12.2 New-Home Warranties, Tarion and HCRA Licensing

Key Takeaways

  • Check the Home Construction Regulatory Authority directory for the actual entities on the agreement and confirm enrolment of the particular home separately with Tarion.

  • Identify the title and possession dates, record the condition at delivery, and use the current initial, mid-year, year-end, second-year and major structural defect processes as applicable.

  • The 45-day purchase notice applies to qualifying freehold agreements from April 1, 2026. The special-fund limit for late or missing notice applies to qualifying agreements from January 1, 2027.

  • Distinguish the pre-closing deposit protection for a freehold purchase, a condominium dwelling-unit purchase and a construction contract with a landowner.

  • Use the correct addendum and critical dates to determine compensation and termination rights. Calendar the builder and Tarion claim steps.

Last updated: November 2026

Check the builder, vendor and particular property

The Home Construction Regulatory Authority (HCRA) licenses Ontario new-home builders and vendors. Under the New Home Construction Licensing Act, 2017, s. 37, the applicable licence is required to carry on the regulated activity. Look up the actual contracting entities in the Ontario Builder Directory and review active status, conditions and disclosable history. Tarion administers the provincial warranty plan. Verify the home’s enrolment directly and request the addendum and warranty information for this transaction. A licence search and a home-specific enrolment check answer different questions. If either raises a problem, obtain confirmation of coverage before advising the buyer to proceed. Do not assume a seller’s failure to enrol decides whether a particular post-possession claim falls within the Act. Check the statutory definition and treatment of a home that should have been enrolled. A dwelling built and sold for temporary or seasonal occupancy is excluded from the Act’s definition of a home. Screen owner-managed construction and whether the client is commissioning a builder on their own land before applying the purchase-agreement rules. Licensing Act, s. 37, HCRA directory guidance and Ontario New Home Warranties Plan Act

Record the inspection and preserve claims

At the pre-delivery inspection, record incomplete work, visible damage and missing items. Keep dated photos, any written acceptance and the completed inspection form. Use the certificate of completion and possession to verify the start date. The inspection is evidence; report covered issues within the applicable separate warranty claim period. For a resale within a warranty period, verify the original date and remaining coverage and arrange to update Tarion’s records. The statutory vendor warranty can be enforced without contractual privity.

PeriodExamples of coverage and relevant authority
One yearWorkmanship, materials, fitness for habitation and Building Code compliance under s. 13(1)(a). Review statutory exclusions such as normal wear, owner-supplied work and surface defects specifically accepted in writing at possession.
Two yearsBasement or foundation water penetration under Reg. 892, s. 14. Section 15 covers specified envelope penetration, delivery and distribution defects in electrical, plumbing and heating systems, cladding defects and Building Code violations affecting health and safety. Appliances, fittings and fixtures are excluded from the defined delivery and distribution systems.
Seven yearsMajor structural defects. For newer homes, use the prescribed alternatives involving load-bearing failure, material impairment of load-bearing capacity or material impairment of ordinary residential use of a significant portion. Check exclusions and the claim period in Reg. 892.

For eligible individual homes with possession on or after May 1, 2024, Reg. 892, s. 4.5 sets a 40-day initial period beginning the day after possession, a mid-year period through day 183, and a year-end period through the first anniversary. A limited year-end grace period is available for items reported to the vendor in writing before the first anniversary using the established communication method. Verify submission and keep the confirmation. Use the second-year form for eligible claims during year two, and the major structural defect process for structural claims in the later period. Notify the builder, track repair and conciliation dates, and check Tarion’s applicable process for the home. For ordinarily covered condominium common elements, the corporation claims from the declaration and description registration date. Section 15 provides different treatment for phased, vacant-land and common-elements corporations. Plan Act, ss. 13 and 15, Reg. 892 and Tarion claim procedures

Protect funds before closing

Under Plan Act s. 14(1), guarantee-fund deposit relief is subject to the regulations and the statutory grounds. Examples include qualifying statutory rescission or failure to convey because the vendor went bankrupt or fundamentally breached the agreement. Verify payments, credits, refund rights and supporting evidence.

