12.3 Construction Liens, Holdback Release and Mortgage Priority
Key Takeaways
A payer retains 10% of the price as lienable work or materials are supplied. After the certified or declared date of substantial performance, the separate finishing holdback applies to the remaining supply.
For the annual release, identify the first applicable anniversary, publish Form 6 and measure the payment window from publication. Check the statutory lien exceptions and downstream payments.
Select the applicable section 31 trigger and distinguish early preservation from the last possible preservation day. That last day starts the 90-day perfection period under the current regime.
Separate building-finance holdback deficiency from the priority of later advances after notice or a preserved or perfected lien. The home buyer exception addresses specified mortgage priorities.
Identify the improvement and the applicable law
Under the Construction Act, s. 14, a person supplying services or materials for an owner, contractor or subcontractor to an improvement can have a lien for the price. Verify the relationship, actual supply and amounts owed. Capital repair may qualify under s. 1(1.1); routine work that merely prevents normal deterioration is different. The amount owed and the property or funds affected are separate questions under ss. 16–17 and 21.
Before calendaring, check ss. 87.3 and 87.4. The version in force on June 29, 2018 remains relevant to qualifying older contracts, procurement and certain leasehold cases, with specified exceptions. For covered improvements under the current regime, the annual holdback changes began January 1, 2026. Section 87.4(4) defers the new annual mechanism on an existing qualifying contract until the second anniversary of the contract date that falls after commencement. The first such release captures accrued holdback from before that anniversary. Check the separate prescribed project-agreement exception. Construction Act
Retain and release holdback in order
| Obligation | How to apply it |
|---|---|
| Basic holdback, s. 22(1) | Retain 10% of the price of services or materials as actually supplied under a lienable contract or subcontract, subject to statutory release and permitted retention forms. |
| Finishing holdback, ss. 22(2), 27 | When the contract is certified or declared substantially performed, retain a separate 10% of remaining services and materials as supplied from the certified or declared date. Segment the supply. The finishing amount becomes payable under s. 27 once the related liens are resolved as the statute specifies. |
| Written notice of a lien, s. 24 | Ordinary payments can proceed within the 90% rule unless written notice is received. To make protected payments thereafter, retain sufficient additional money for the notified lien and reduce the otherwise protected payment accordingly. Verify the notice form, amount and any effective withdrawal or court order. |
Under s. 26, the owner publishes the annual release notice on a construction trade news website using the prescribed Form 6 within 14 days after the applicable contract anniversary. The notice states the amount and intended date. Payment to the contractor is due 60 through 74 days after publication, unless a preserved or perfected lien and the unresolved circumstances in s. 26(4) prevent payment. An order vacating registration can matter even when the underlying dispute persists. The contractor and subsequent payers generally have 14 days from receipt to pay down the chain, subject to the equivalent restriction for each subcontract. When the impediment ends, s. 26(7) sets a 14-day period for the previously withheld payment. Section 26(8) governs holdback outside the annual payment rules. O. Reg. 303/18 and O. Reg. 304/18
Apply the transition. A covered contract was entered into February 10, 2025. Its first post-commencement anniversary was February 10, 2026. The second is February 10, 2027. The new annual procedure first applies to the latter and includes prior accrued holdback that falls within s. 87.4(4). Under the current Act, publication of the annual release notice is separate from the lien expiry triggers in s. 31.
Preserve, perfect and track the action
For supplies before or on the certified or declared date of substantial performance, s. 31 ordinarily measures 60 days from the earliest applicable event. For the contractor, check publication and contract completion, abandonment or termination. For a subcontractor or supplier, also check last supply and certification of subcontract completion. Where there is no certification or declaration, or for supply after the applicable substantial performance date, use the distinct lists in ss. 31(2)(b) and (3)(b). A later supply tranche does not extend the earlier lien under s. 31(4). For termination, ss. 31(6)–(7) require publication within seven days and use the first qualifying notice publication date for the termination trigger. Verify transition where notice predates the amendment.
