35%
- Copper (Cu): 0.22%
- Vanadium (V): 0.04%
- Boron (B): 0.0012%
- Niobium (Nb): 0.03%
- Phosphorus (P): 0.010%
- Sulfur (S): 0.003%
Calculations Required:
- Calculate the International Institute of Welding Carbon Equivalent (CE_IIW).
- Calculate the Ito-Bessyo Cracking Parameter (Pcm).
- Determine which parameter (CE_IIW or Pcm) metallurgically governs this steel and justify your selection.
- Using the empirical Ito-Bessyo minimum preheat formulation for thick, highly restrained joints:
whereT_p (°C) = 1440 * P_c - 392P_c = Pcm + [H_diff]/60 + t/600, evaluate T_p for:- Condition 1: Shielded Metal Arc Welding (SMAW) using improperly stored basic electrodes with H_diff = 12 mL/100g.
- Condition 2: Flux-Cored Arc Welding (FCAW-G) using certified H4 consumables with H_diff = 3.5 mL/100g.
- Calculate the DHT soak duration at 250°C required for hydrogen to diffuse an effective diffusion distance x = 25 mm (2.5 cm), given D_H(250°C) = 1.6 x 10^-5 cm^2/s.
Step-by-Step Solution
Step 1: Calculate CE_IIW
CE_IIW = C + Mn/6 + (Cr + Mo + V)/5 + (Ni + Cu)/15
CE_IIW = 0.09 + 1.45/6 + (0.06 + 0.18 + 0.04)/5 + (0.35 + 0.22)/15
CE_IIW = 0.09 + 0.2417 + 0.28/5 + 0.57/15
CE_IIW = 0.09 + 0.2417 + 0.0560 + 0.0380 = 0.4257%
Step 2: Calculate Pcm
Pcm = C + Si/30 + (Mn + Cu + Cr)/20 + Ni/60 + Mo/15 + V/10 + 5*B
Pcm = 0.09 + 0.28/30 + (1.45 + 0.22 + 0.06)/20 + 0.35/60 + 0.18/15 + 0.04/10 + 5*(0.0012)
Pcm = 0.09 + 0.00933 + 1.73/20 + 0.00583 + 0.0120 + 0.0040 + 0.0060
Pcm = 0.09 + 0.00933 + 0.0865 + 0.00583 + 0.0120 + 0.0040 + 0.0060 = 0.2137%
Step 3: Metallurgical Parameter Selection The carbon concentration of this steel is C = 0.09%, which is substantially below the 0.18% threshold. Applying CE_IIW to low-carbon microalloyed/TMCP steels significantly overestimates the hardenability contribution of carbon and assigns excessive weight to alloying elements like manganese. Therefore, Pcm = 0.214% is the correct governing parameter for this steel.
Step 4: Calculate Minimum Preheat Temperature (T_p) Base plate thickness t = 50 mm. The thickness restraint term is:
t / 600 = 50 / 600 = 0.0833
-
Condition 1: High Hydrogen (H_diff = 12 mL/100g)
P_c1 = 0.2137 + 12/60 + 0.0833 = 0.2137 + 0.2000 + 0.0833 = 0.4970 T_p1 = 1440 * (0.4970) - 392 = 715.7 - 392 = 323.7°C approx 325°C (617°F)Engineering Assessment: Requiring a 325°C preheat is excessively high, commercially impractical, and risks degrading the fine-grained TMCP microstructure through over-tempering.
-
Condition 2: Certified Low Hydrogen (H_diff = 3.5 mL/100g)
P_c2 = 0.2137 + 3.5/60 + 0.0833 = 0.2137 + 0.0583 + 0.0833 = 0.3553 T_p2 = 1440 * (0.3553) - 392 = 511.6 - 392 = 119.6°C approx 120°C (248°F)Engineering Assessment: By switching from non-controlled electrodes to certified H4 consumables, the minimum required preheat drops by over 200°C (from 325°C down to 120°C), demonstrating the critical impact of diffusible hydrogen control on fabrication economics and joint integrity.