  • Qualifying freehold purchase. For the ordinary purchase cap from 2018, take the greater of $60,000 and the lesser of 10% of the price and $100,000. A cap does not create a claim for more than the eligible loss. Section 2.1 of Reg. 892 requires purchasers under qualifying agreements entered into from April 1, 2026 to give Tarion the specified information within 45 days. Use the portal or deliver the information in writing and preserve proof. The changed guarantee-fund and special-fund limits under ss. 4.9 and 6.1 are tied to agreements entered into from January 1, 2027. Late or missing notice for those agreements can put a claim in the special fund with a $15 million annual aggregate and pro rata reduction when claims exceed it. The special-fund limit does not apply to an agreement made in 2026 merely because a claim is filed later.
  • Condominium dwelling unit. Review the separate trust and permitted security routes under Condominium Act, 1998, s. 81. Reg. 892, s. 6(2) sets Tarion’s deposit cap at $20,000 plus prescribed interest on the net principal payable. Check trust evidence and available security rather than treating the Tarion limit as the protection for the entire deposit. The s. 2.1 purchase notice excludes units in a condominium project.
  • Construction contract on the client’s land. If the builder fails to substantially perform and the owner has the required cause of action, test the excess of the amount paid over work and materials received under Plan Act s. 14(2). For an ordinary qualifying modern contract, check the $40,000 cap under Reg. 892, s. 6(1)(b)(ii). Tarion purchase registration, Tarion pre-possession coverage and Condominium Act, s. 81

Review the addendum and delay compensation

Identify the correct addendum for the property type, agreement date, and firm or tentative schedule. Use the Statement of Critical Dates and contract notices to calculate the firm, delayed and outside dates and applicable termination period. In a qualifying delay, the standard freehold addendum can provide $150 per day for living expenses without receipts plus documented direct expenses, subject to a combined $7,500 cap. Screen any extension, unavoidable delay, notice failure or buyer default under the applicable addendum. Keep notices and receipts. For the ordinary freehold process, Tarion describes a builder claim within 180 days of closing or termination and, if unresolved, a Tarion submission within the first year of possession or within 365 days of termination. Check the separate occupancy addendum for a condominium. O. Reg. 165/08, Tarion freehold delay procedures and Tarion condominium delay procedures

Loading diagram...
Ontario new-home buyer checks
Test Your Knowledge

Eighteen months after first possession of a new Ontario freehold home, the owner documents water penetration through the foundation and a defect in the home’s electrical distribution wiring. There is no exclusion and the owner is ready to submit the form during the second year. Which route applies?

A

Only the expired first-year warranty can address these issues.

B

Both issues can be claimed under the second-year warranties.

C

A major structural defect must be established to claim any foundation seepage.

D

File the defect claim with HCRA as the builder’s licensing authority.

Test Your Knowledge

An Ontario freehold purchaser signed on June 1, 2026 and inadvertently gave Tarion the required purchase information on day 55. The price was $1,100,000, $140,000 was paid toward the price, and the vendor’s bankruptcy prevented conveyance. Assume no other recovery or exclusion and the claim otherwise qualifies. What limit applies?

A

The condominium guarantee-fund limit of $20,000.

B

The 2027 special-fund limit because the purchaser missed day 45.

C

The full $140,000 because the vendor went bankrupt.

D

The ordinary maximum of $100,000, although the purchaser missed the notice requirement.

Test Your Knowledge

A new freehold home closes 40 days after the firm date. The ordinary Tarion addendum applies, all required delay notices were timely, the delay qualifies for compensation, and the buyer has $1,200 in documented necessary storage and moving costs caused by the delay. How much is compensable on these facts?

A

$7,200.

B

$6,000.

C

$7,500.

D

$1,200.

Sections you finish are checked off in the contents.