Preserve by registering the claim if the lien attaches to land. If it does not attach, follow the delivery route in s. 34, including the prescribed Crown recipient, municipal clerk or railway office as applicable. Then s. 36 generally allows 90 days after the last day the lien could have been preserved. For an attached lien, commence the action and register the certificate of action unless registration has been vacated by order. A lien that does not attach is ordinarily perfected by commencing the action. Sheltering is a separate statutory route with limits. Calendar trial or setting down under s. 37, and check the time computation and office access before relying on the last day.
Calendar example. The earliest trigger for a private lien is publication on May 11, 2026 for completed supply. The 60th day is July 10. If the claimant preserved it June 1, the perfection date still runs from July 10, reaching October 8. A last-minute client should verify the applicable filing and registration deadlines rather than wait for that date. Construction Act, ss. 31–37 and Legislation Act, 2006, s. 89
Test priority and protect the conveyance
| Question | Section 78 analysis |
|---|---|
| Was the mortgage intended to finance the improvement, or taken to repay such a mortgage? | Section 78(2) gives liens priority to the extent of the owner’s required holdback deficiency, regardless of registration timing. |
| Was the mortgage registered, and the advance made, before the first lien arose? | Subject to s. 78(2), apply s. 78(3) to the lesser of the amount advanced and actual property value at the time the first lien arose. |
| Was the advance later, or the registration after the first lien arose? | Check ss. 78(4)–(6), including the distinct holdback deficiency issue for a subsequent mortgage. Test whether there was a preserved or perfected lien when the advance was made or qualifying written notice had already been received. A later parcel entry does not cancel earlier written notice. |
| Is it a home buyer’s mortgage? | Test the definition in s. 1(1). At most 30% can have been paid before conveyance excluding specified condominium trust money, and conveyance must wait until the home is ready for occupancy. For a new home, obtain the statutory evidence. Section 78(11) disapplies ss. 78(2) and (5) for a mortgage given or assumed by a qualifying home buyer. |
Holdback deficiency is fact-specific. In KingSett Mortgage Corporation v. Mapleview Developments Ltd., the Ontario Court of Appeal held that where no subcontractor lien claims remained at the time of the dispute, fully paid contractor invoices were not included in the deficiency under s. 78(2). In that setting, with $300,000 in wholly unpaid qualifying invoices and no retained holdback referable to them, the deficiency is $30,000, not 10% of the entire contract price. Owner holdback duties and the extent of the priority remedy require separate analysis. KingSett, 2026 ONCA 512, paras. 51–53, 71
For a purchase or refinance, ask about recent work and direct notice, obtain dates and payment or discharge evidence, search for registrations, and examine the terms and limits of any insurance or contractual holdback. Title insurance terms vary. Actual notice of unpaid work calls for an evidence-based cure or client decision before funds move. A standard percentage does not necessarily resolve the claim. Construction Act, ss. 39, 41, 44 and 78
For a private current-regime improvement, the earliest section 31 trigger for the subcontractor’s certified pre-completion supply is publication on May 11, 2026. The subcontractor registers the claim June 1. No exception or sheltering applies. Leaving aside office hours, what is the final calendar day to perfect?
August 30, measured from actual registration.
August 9, measured directly from publication.
October 8, measured 90 days after the final preservation day.
July 10, because both steps must occur within 60 days.
A commercial acquisition mortgage was registered before any construction lien arose. The lender advanced $500,000 before the first lien, when the property was worth at least that much. This is not a building mortgage. The lender later receives a valid written notice of lien on June 1, then makes a $200,000 advance on June 5. The notified lien is preserved June 15. How do the advances rank against it?
Both advances rank first because the claim was not registered by June 5.
The initial advance retains priority. The notified lien ranks ahead of the June 5 advance to the extent of the lien.
The lien ranks ahead of both advances because the later advance followed written notice.
The later advance ranks first unless the claimant obtained an injunction before funding.
New Ontario townhome buyers paid 15% before conveyance and took title once ready for occupancy, evidenced by the required municipal permit. They grant their own purchase mortgage. A supplier invokes the developer’s holdback deficiency and claims priority under sections 78(2) and (5). Which answer addresses those provisions?
They do not apply to this mortgage because it was granted by qualifying home buyers.
Both apply against the buyers’ mortgage to the extent of 10% of their purchase price.
The buyers become the developer’s defaulting payer through registration.
The buyers need a separate purchase filing with HCRA to obtain section 78(11) protection.