Step 5: Calculate Dehydrogenation Post-Heat Soak Time
Using the diffusion approximation x = 2 * sqrt(D_H * t):
t = x^2 / (4 * D_H) = (2.5 cm)^2 / [4 * (1.6 x 10^-5 cm^2/s)] = 6.25 / (6.4 x 10^-5) = 97,656 seconds
t = 97,656 / 3600 approx 27.1 hours (for single-surface effusion)
In standard industrial practice where hydrogen diffuses symmetrically across both top and bottom surfaces (maximum diffusion path length to nearest surface = t/2 = 25 mm = 1.25 cm):
t_sym = (1.25 cm)^2 / [4 * (1.6 x 10^-5 cm^2/s)] = 1.5625 / (6.4 x 10^-5) = 24,414 s approx 6.78 hours
Conclusion: Specifying an immediate post-heat soak (DHT) of 250°C for 4 to 6 hours reduces the residual diffusible hydrogen concentration in the mid-thickness below the critical cracking threshold (< 1.0 mL/100g).
Real-World Engineering Scenarios & Exam Pitfalls
Industrial Scenario: Delayed Toe Cracking in Heavy Mining Shovel Booms
A heavy equipment manufacturer fabricated mining excavator booms using 65 mm thick ASTM A514 Grade B (690 MPa minimum yield strength) quenched and tempered plates. Multipass flux-cored arc welding (FCAW-G) was performed with a preheat of 110°C. Visual and magnetic particle testing (MT) conducted 2 hours after weld completion showed complete compliance. However, after full structural blast cleaning and painting 72 hours later, 100% shear toe cracking was observed running parallel to the fusion boundary across multiple structural diaphragms.
Failure Investigation & Root Cause:
- NDE was conducted prematurely. For high-strength Q&T steels, AWS D1.1 Clause 8 mandates an inspection hold period of at least 48 hours post-weld.
- The FCAW wire coils were left mounted on wire feeders inside the unheated shop over a humid weekend, absorbing moisture into the seam and flux core, driving diffusible hydrogen levels from an initial H4 (3.2 mL/100g) to > 14 mL/100g.
- The preheat temperature of 110°C was inadequate for the high weld restraint and elevated hydrogen level.
Corrective Action: The fabricator instituted climate-controlled wire storage cabinets, increased preheat to 175°C, mandated an immediate dehydrogenation bakeout at 230°C for 2 hours post-weld, and enforced a strict 48-hour hold before final MT and ultrasonic examination.
Common Exam Traps
Exam Trap 1: Misapplying IIW CE to Modern Low-Carbon TMCP Steels Certification exam questions frequently present a steel with carbon content between 0.05% and 0.12% and ask which formula to use for preheat determination. Do not use CE_IIW for steels with carbon < 0.18%. CE_IIW was calibrated on 1940s-era normalized C-Mn steels; it grossly overestimates the preheat required for modern microalloyed steels. You must select the Ito-Bessyo Pcm formula.
Exam Trap 2: Preheat Only Retards Martensite Formation A widespread misconception is that preheating only serves to slow the cooling rate to avoid martensite. In high-strength steels, preheat's equally vital role is accelerating hydrogen effusion. At 150°C to 200°C, the diffusion rate of hydrogen is hundreds of times faster than at room temperature, allowing hydrogen to safely escape before the steel transforms to martensite and reaches room-temperature embrittlement ranges.
Exam Trap 3: Timing of HICC Formation If an exam question asks when hydrogen-induced cold cracking initiates, never select "during solidification" or "immediately upon arc extinguishment." HICC is delayed cracking occurring between -100°C and +200°C, typically hours or days after the joint has reached ambient temperature.
A welding engineer is evaluating the chemical composition of a modern thermo-mechanically controlled processed (TMCP) line pipe steel: 0.08% C, 1.60% Mn, 0.25% Si, 0.20% Ni, 0.15% Cr, 0.10% Mo, 0.04% V, and 0.001% B. Which carbon equivalent formulation is metallurgically appropriate for establishing the preheat requirements to prevent cold cracking, and why?
The IIW Carbon Equivalent formula, because its heavier weighting of manganese (Mn/6) is required for high-manganese pipeline grades.
The DeLong equivalent formula, because it specifically accounts for nitrogen-induced austenitic phase stabilization.
The Ito-Bessyo Pcm formula, because the carbon content is below 0.18%, where IIW CE overestimates hardenability and the cracking contribution of substitutional alloying elements.
The Schaeffler equivalent formula, because high-strength line pipe steels form mixed martensite-austenite constituent phases.
Sections you finish are checked off in the contents.